PubWorks Occupancy Approval | 4/16/2018 | 4/16/2018 | 4/16/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 4/16/2018 | | DONE |
|
|
|
|
BLD-Final | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
Temporary Occupancy | 4/6/2018 | 7/5/2018 | 4/6/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason B ok'd 45 day ext
|
Zoning Approval | 4/2/2018 | 4/2/2018 | 4/2/2018 | | PASS |
Katelyn Menuge
|
|
|
Final
|
Telephone call | | | 3/22/2018 | | DONE |
|
|
|
emailed Dave that the temp c of o was either going to or was expired and he needs tocall in his final or requet an extension
|
BLD-Aging Inspection | 2/13/2018 | 2/13/2018 | 2/13/2018 | | PASS |
Mike Jordan
|
|
|
|
Temporary Occupancy | 12/20/2017 | 3/20/2018 | 12/20/2017 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 12/14/2017 | 12/15/2017 | 12/15/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Ok for temp. occ. Will be ok for perm. occ. once zoning and public works signs perm.
|
FIRE-Final Inspection | 12/14/2017 | 12/15/2017 | 12/15/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans or notes on site. Need the GRD permit inspected/finaled. I did test all of the smoke alarms and verified fire extinguishers. Per conversation with Ron Johnson an address monument will be needed at the entrance to show the interior building addresses for the responding personell.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
PubWorks Temp Occupancy Appr | 12/14/2017 | 12/14/2017 | 12/14/2017 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval Temp | 12/14/2017 | 12/14/2017 | 12/14/2017 | | PASS |
Katelyn Menuge
|
|
|
Temp
|
BLD-Final | 12/12/2017 | 12/13/2017 | 12/13/2017 | A | NR |
Mike Jordan
|
|
|
Please call contact number when complete so we can obtain physical sign off. Phone #: ###-#### Inspection requested via web by David Scaggs. Needs fire/life/safety finals and zoning.
|
Print Occupancy Form | | | 12/12/2017 | | DONE |
|
|
|
|
BLD-Energy code compliance | 10/3/2017 | 10/3/2017 | 10/3/2017 | P | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Energy code compliance | 10/2/2017 | 10/2/2017 | 10/2/2017 | P | NR |
Mike Jordan
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 9/28/2017 | 9/29/2017 | 9/29/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by david scaggs
|
FIRE-Sprinkler Rough-in | 9/28/2017 | 9/28/2017 | 9/28/2017 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered except for tie in area
|
BLD-Wall Bracing | 7/10/2017 | 7/11/2017 | 7/11/2017 | A | PASS |
Mike Jordan
|
|
|
Exterior shear Inspection requested via web by Marty Short
|
BLD-Footing | 6/9/2017 | 6/9/2017 | 6/9/2017 | P | PASS |
Brandon Shaw
|
|
|
Marty Phone #: ###-####
|
BLD-Footing | 6/8/2017 | 6/8/2017 | 6/8/2017 | P | FAIL |
Dave Hannah
|
|
|
Marty Phone #: ###-####
|
BLD-Energy code compliance | 6/6/2017 | 6/6/2017 | 6/6/2017 | P | PASS |
Mike Jordan
|
|
|
Marty Phone #: ###-####. Rigid insulation on stemwalls interior side under slab on grade.
|
BLD-Concrete | 5/23/2017 | 5/24/2017 | 5/24/2017 | P | CANC |
Mike Jordan
|
|
|
Wall // Marty Phone #: ###-####
|
BLD-Foundation | 5/24/2017 | 5/24/2017 | 5/24/2017 | P | PASS |
Mike Jordan
|
|
|
Wall // Marty Phone #: ###-####
|
BLD-Footing | 5/19/2017 | 5/22/2017 | 5/22/2017 | A | PASS |
Mike Jordan
|
|
|
Marty Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/9/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/9/2017 | | DONE |
Christina Prado
|
|
|
|
Expiration Notice | 5/3/2017 | 5/24/2017 | 5/3/2017 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (CDM) | 12/7/2016 | 12/7/2016 | 4/25/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp. Marina apartments
|
Routing - PLANNING Land Div | 12/7/2016 | | 4/25/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Erosion and Sediment | 12/7/2016 | | 4/25/2017 | | PASS |
Andy J. Long
|
|
|
|
Routing - PLAN CHECK | 4/25/2017 | | 4/25/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 4/25/2017 | | 4/25/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/25/2017 | | DONE |
Christina Prado
|
|
|
Need GC form & RP for issuance
|
Routing - MECHANICAL | 3/2/2017 | | 4/25/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/2/2017 | | 4/25/2017 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - PUBLIC WORKS | 3/2/2017 | | 4/25/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 3/2/2017 | | 4/25/2017 | | PASS |
Andy J. Long
|
|
|
|
Routing - Design Review | 4/12/2017 | | 4/12/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH17-00088.
|
Routing - Design Review | 4/12/2017 | | 4/12/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH17-00088.
|
Routing - PLAN CHECK | 3/2/2017 | | 3/10/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 3/2/2017 | | 3/10/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - Design Review | 3/2/2017 | | 3/7/2017 | | FAIL |
Sarah Schafer
|
|
|
The following changes are required:
Modification required for changes to building materials.
Bike racks need to be shown on improved surface.
Additional trees in planters and along Preece
Left message for applicant today.
|
Routing - FIRE | 3/2/2017 | 3/2/2017 | 3/3/2017 | | PASS |
Scott Arellano
|
|
|
Sufficient fire flow provided.
|
Routing - PUBLIC WORKS | 12/7/2016 | | 3/2/2017 | | PASS |
Rachael Beierle
|
|
|
WEST BOISE SEWER DISTRICT
|
Route to Impact Fee Review | 1/5/2017 | 1/8/2017 | 1/9/2017 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 12/7/2016 | | 1/5/2017 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 1/5/2017 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/7/2016 | | 1/5/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 12/7/2016 | | 12/12/2016 | | FAIL |
Troy James
|
|
|
|
Routing - FIRE | 12/7/2016 | 12/7/2016 | 12/9/2016 | | PASS |
Katie Marron
|
|
|
No fire flow provided, will be requested under permit BLD16-04308. Comments attached to case.
|
Routing - Addressing | 12/7/2016 | | 12/8/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PLUMBING | 12/7/2016 | | 12/8/2016 | | FAIL |
Bill VanDegrift
|
|
|
|
Routing - Design Review | 12/7/2016 | | 12/8/2016 | | FAIL |
Josh Wilson
|
|
|
|
Intake Approval | | | 12/7/2016 | | PASS |
|
|
|
|
Routing - PLANNING | 12/7/2016 | | 12/7/2016 | | PASS |
Cody Riddle
|
|
|
|
Application received | | | 11/29/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 29 2016 10:46AM
|
First Notice | | 4/26/2018 | | | |
|
|
|
|