BLD-Final | 7/13/2017 | 7/14/2017 | 7/14/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 7/14/2017 | 7/14/2017 | 7/14/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 5/2/2017 | 5/2/2017 | 5/2/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Framing/Rough-in | 5/2/2017 | 5/2/2017 | 5/2/2017 | A | PASS |
Brandon Shaw
|
|
|
Re inspect Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Framing/Rough-in | 4/28/2017 | 4/28/2017 | 4/28/2017 | A | PART |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen See correction notice
|
BLD-Wall cover | 4/7/2017 | 4/7/2017 | 4/7/2017 | P | PASS |
Jim Storey
|
|
|
REQUESTING A PM SHEER INSPECTION PLEASE. PLEASE CALL JOSH WITH ANY QUESTIONS. ###-####. THANK YOU Phone #: ###-#### Inspection requested via web by Joshua Edwards exterior ok to cover
|
BLD-Wall Bracing | 4/6/2017 | 4/7/2017 | 4/7/2017 | A | FAIL |
Mike Jordan
|
|
|
Shear inspection Inspection requested via web by Erby Gonzales. No city plans.
|
BLD-Foundation | 3/7/2017 | 3/7/2017 | 3/7/2017 | P | PASS |
Jim Storey
|
|
|
Sergio Phone #: ###-#### footting
|
BLD-Footing | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | PASS |
Jim Storey
|
|
|
Sergio Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 2/23/2017 | | DONE |
|
|
|
Plan Mod
|
(F) Reprint permit | | | 2/23/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 2/22/2017 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/22/2017 | | |
|
|
|
plan modification, 1 hr admin. fee for building review
|
Permit Ready to Issue | | | 2/22/2017 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 2/14/2017 | | 2/22/2017 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 2/16/2017 | | 2/22/2017 | | PASS |
Tisha Gallop
|
|
|
flipped house on lot
|
Routing - PLANNING | 2/16/2017 | | 2/21/2017 | | PASS |
Nicolette Womack
|
|
|
Driveway width shall not exceed 33' within the front yard setback.
|
Routing - MECHANICAL | 2/16/2017 | | 2/17/2017 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 2/14/2017 | | DONE |
Christina Prado
|
|
|
requesting to flip lot
|
Issue PAID IN FULL permit | | | 1/17/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 12/28/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 12/28/2016 | 12/28/2016 | 12/28/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 12/28/2016 | | 12/28/2016 | | PASS |
Brian McGowan
|
|
|
Reviewed the resubmittal for Tisha 12-28-16
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/28/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 12/28/2016 | | DONE |
|
|
|
All Met
|
Plan assigned to (LEG) Tisha | 11/9/2016 | | 12/28/2016 | | DEFR |
Tisha Gallop
|
|
|
1st review 11/22; plan check (wall bracing/tall wall)
|
Routing - PLAN CHECK | 11/9/2016 | | 11/22/2016 | | FAIL |
Tisha Gallop
|
|
|
|
1st review completed | | | 11/22/2016 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 11/9/2016 | | 11/16/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 11/9/2016 | | 11/9/2016 | | PASS |
Nicolette Womack
|
|
|
Driveway width shall not exceed 33' within the front yard setback.
|
Routing - Addressing | 11/9/2016 | | 11/9/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/9/2016 | | 11/9/2016 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/9/2016 | | DONE |
|
|
|
|
Intake Approval | | | 11/9/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/9/2016 | | DONE |
|
|
|
|
Application received | | | 11/4/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 4 2016 11:48AM
|