FIRE-Final Inspection | 7/5/2018 | 7/5/2018 | 7/5/2018 | A | PASS |
Jim Page
|
|
|
Fire alarm permit has been finaled, final life fire safety nispection complete.
|
FIRE-Final Inspection | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | FAIL |
Jim Page
|
|
|
Fire alarm permit FIR17-00230 needs to be inspected and finaled before life fire safety inspection can be completed.
call him if have any questions // Brandon Phone #: ###-####
|
BLD-Final | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | NR |
Jim Sly
|
|
|
Brandon Phone #: ###-#### Called Brandon and gave him a list........Need final letter of approval from MTI special inspections, Finals from Ele 17-01549 Fir 17- 00230 (alarm). Fire Life Safety, PWK 17-00071, 00008 and 00019 and Zoning. Then call for structural final.
|
BLD-Aging Inspection | 5/1/2018 | 5/1/2018 | 5/1/2018 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 12/15/2017 | 12/15/2017 | 12/18/2017 | P | PART |
Dave Hannah
|
|
|
Partial for occupancy Phone #: ###-#### Inspection requested via web by Brandon Reynolds hand rail front steps ok to use
|
BLD-Conference | 10/25/2017 | 10/26/2017 | 10/26/2017 | A | DONE |
Dave Hannah
|
|
|
Would like to discuss handrails on ped ramp at Idaho St. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Final | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | PART |
Dave Hannah
|
|
|
This is for approval to allow pedestrian access to the Capitol St. doors on Wednesday the 25th. Phone #: ###-#### Inspection requested via web by Brandon Reynolds ok to use front doors
|
BLD-Final | 10/23/2017 | 10/24/2017 | 10/24/2017 | P | NR |
Dave Hannah
|
|
|
This is for approval to allow pedestrian access to the Capitol St. doors on Wednesday the 25th. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Ceiling Grid Inspection | 10/16/2017 | 10/17/2017 | 10/18/2017 | P | PASS |
Dave Hannah
|
|
|
Ceiling grid inspection, Electrical inspection in a.m. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Framing/Rough-in | 9/19/2017 | 9/19/2017 | 9/19/2017 | P | PASS |
Dave Hannah
|
|
|
Wall and header framing in vestibule capitol st. entrance. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Foundation | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | PEND |
Dave Hannah
|
|
|
Brandon-rebar Phone #: ###-#### ok after spec insp sign off
|
Print Occupancy Form | | | 4/4/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/4/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/31/2017 | | |
|
|
|
|
Plan assigned to (CDM) | 12/19/2016 | 12/19/2016 | 3/31/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp. City Hall Plaza
|
Routing - PLAN CHECK | 3/31/2017 | | 3/31/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/31/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/31/2017 | | DONE |
|
|
|
***ALL MET*** Need RP, GC Form and Revised Cert of Value
|
Routing - PUBLIC WORKS | 2/13/2017 | | 3/31/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing Off Site - STRUCTURAL | 2/13/2017 | | 3/11/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/13/2017 | | 3/11/2017 | | FAIL |
Carl D Madsen
|
|
|
Failed pending handrail discussions.
|
Routing PW Street Lights | 12/19/2016 | | 2/13/2017 | | PASS |
Tom Marshall
|
|
|
|
Route to Impact Fee Review | 1/28/2017 | 1/31/2017 | 1/30/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Routing Off Site - STRUCTURAL | 12/19/2016 | | 1/28/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/19/2016 | | 1/28/2017 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 1/28/2017 | | FAIL |
|
|
|
|
Routing PW Environmental | 12/19/2016 | | 1/19/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Drainage | 12/19/2016 | | 1/12/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 12/19/2016 | | 12/23/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing PW Geothermal | 12/19/2016 | | 12/22/2016 | | PASS |
Jon R. Gunnerson
|
|
|
no geothermal use
|
Routing - Erosion and Sediment | 12/19/2016 | | 12/20/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan approved, RP to be designated.
|
Routing - Addressing | 12/19/2016 | | 12/20/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - FIRE | 12/19/2016 | 12/19/2016 | 12/19/2016 | | PASS |
Katie Marron
|
|
|
Work to entry vestibule will require Separate Fire Permits. No comments attached.
|
Plan Reviewer's activity | | | 12/19/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
City working on ACHD agreement, do not issue till completed
|
Routing - PUBLIC WORKS | 12/19/2016 | | 12/19/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLUMBING | 12/19/2016 | | 12/19/2016 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 12/19/2016 | | PASS |
David Ferguson
|
|
|
|
Intake Approval | | | 12/13/2016 | | FAIL |
David Ferguson
|
|
|
Need proper naming convention, code analysis and fire flow letter.
|
Application received | | | 12/6/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 6 2016 5:50PM
|