DOC - Permit Finaled | | | 3/1/2017 | | DONE |
|
|
|
as per Steve-no more inspections are going to be called on this permit-he wants it closed-couldn't get a hold of Harrison Renovation PLM16-04627-they still have fees due and need to have another inspection before plm permit can be finaled-i attached it to BLD17-00212 so we could close this permit
|
BLD-Foundation | 1/12/2017 | 1/12/2017 | 1/12/2017 | P | PASS |
Phil Shearer
|
|
|
trent - pouring at 1 Phone #: ###-####
|
BLD-Foundation | 12/28/2016 | 12/29/2016 | 12/29/2016 | A | PART |
Tony Young
|
|
|
Pouring at 10 // Trent Phone #: ###-####,, basement retaining wall footings,, work in progress,, ok
|
Issue PAID IN FULL permit | | | 11/21/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/18/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 11/18/2016 | 11/18/2016 | 11/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/18/2016 | | 11/18/2016 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 11/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 11/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 11/18/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/18/2016 | | DONE |
|
|
|
MET
|
Telephone call | | | 11/18/2016 | | DONE |
|
|
|
called Steven to let know permit is ready and let him know the fees
|
Plan resubmittals received | | | 11/18/2016 | | DONE |
|
|
|
received (2) sets of resubmittals of calculations
|
Routing Walk-In (Zoning) | 11/16/2016 | 11/16/2016 | 11/16/2016 | P | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 11/16/2016 | 11/16/2016 | 11/16/2016 | P | FAIL |
Brian McGowan
|
|
|
Need section/detail showing beam and structure at window wells.
I took in the plans and he will email or bring in the information needed.
|
1st review completed | | | 11/16/2016 | | FAIL |
Brian McGowan
|
|
|
Need section/detail showing beam and structure at window wells.
|
Routing - PLAN CHECK | 11/16/2016 | | 11/16/2016 | | FAIL |
Brian McGowan
|
|
|
Need section/detail showing beam and structure at window wells.
|
Routing Walk-In (BLD) | 11/15/2016 | 11/15/2016 | 11/15/2016 | A | FAIL |
Brian McGowan
|
|
|
Had no foundation plan, sections or structure to submit. No reports for the ICF wall he is proposing to use.
|
Application received | | 11/15/2016 | | | |
|
|
|
|