Third Notice | | 1/16/2018 | 1/17/2018 | | DONE |
|
|
|
This permit finaled on the web by Andrew Stewart
|
Second Notice | | 12/22/2017 | 1/11/2018 | | DONE |
|
|
|
Mailed 1-12-18
|
First Notice | | 12/11/2017 | 12/12/2017 | | DONE |
|
|
|
sent in mail 12-13-17
|
Permanent Occupancy | | | 12/1/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/1/2017 | | DONE |
|
|
|
|
BLD-Final | 10/30/2017 | 10/31/2017 | 10/31/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Ok for temp occ. Will be ok for perm oc. once electrical signs off.
|
FIRE-Final Inspection | 10/30/2017 | 10/31/2017 | 10/31/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor provided documentation that the thumbturn deadbolt hardware met ADA
|
FIRE-Final Inspection | 10/24/2017 | 10/25/2017 | 10/25/2017 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire sprinkler and fire alarm permits finaled. Only item for life safety inspected today was the exit signs and emergency lights. I noted two lights that are non-functional.
|
BLD-Final | 10/24/2017 | 10/25/2017 | 10/25/2017 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton needs fire and mec finals
|
FIRE-Final Inspection | 10/24/2017 | 10/24/2017 | 10/24/2017 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
BLD-Final | 10/24/2017 | 10/24/2017 | 10/24/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
BLD-Conference | 10/20/2017 | 10/23/2017 | 10/23/2017 | P | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
PubWorks Occupancy Approval | 10/23/2017 | 10/23/2017 | 10/23/2017 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 10/19/2017 | 10/19/2017 | 10/19/2017 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Ceiling Grid Inspection | 10/5/2017 | 10/6/2017 | 10/6/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Ceiling Grid Inspection | 10/5/2017 | 10/5/2017 | 10/5/2017 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Noted several areas were clips are missing.
|
BLD-Energy code compliance | 8/21/2017 | 8/21/2017 | 8/21/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Remainder of north west portion of soffits at main entry ok.
|
BLD-Wall cover | 8/15/2017 | 8/16/2017 | 8/16/2017 | A | PASS |
Mike Jordan
|
|
|
Two interior sheer walls for cover. Early as possible. Thanks Phone #: ###-#### Inspection requested via web by Darius Saxton. interior shear walls on east side of building ok.
|
BLD-Energy code compliance | 8/10/2017 | 8/10/2017 | 8/10/2017 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Work in progress on completing the soffit areas north west portion of building.
|
BLD-Energy code compliance | 8/2/2017 | 8/3/2017 | 8/3/2017 | A | PASS |
Mike Jordan
|
|
|
Early if possible Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Energy code compliance | 7/28/2017 | 7/31/2017 | 7/31/2017 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Framing/Rough-in | 7/31/2017 | 7/31/2017 | 7/31/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Remainder of interior steel stud framed walls at south west portion of building.
|
BLD-Energy code compliance | 7/27/2017 | 7/28/2017 | 7/28/2017 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton north ext wall ok to cover
|
BLD-Energy code compliance | 7/27/2017 | 7/27/2017 | 7/27/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
BLD-Energy code compliance | 7/26/2017 | 7/26/2017 | 7/26/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
BLD-Framing/Rough-in | 7/20/2017 | 7/24/2017 | 7/24/2017 | P | PART |
Mike Jordan
|
|
|
If you have any questions, Andrew will be onsite. His number is ###-#### Phone #: ###-#### Inspection requested via web by Darius Saxton. Pending plumbing rough in inspection.
|
BLD-Framing/Rough-in | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Interior steel stud framed walls ok on north half of building.
|
BLD-Wall cover | 7/13/2017 | 7/14/2017 | 7/14/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. All exterior shear walls ok to cover.
|
BLD-Framing/Rough-in | 7/14/2017 | 7/14/2017 | 7/14/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. exterior soffits and column wraps ok.
|
BLD-Wall cover | 7/7/2017 | 7/10/2017 | 7/10/2017 | A | PART |
Mike Jordan
|
|
|
Around 10 a.m. if possible Phone #: ###-#### Inspection requested via web by Darius Saxton. Exterior shear walls, noted some areas that reaquire additional fasteners.
|
BLD-Energy code compliance | 7/6/2017 | 7/7/2017 | 7/7/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Portion of exterior south east wall only.
|
BLD-Framing/Rough-in | 6/6/2017 | 6/6/2017 | 6/6/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Exterior steel stud framed walls.
|
BLD-Framing/Rough-in | 6/5/2017 | 6/5/2017 | 6/5/2017 | P | PART |
Mike Jordan
|
|
|
Exterior wall inspection Phone #: ###-#### Inspection requested via web by Darius Saxton
|
Plan assigned to (CJW) | 5/8/2017 | 5/8/2017 | 5/18/2017 | | PASS |
Carl Westfall
|
|
|
Deferred submittal
|
Routing - PLAN CHECK | 5/8/2017 | | 5/18/2017 | | PASS |
Carl Westfall
|
|
|
routed drawings
|
Plan Reviewer's activity | | | 5/18/2017 | | DONE |
|
|
|
Deferred submittal routed and approved. .5 hrs for Plan Review and 2.0 hrs for Consultant Structural review.
|
CHANGE STATUS TO (ISS) | | | 5/18/2017 | | DONE |
|
|
|
deferred submittal only. Per CJW no fee due, was included in original cert of value by GC
|
Routing Off Site - STRUCTURAL | 5/9/2017 | | 5/17/2017 | | PASS |
Carl Westfall
|
|
|
KPFF (Jordan Terry) - 2-hrs to review deferred submittal
|
BLD-Concrete | 5/5/2017 | 5/8/2017 | 5/8/2017 | A | DEFR |
Mike Jordan
|
|
|
60 yard slab pour. MTI scheduled to test concrete and to inspect wire mesh and vapor barrier. Concrete at 5 am. Phone #: ###-#### Inspection requested via web by Darius Saxton. special inspector on site.
|
Plan Modification Accepted | | | 5/8/2017 | | |
Christina Prado
|
|
|
For deferred submittal upload, as per CJW
|
BLD-Foundation | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Mike Jordan
|
|
|
As close to noon if possible. MTI scheduled for rebar and concrete at 2 pm. Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Footing | 4/25/2017 | 4/25/2017 | 4/25/2017 | P | PASS |
Mike Jordan
|
|
|
Rebar on trash enclosure. 2 pm if possible. Concrete at 3 pm. Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Footing | 4/24/2017 | 4/24/2017 | 4/24/2017 | P | PART |
Jim Sly
|
|
|
Darius Saxton Anderson. North East corner OK pending MTI special inspection, tests and approval.
|
BLD-Footing | 4/21/2017 | 4/24/2017 | 4/24/2017 | A | PASS |
Jim Sly
|
|
|
Around 11 if possible or late morning. MTI is scheduled for 11 and concrete at 2 pm. Phone #: ###-#### Inspection requested via web by Darius Saxton Septic appears to be full (grout, per Eng.) OK to pour footing.
|
BLD-Foundation | 4/12/2017 | 4/14/2017 | 4/14/2017 | A | DEFR |
Mike Jordan
|
|
|
Stem walls with rebar. Concrete pour at 1 p.m. Phone #: ###-#### Inspection requested via web by Darius Saxton. Pend. special inspection.
|
BLD-Footing | 4/4/2017 | 4/5/2017 | 4/5/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Nathan Shute. East and south footings. Partial footings on west and north ends. Needs to install corner bars. Will have special inspection.
|
Issue PAID IN FULL permit | | | 2/27/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/27/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 1/27/2017 | | |
|
|
|
|
Plan assigned to (CJW) | 12/5/2016 | 12/5/2016 | 1/27/2017 | | PASS |
Carl Westfall
|
|
|
(2nd done) (Dec 23 - 15 days) (Jan 13 - 30 days) (92 sheets) SAMG Emerald Clinic
|
Routing - PLAN CHECK | 1/17/2017 | | 1/27/2017 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/27/2017 | | DONE |
|
|
|
**ALL MET** needs: RP, GC, Revised Cert of Value 2-2-17 /CEV
need ACHD, RP, GC & Rev Cert of Val
|
Routing Off Site - STRUCTURAL | 1/18/2017 | | 1/25/2017 | | PASS |
Carl Westfall
|
|
|
KPFF (Jordan Terry)
|
Routing PW Solid Waste | 1/18/2017 | | 1/20/2017 | | PASS |
Evan Carpenter
|
|
|
Solid waste is OK as planned.
|
Plan resubmittals received | | | 1/17/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/3/2017 | 1/6/2017 | 1/4/2017 | | PASS |
Stephanie Jensen
|
|
|
|
1st review completed | | | 1/3/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/3/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/5/2016 | | 1/3/2017 | | FAIL |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 12/5/2016 | | 12/21/2016 | | FAIL |
Carl Westfall
|
|
|
KPFF (Jordan Terry)
|
Routing PW Sewer Design | 12/6/2016 | | 12/15/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Environmental | 12/6/2016 | | 12/14/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 12/6/2016 | | 12/12/2016 | | FAIL |
Evan Carpenter
|
|
|
Solid waste enclosure gates must be able to open 120 degrees.
|
Routing PW Street Lights | 12/6/2016 | | 12/12/2016 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Drainage | 12/6/2016 | | 12/12/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing - Erosion and Sediment | 12/5/2016 | | 12/8/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan submitted and approved. Valid PD and RP. Site preparation inspection required.
|
Routing - PLANNING Land Div | 12/5/2016 | | 12/7/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - FIRE | 12/5/2016 | 12/5/2016 | 12/6/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - PUBLIC WORKS | 12/5/2016 | | 12/6/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 12/5/2016 | | 12/6/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 12/5/2016 | | 12/5/2016 | | PASS |
Bill VanDegrift
|
|
|
Per plans and ISPC.
|
Routing - PLANNING | 12/5/2016 | | 12/5/2016 | | PASS |
Cody Riddle
|
|
|
Approved through DR.
|
Routing - Design Review | 12/5/2016 | | 12/5/2016 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 12/5/2016 | | PASS |
|
|
|
|
Routing - Addressing | 12/5/2016 | | 12/5/2016 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 12/2/2016 | | FAIL |
Javier Guzman
|
|
|
Please provide the following:
1. Soils and geotech report stamped and signed by an Idaho licensed engineer, the uploaded report is not signed/stamped/dated by an Idaho licensed soil engineer
2. stamped and signed by Idaho licensed design professional Drainage System Operation & Maintenance Plan.
3. ESC plans must be signed by a plan designer certified by Boise City.
|
Application received | | | 11/22/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 22 2016 8:38AM
|