First Notice | 11/8/2018 | 11/8/2018 | 11/8/2018 | | DONE |
Mike Jordan
|
|
|
This permit finaled on the web by Stephen Lee
|
BLD-Final | 11/5/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Mike Jordan
|
|
|
Please call me when you''re expected to be on site and I will meet you there. Phone #: ###-#### Inspection requested via web by Stephen Lee
|
DOC - Permit Finaled | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Mike Jordan
|
|
|
All issues have been resolved. ok for final.
|
BLD-Conference | 10/31/2018 | 10/31/2018 | 10/31/2018 | P | PASS |
Mike Jordan
|
|
|
Review of fire shaft and first layer of fire rated gypsum board. Work commences at 8:30, please call if you have time earlier to stop by. If first layer is installed, will call to have you come by an inspect. Phone #: ###-#### Inspection requested via web by Stephen Lee
|
BLD-Conference | 9/29/2018 | 10/1/2018 | 10/1/2018 | A | PASS |
Mike Jordan
|
|
|
Please call prior to arrival, I will meet you onsite. Earlier in the AM preferred. Phone #: ###-#### Inspection requested via web by Stephen Lee. Angle supports added per plan and noted special inspection reports. Ok to fire proof new supports.
|
BLD-Conference | 9/27/2018 | 9/28/2018 | 9/28/2018 | P | CANC |
Mike Jordan
|
|
|
Please call prior to arrival and I will meet you onsite. This conference is for you to inspect the structural bracing that was just installed on 09/26/2018. Phone #: ###-#### >> Inspection requested via web by Stephen Lee Inspection cancelled from web by: Stephen Lee
|
BLD-Conference | 7/11/2018 | 7/12/2018 | 7/12/2018 | P | DONE |
Mike Jordan
|
|
|
afternoon between 1:45 and 3:45 for review of fire shaft correction notice. Please call me before you plan on going out so I can meet you there. Phone #: ###-#### Inspection requested via web by Stephen Lee. Discussed repairs with contractor and their proposed solutions prior to moving foward.
|
BLD-Conference | 7/10/2018 | 7/11/2018 | 7/11/2018 | P | CANC |
Mike Jordan
|
|
|
Reschedule for tomorrow afternoon between 1:45 and 3:45 for review of fire shaft correction notice. Please call me before you plan on going out so I can meet you there. Phone #: ###-#### Inspection requested via web by Stephen Lee. rescheduled for tomorow afternoon.
|
BLD-Conference | 7/10/2018 | 7/11/2018 | 7/10/2018 | A | CANC |
Mike Jordan
|
|
|
Please call Stephen prior to heading over, I will meet you onsite. The site is available to meet between 8:45 am to 10:45 am. in the morning, if those times do not work for your schedule then we have another window between 1:45 to 3:45 in the afternoon. This is to review the fire shaft correction notice. Phone #: ###-#### >> Inspection requested via web by Stephen Lee Inspection cancelled from web by: Stephen Lee
|
BLD-Final | 5/6/2018 | 5/9/2018 | 5/9/2018 | A | FAIL |
Mike Jordan
|
|
|
Please contact Stephen Lee when on your way, I will meet you there. Phone #: ###-#### Inspection requested via web by Stephen Lee. Provide the UL for the double wall grease duct from captive air showing 1hr. assembly and fireblock detail at penetrations. Make up air duct needs to be wrapped or in 1hr shaft for entire length. Provide UL and method for wrapping make up air duct and firestop details at penetrationns. Install all structural components as shown on Sheet A1-1.. Provide special inspection for epoxt bolting. correction notice issued.
|
FIRE-Final Inspection | 5/2/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
call on your way- Steve Phone #: ###-####
|
Extend Review Timeline | | | 12/12/2017 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Plan assigned to (CJW) | 12/1/2016 | 12/1/2016 | 12/14/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) (Dec. 21 - 15 days) (5 sheets) Valley View Senior Living
|
Routing - PLAN CHECK | 12/13/2016 | | 12/14/2016 | | PASS |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 12/14/2016 | | 12/14/2016 | | PASS |
Carl Westfall
|
|
|
The detail at the roof is the same as the previously approved detail for the floor. Since the only comment from the Consultant Structural Engineer was that the structural detail be placed on the drawings, the plan was not sent back to the Consultant to review the roof.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/14/2016 | | DONE |
|
|
|
all requirements met
|
Issue PAID IN FULL permit | | | 12/14/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/14/2016 | | DONE |
|
|
|
|
1st review completed | | | 12/13/2016 | | DONE |
|
|
|
The Owner is in a crisis and needed this project to be reviewed. It likely should have been routed to Environmental and CDHD the 1st time but was not. Approval from CDHD is a contitional of permit issuance. If Environmental had concerns they may need to be resolved after permit issuance. CJW
|
Plan resubmittals requested | | | 12/13/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/13/2016 | | DONE |
|
|
|
Submitted 25 seconds before midnight
|
Routing - PLAN CHECK | 12/1/2016 | | 12/13/2016 | | FAIL |
Carl Westfall
|
|
|
1st review done
|
Routing - MECHANICAL | 12/1/2016 | | 12/7/2016 | | PASS |
Troy James
|
|
|
|
Routing Off Site - STRUCTURAL | 12/1/2016 | | 12/6/2016 | | FAIL |
Carl Westfall
|
|
|
Keith Jones
|
Routing - FIRE | 12/1/2016 | 12/1/2016 | 12/2/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case
|
Intake Approval | | | 12/1/2016 | | PASS |
David Ferguson
|
|
|
|
Routing - Addressing | 12/1/2016 | | 12/1/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/1/2016 | | 12/1/2016 | | PASS |
Rachael Beierle
|
|
|
WEST BOISE SEWER DISTRICT
|
Application received | | | 11/17/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 17 2016 4:37PM
|
Routing PW Environmental | | | | | CANC |
|
|
|
Is a grease trap required? PW did not route it to PW Environmental the 1st time.
|
Routing Off Site - C.D.H | | | | | CANC |
|
|
|
Was not routed to CDHD the 1st time. Evidently this facility is not regulated by CDHD.
|