Third Notice | | 9/15/2018 | 10/12/2018 | | DONE |
|
|
|
mailed 10-15-18
|
Second Follow up | | | 10/12/2018 | | DONE |
|
|
|
|
Third Notice | | 8/13/2018 | 9/10/2018 | | DONE |
|
|
|
mailed 9-11-18 sent letter
|
First Follow up | | | 9/10/2018 | | DONE |
|
|
|
|
Third Notice | | 7/15/2018 | 8/8/2018 | | DONE |
|
|
|
mailed 8-10-18
|
Third Notice | | 6/16/2018 | 7/10/2018 | | DONE |
|
|
|
mailed 7-11-18
|
Second Notice | | 5/20/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
First Notice | | 4/15/2018 | 5/10/2018 | | DONE |
|
|
|
mailed 5-11-18
|
Print Occupancy Form | | | 4/5/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 4/5/2018 | | DONE |
|
|
|
|
BLD-Final | 4/3/2018 | 4/4/2018 | 4/4/2018 | A | PASS |
Jim Sly
|
|
|
Perm C of O Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Final | 4/2/2018 | 4/2/2018 | 4/3/2018 | P | PART |
Jim Sly
|
|
|
Late afternoon if possible Phone #: ###-#### Inspection requested via web by Chris Palmer OK for Temp. Occ. OK for Perm. Occ. when Plumbing finals.
|
Temporary Occupancy | 4/3/2018 | 7/2/2018 | 4/3/2018 | | DONE |
Christina Prado
|
|
|
|
PubWorks Occupancy Approval | 4/3/2018 | 4/3/2018 | 4/3/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | CANC |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
|
Zoning Approval | 3/27/2018 | 3/27/2018 | 3/27/2018 | | DONE |
Leon Letson
|
|
|
|
BLD-Final | 3/16/2018 | 3/16/2018 | 3/16/2018 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits finaled, Need city approved plans and small documents. No testing was performed.
Please coordinate with sprinkler and alarm. Thanks Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Conference | 3/8/2018 | 3/9/2018 | 3/9/2018 | A | DONE |
Jim Sly
|
|
|
Pre-final/CofO Conference Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Ceiling Grid Inspection | 1/11/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Jim Sly
|
|
|
Admin Bldg. Please coordinate with electrical inspection scheduled for pm. Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Energy code compliance | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer Interior sound batts
|
BLD-Energy code compliance | 11/7/2017 | 11/7/2017 | 11/7/2017 | P | PASS |
Jim Sly
|
|
|
Exterior walls foam insulation in the Admin Bldg. Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | PASS |
Jim Sly
|
|
|
Dave Phone #: ###-####
|
BLD-Other | 6/28/2017 | 6/29/2017 | 6/29/2017 | P | PART |
Jim Sly
|
|
|
insp for reinforcement for slab on grade for admin classroom building // Justin Rueb Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 6/22/2017 | 6/26/2017 | 6/26/2017 | P | PART |
Mike Jordan
|
|
|
reinforcing for slab on grade // Dave Perkins Phone #: ###-####. Ok, pending special inspection.
|
BLD-Wall Bracing | 6/5/2017 | 6/6/2017 | 6/7/2017 | P | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### Should be Concrete.......MTI on site.
|
Issue PAID IN FULL permit | | | 3/28/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 3/28/2017 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JG) | 11/26/2016 | 11/26/2016 | 1/11/2017 | | PASS |
Javier Guzman
|
|
|
1st review completed, BOISE FIRE DEPT. - ADMIN/CLASSROOM BUILDING #1
|
Routing - PLAN CHECK | 12/29/2016 | | 1/11/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 12/29/2016 | | 1/11/2017 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by Stapley Engineering Jan Welch
|
Routing PW Drainage | 12/29/2016 | | 1/11/2017 | | PASS |
Brian Murphy
|
|
|
signed off in ePlan by PW Drainage Brian Murphy
|
Routing PW Sewer Design | 1/11/2017 | | 1/11/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/11/2017 | | DONE |
|
|
|
need ACHD, GC and Rev Cert of Val
|
Routing PW Sewer Design | 12/29/2016 | | 1/3/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Currently under PW review.
|
Route to Impact Fee Review | 12/13/2016 | 12/16/2016 | 12/15/2016 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 12/13/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 11/26/2016 | | 12/13/2016 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by Stapley Engineering Jan Welch
|
Routing PW Environmental | 11/28/2016 | | 12/9/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Drainage | 11/28/2016 | | 12/7/2016 | | FAIL |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 11/26/2016 | | 12/2/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 11/26/2016 | 11/26/2016 | 11/29/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - PLANNING | 11/26/2016 | | 11/29/2016 | | PASS |
Leon Letson
|
|
|
|
Routing - PLANNING Land Div | 11/26/2016 | | 11/29/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 11/26/2016 | | 11/28/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/26/2016 | | 11/28/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 11/26/2016 | | 11/28/2016 | | PASS |
Andy J. Long
|
|
|
no seperate ESC permit required, ESC plan & site SWPPP submitted and covered with GRD-00084 & ESC16-01512
|
Routing - MECHANICAL | 11/26/2016 | | 11/28/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 11/26/2016 | | 11/28/2016 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing PW Sewer Design | 11/28/2016 | | 11/28/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Add note: Contact Boise Public Works 48 hours prior to manhole work to obtain tap permit and schedule inspection.
Change manhole label from 589F1 to a number unrelated to the Boise Sewer manholes nearby (to avoid confusion). Public ownership of the sewer main will cease at manhole 589F.
|
Routing PW Solid Waste | 11/28/2016 | | 11/28/2016 | | PASS |
Evan Carpenter
|
|
|
Solid waste is OK as planned.
|
Intake Approval | | | 11/23/2016 | | PASS |
|
|
|
|
Intake Approval | | | 11/18/2016 | | FAIL |
David Ferguson
|
|
|
Remove "Not for construction" from plans and make sure that all plan sheets are stamped, signed and dated.
|
Application received | | | 11/7/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 7 2016 2:18PM
|