BLD-Final | 4/2/2018 | 4/2/2018 | 4/3/2018 | P | PASS |
Jim Sly
|
|
|
Late afternoon if possible Phone #: ###-#### Inspection requested via web by Chris Palmer
|
PubWorks Occupancy Approval | 4/3/2018 | 4/3/2018 | 4/3/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 4/3/2018 | 4/3/2018 | 4/3/2018 | | DONE |
Leon Letson
|
|
|
|
Letter of compliance/Occupancy | | | 4/3/2018 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (FNL) | | | 4/3/2018 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | CANC |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
|
FIRE-Final Inspection | 3/28/2018 | 3/29/2018 | 3/29/2018 | P | PASS |
Troy Cobbley
|
|
|
As per activity notes, no inspection required, hydrants and fire dept access under the associated Grading permit
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Final | 3/27/2018 | 3/28/2018 | 3/29/2018 | A | CANC |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need the Grading permit finaled
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 9/18/2017 | 9/19/2017 | 9/19/2017 | A | PASS |
Jim Sly
|
|
|
Dave-roof framing Phone #: ###-####
|
BLD-Foundation | 8/25/2017 | 8/25/2017 | 8/28/2017 | P | CANC |
Jim Sly
|
|
|
|
BLD-Foundation | 8/24/2017 | 8/25/2017 | 8/25/2017 | A | CANC |
Brandon Shaw
|
|
|
Rebar // Dave Phone #: ###-####
|
BLD-Other | 8/16/2017 | 8/17/2017 | 8/17/2017 | P | PART |
Jim Sly
|
|
|
for deck david Phone #: ###-#### OK pending MTI approvals.
|
BLD-Foundation | 5/22/2017 | 5/23/2017 | 5/23/2017 | P | PART |
Jim Sly
|
|
|
Rebar // Dave Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|
Issue PAID IN FULL permit | | | 3/28/2017 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 3/28/2017 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JG) | 11/26/2016 | 11/26/2016 | 1/19/2017 | | PASS |
Javier Guzman
|
|
|
1st review completed, BOISE FIRE DEPT. BURN BUILDING - TWO STORY SINGLE FAMILY BUILDING #3 pend struct/eng
|
Routing Off Site - STRUCTURAL | 1/11/2017 | | 1/19/2017 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan by Stapley Engineering Jan Welch
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/19/2017 | | DONE |
|
|
|
Needs; RP, GC Form, Revised Cert of Value
|
Routing - PLAN CHECK | 1/11/2017 | | 1/18/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Drainage | 1/11/2017 | | 1/12/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 1/11/2017 | | 1/12/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Route to Impact Fee Review | 12/14/2016 | 12/17/2016 | 12/15/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Drainage | 11/28/2016 | | 12/14/2016 | | FAIL |
Brian Murphy
|
|
|
Failed in ePlan by PW Drainage Brian Murphy
|
Routing Off Site - STRUCTURAL | 11/26/2016 | | 12/14/2016 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by Stapley Engineering Jan Welch
|
1st review completed | | | 12/14/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 11/28/2016 | | 12/9/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLAN CHECK | 11/26/2016 | | 12/9/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLANNING | 11/26/2016 | | 11/29/2016 | | PASS |
Leon Letson
|
|
|
|
Routing - PLANNING Land Div | 11/26/2016 | | 11/29/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - FIRE | 11/26/2016 | 11/26/2016 | 11/28/2016 | | PASS |
Scott Arellano
|
|
|
No inspection required. FD Access and Hydrants will be inspected under GRD16-00084.
|
Routing - Addressing | 11/26/2016 | | 11/28/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/26/2016 | | 11/28/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 11/26/2016 | | 11/28/2016 | | PASS |
Andy J. Long
|
|
|
no seperate ESC permit required, ESC plan & site SWPPP submitted and covered with GRD-00084 & ESC16-01512
|
Routing PW Street Lights | 11/28/2016 | | 11/28/2016 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 11/28/2016 | | 11/28/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Add note: Contact Boise Public Works 48 hours prior to manhole work to obtain tap permit and schedule inspection.
Change manhole label from 589F1 to a number unrelated to the Boise Sewer manholes nearby (to avoid confusion). Public ownership of the sewer main will cease at manhole 589F.
|
Routing PW Solid Waste | 11/28/2016 | | 11/28/2016 | | PASS |
Evan Carpenter
|
|
|
Solid waste is OK as planned.
|
Intake Approval | | | 11/24/2016 | | PASS |
|
|
|
|
Application received | | | 11/23/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 23 2016 9:27AM
|
Plan Reviewer's activity | | | 11/23/2016 | | DONE |
Javier Guzman
|
|
|
emailed applicant and project manager Ron Hill requesting the required form 304 and to sign form 310
|