Permanent Occupancy | | | 4/16/2018 | | DONE |
|
|
|
|
BLD-Final | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
Temporary Occupancy | 4/6/2018 | 7/5/2018 | 4/6/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason B ok'd 45 day extension
|
Zoning Approval | 4/2/2018 | 4/2/2018 | 4/2/2018 | | PASS |
Katelyn Menuge
|
|
|
Final
|
BLD-Aging Inspection | 3/12/2018 | 3/12/2018 | 3/12/2018 | | PEND |
Mike Jordan
|
|
|
|
Temporary Occupancy | 1/16/2018 | 4/16/2018 | 1/16/2018 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Ok for temp occ. Will be ok for perm occ. once zoning and public works sign perm.
|
BLD-Final | 1/9/2018 | 1/9/2018 | 1/9/2018 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 1/9/2018 | 1/9/2018 | 1/9/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 1/9/2018 | 1/9/2018 | 1/9/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by David Scaggs Inspection cancelled from web by: David Scaggs
|
FIRE-Final Inspection | 1/4/2018 | 1/5/2018 | 1/5/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by David Scaggs
|
PubWorks Occupancy Approval | 1/2/2018 | 1/2/2018 | 1/2/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval Temp | 12/14/2017 | 12/14/2017 | 12/14/2017 | | PASS |
Katelyn Menuge
|
|
|
Temp
|
Print Occupancy Form | | | 12/12/2017 | | DONE |
|
|
|
|
BLD-Energy code compliance | 11/5/2017 | 11/6/2017 | 11/6/2017 | A | PASS |
Brandon Shaw
|
|
|
Framing corrections sat.
|
BLD-Energy code compliance | 11/3/2017 | 11/3/2017 | 11/3/2017 | P | NR |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Framing corrections not made.
|
BLD-Energy code compliance | 11/2/2017 | 11/3/2017 | 11/3/2017 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by david scaggs
|
BLD-Framing/Rough-in | 10/31/2017 | 10/31/2017 | 10/31/2017 | P | PART |
Mike Jordan
|
|
|
Dave Phone #: ###-####. frame around dry vents and fireblock at ceiling level. firecaulk penetrations at party walls. ok to insulate.
|
BLD-Wall Bracing | 8/3/2017 | 8/3/2017 | 8/3/2017 | A | PASS |
Brandon Shaw
|
|
|
Ext shear Inspection requested via web by Marty Short
|
BLD-Wall Bracing | 8/1/2017 | 8/1/2017 | 8/1/2017 | P | FAIL |
Mike Jordan
|
|
|
Ext shear Inspection requested via web by Marty Short
|
BLD-Footing | 7/6/2017 | 7/6/2017 | 7/6/2017 | P | PASS |
Mike Jordan
|
|
|
Marty Phone #: ###-####
|
BLD-Foundation | 7/5/2017 | 7/5/2017 | 7/5/2017 | P | PASS |
Mike Jordan
|
|
|
Marty Phone #: ###-####
|
BLD-Energy code compliance | 6/22/2017 | 6/22/2017 | 6/22/2017 | P | PASS |
Mike Jordan
|
|
|
Marty Phone #: ###-####. Rigid insulation on stemwall, interior side.
|
BLD-Foundation | 6/20/2017 | 6/21/2017 | 6/21/2017 | A | PASS |
Mike Jordan
|
|
|
pour time at 10 // Marty Phone #: ###-####
|
BLD-Footing | 6/13/2017 | 6/14/2017 | 6/14/2017 | A | PASS |
Jim Storey
|
|
|
Marty Phone #: ###-####
|
BLD-Footing | 6/12/2017 | 6/13/2017 | 6/13/2017 | A | FAIL |
Dave Hannah
|
|
|
Marty Phone #: ###-#### grade is mud standing water and one area ftg is to narrow
|
Issue PAID IN FULL permit | | | 5/9/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/9/2017 | | DONE |
|
|
|
|
Expiration Notice | 5/3/2017 | 5/24/2017 | 5/3/2017 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (CDM) | 12/7/2016 | 12/7/2016 | 4/25/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp. Marina Apartments
|
Routing - PLANNING Land Div | 12/7/2016 | | 4/25/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Erosion and Sediment | 12/7/2016 | | 4/25/2017 | | PASS |
Andy J. Long
|
|
|
|
Routing - MECHANICAL | 3/2/2017 | | 4/25/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/2/2017 | | 4/25/2017 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - PUBLIC WORKS | 3/2/2017 | | 4/25/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 3/2/2017 | | 4/25/2017 | | PASS |
Andy J. Long
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/25/2017 | | DONE |
Christina Prado
|
|
|
Need GC form & RP for issuance
|
Routing - Design Review | 4/12/2017 | | 4/12/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH17-00088.
|
Routing - PLAN CHECK | 3/2/2017 | | 3/10/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 3/2/2017 | | 3/10/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Design Review | 3/2/2017 | | 3/7/2017 | | FAIL |
Sarah Schafer
|
|
|
The following changes are required:
Modification required for changes to building materials.
Bike racks need to be shown on improved surface.
Additional trees in planters and along Preece
Left message for applicant today.
|
Routing - FIRE | 3/2/2017 | 3/2/2017 | 3/3/2017 | | PASS |
Scott Arellano
|
|
|
Sufficient fire flow provided.
|
Routing - PUBLIC WORKS | 12/7/2016 | | 3/2/2017 | | PASS |
Rachael Beierle
|
|
|
WEST BOISE SEWER DISTRICT
|
Route to Impact Fee Review | 1/5/2017 | 1/8/2017 | 1/9/2017 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 12/7/2016 | | 1/5/2017 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 1/5/2017 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/7/2016 | | 1/5/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 12/7/2016 | | 12/12/2016 | | FAIL |
Troy James
|
|
|
|
Routing - FIRE | 12/7/2016 | 12/7/2016 | 12/9/2016 | | PASS |
Scott Arellano
|
|
|
No fire flow provided, will be requested under permit BLD16-04308. Comments attached to case.
|
Routing - Addressing | 12/7/2016 | | 12/8/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PLUMBING | 12/7/2016 | | 12/8/2016 | | FAIL |
Bill VanDegrift
|
|
|
|
Routing - Design Review | 12/7/2016 | | 12/8/2016 | | FAIL |
Josh Wilson
|
|
|
Changemarks in Eplan.
|
Intake Approval | | | 12/7/2016 | | PASS |
|
|
|
|
Routing - PLANNING | 12/7/2016 | | 12/7/2016 | | PASS |
Cody Riddle
|
|
|
|
Application received | | | 11/29/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 29 2016 10:46AM
|
First Notice | | 4/26/2018 | | | |
|
|
|
|