Second Notice | | 5/20/2017 | 6/12/2017 | | DONE |
|
|
|
Mailed 6-13-17
|
First Notice | 4/21/2017 | 4/21/2017 | 5/10/2017 | | DONE |
Jim Sly
|
|
|
Mailed 5-11
|
BLD-Final | 4/20/2017 | 4/21/2017 | 4/21/2017 | A | PASS |
Jim Sly
|
|
|
Jeff Phone #: ###-####
|
DOC - Permit Finaled | 4/21/2017 | 4/21/2017 | 4/21/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 4/19/2017 | 4/20/2017 | 4/20/2017 | A | NR |
Jim Sly
|
|
|
Jeff Phone #: ###-#### Need Approved plans on site. called Jeff......need to fix Gap in floor next to new door.
|
FIRE-Final Inspection | 4/19/2017 | 4/19/2017 | 4/19/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 4/18/2017 | 4/19/2017 | 4/19/2017 | A | PEND |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Needs fire/life/safety final.
|
Issue PAID IN FULL permit | | | 3/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 3/10/2017 | 3/10/2017 | 3/17/2017 | | PASS |
Javier Guzman
|
|
|
3/23 L2 Outside Patio
|
Routing - PLAN CHECK | 3/10/2017 | | 3/17/2017 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 3/17/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/17/2017 | | DONE |
Christina Prado
|
|
|
Applicant is GC - need form only to confirm, fees added based on app. value
|
Routing - Design Review | 3/17/2017 | | 3/17/2017 | | PASS |
Katelyn Menuge
|
|
|
Gate location change okay. 3-17-17
|
Routing - PLAN CHECK | 3/17/2017 | | 3/17/2017 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 3/17/2017 | | DONE |
|
|
|
Need GC Form
|
Routing - Design Review | 3/10/2017 | | 3/16/2017 | | PASS |
Katelyn Menuge
|
|
|
signed off in ePlan by DR Katelyn Menuge
|
Routing - Erosion and Sediment | 3/10/2017 | | 3/13/2017 | | PASS |
Andy J. Long
|
|
|
No earth work involved. Contain and dispose of any concrete waste & washout. No other comments or permit required.
|
Routing - FIRE | 3/10/2017 | 3/10/2017 | 3/10/2017 | | PASS |
Katie Marron
|
|
|
No comments required.
|
Routing - Addressing | 3/10/2017 | | 3/10/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/10/2017 | | 3/10/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 3/10/2017 | | PASS |
David Ferguson
|
|
|
|
Intake Approval | | | 3/8/2017 | | FAIL |
David Ferguson
|
|
|
1) A structural analysis on installing the new store front door and cutting out the bottom of the windows.
2) Need the code analysis to include type of construction, occupant load, etc.)
|
Intake Approval | | | 11/17/2016 | | FAIL |
David Ferguson
|
|
|
Need completed #518 checklist, #304 form, and a Zoning Certificate from Planning.
|
Application received | | | 11/7/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 7 2016 1:17PM
|