BLD-Wall cover | 4/21/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Tony Young
|
|
|
Would like to combine this with energy and final. Phone #: ###-#### Inspection requested via web by Adam Watkins
|
DOC - Permit Finaled | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 4/21/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Tony Young
|
|
|
Would like to combine this with wall cover and final. Phone #: ###-#### Inspection requested via web by Adam Watkins
|
BLD-Final | 4/19/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Watkins
|
BLD-Final | 4/18/2019 | 4/19/2019 | 4/19/2019 | P | NH |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Watkins
|
BLD-Framing/Rough-in | 3/23/2017 | 3/24/2017 | 3/27/2017 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Watkins
|
BLD-Other | 3/9/2017 | 3/10/2017 | 3/11/2017 | A | DONE |
Dave Hannah
|
|
|
We''ll be ready for final framing inspection at or around 11:00 a.m. Phone #: ###-#### Inspection requested via web by Adam Watkins
|
BLD-Final | 3/9/2017 | 3/10/2017 | 3/9/2017 | A | CANC |
Dave Hannah
|
|
|
We''ll be ready at 11:00 a.m. for the final inspection. Phone #: ###-#### >> Inspection requested via web by Adam Watkins Inspection cancelled from web by: Adam Watkins
|
BLD-Other | 2/13/2017 | 2/14/2017 | 2/14/2017 | A | PASS |
Dave Hannah
|
|
|
Foundation stem wall inspection.
We''re planning on concrete truck arriving at 1 p.m., so if you can schedule inspection for as late in the morning as possible that would be ideal. Phone #: ###-#### Inspection requested via web by Adam Watkins
|
BLD-Other | 2/10/2017 | 2/10/2017 | 2/10/2017 | P | PASS |
Dave Hannah
|
|
|
Footing inspection prior to pouring concrete
Please schedule between 3:00 and 4:00 p.m. Won''t be ready until then. Phone #: ###-#### Inspection requested via web by Adam Watkins
|
BLD-Footing | 2/10/2017 | 2/10/2017 | 2/10/2017 | P | PASS |
Dave Hannah
|
|
|
|
OVERRIDE | | | 11/23/2016 | | |
|
|
|
|
Routing Walk-In (BLD) | 11/22/2016 | 11/23/2016 | 11/23/2016 | A | DONE |
Brian McGowan
|
|
|
|
1st review completed | | | 11/23/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/23/2016 | | 11/23/2016 | | PASS |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 11/23/2016 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 11/23/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/23/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/23/2016 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 11/23/2016 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 11/22/2016 | 11/22/2016 | 11/22/2016 | A | PASS |
Colleen T Carroll
|
|
|
|
Application received | | 11/22/2016 | | | |
|
|
|
|