BLD-Final | 8/29/2017 | 8/30/2017 | 8/30/2017 | A | PASS |
Tony Young
|
|
|
David Phone #: ###-####
|
DOC - Permit Finaled | 8/30/2017 | 8/30/2017 | 8/30/2017 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 8/29/2017 | 8/29/2017 | 8/29/2017 | P | PART |
Tony Young
|
|
|
David Phone #: ###-####,, ok after trades
|
Zoning Approval | 8/28/2017 | 8/28/2017 | 8/28/2017 | | PASS |
Sarah Schafer
|
|
|
|
BLD-Energy code compliance | 5/10/2017 | 5/11/2017 | 5/11/2017 | A | PASS |
Dave Hannah
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 5/4/2017 | 5/4/2017 | 5/4/2017 | P | PART |
Tony Young
|
|
|
David Hale Phone #: ###-####,, need headers in basement,, strap plates,, hangers on stair landing joists,, ok to insulate
|
BLD-Footing | 4/3/2017 | 4/3/2017 | 4/3/2017 | P | PASS |
Jim Sly
|
|
|
Brandon Phone #: ###-####
|
BLD-Footing | 2/28/2017 | 3/1/2017 | 3/1/2017 | A | PART |
Mike Jordan
|
|
|
Brandon Phone #: ###-####. footing/stem wall for back patio frost wall. Mono placement
|
BLD-Foundation | 2/23/2017 | 2/23/2017 | 2/24/2017 | P | PASS |
Dave Hannah
|
|
|
Brandon-wall Phone #: ###-#### front porch
|
BLD-Footing | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | PART |
Tony Young
|
|
|
Brandon Phone #: ###-####,, front porch footings ok
|
BLD-Foundation | 2/7/2017 | 2/8/2017 | 2/8/2017 | A | PASS |
Dave Hannah
|
|
|
Brandon Phone #: ###-####
|
BLD-Footing | 1/26/2017 | 1/26/2017 | 1/26/2017 | P | PASS |
Jim Sly
|
|
|
Brandon Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/12/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/5/2016 | | DONE |
|
|
|
|
Telephone call | | | 12/5/2016 | | DONE |
|
|
|
Left a message for David informing him that the fees have changed due to the value and sqft went up (per Tisha)
|
Case Summary (BLD) | | | 12/3/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/29/2016 | | 12/2/2016 | | PASS |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 12/2/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/2/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/2/2016 | | DONE |
|
|
|
BLD16-04116 needs to be finaled-once demo is complete attach ESC to New SFD
|
Inspection Record Card- Bld | | | 12/2/2016 | | DONE |
|
|
|
|
Telephone call | | | 12/2/2016 | | DONE |
|
|
|
called Hale Dev to let know permit is ready-let him know the demo permit needs to be finaled before they pick this permit up. Also we need to attach the ESC permit to this one once the demo is complete
|
Plan assigned to (LEG) Tisha | 11/10/2016 | | 12/2/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 11/23; plan check
|
Plan resubmittals received | | | 11/29/2016 | | DONE |
|
|
|
received (2) sets of revised plans
|
1st review completed | | | 11/23/2016 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 11/18/2016 | | 11/23/2016 | | FAIL |
Tisha Gallop
|
|
|
e-mailed applicant on 11/23
|
Routing - MECHANICAL | 11/15/2016 | | 11/18/2016 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 11/10/2016 | 11/13/2016 | 11/17/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 11/14/2016 | | 11/15/2016 | | PASS |
Ted Vanegas
|
|
|
|
Routing - Addressing | 11/10/2016 | | 11/14/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/10/2016 | | 11/14/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/10/2016 | | DONE |
|
|
|
|
Intake Approval | | | 11/10/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/10/2016 | | DONE |
|
|
|
|
Application received | | 11/10/2016 | | | |
|
|
|
|