Permit Information
Permit NumberBLD16-04392
StatusIssued
Name CM COMPANY
Site Address 150 N CAPITOL BLVD
Project NameCity Hall Plaza Renovation
Customer Number 
ePlanReviewYes
Description
(CITY HALL) For the renovation of the existing plaza to create a new streetscape with work to include the removal of the existing concrete, pavers and entry area and the construction of a new fountain, installation of new landscaping and general site work. The existing entry vestibule will be expanded approximately 324 sq. ft. beneath the existing second floor with the existing doors to be relocated and new led lighting installed along with some of the existing ductwork being reconfigured. The occupant load for the plaza is 719 total. There is no change in occupant load for the building as the area to be enclosed is already within the perimeter of the exterior walls of the building. This is a fully fire sprinklered and alarmed building. Any alterations to the sprinkler or alarm systems shall comply with NFPA 13 and 72 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection7/5/20187/5/20187/5/2018APASS
DetailsJim Page
Fire alarm permit has been finaled, final life fire safety nispection complete.
FIRE-Final Inspection7/2/20187/3/20187/3/2018AFAIL
DetailsJim Page
Fire alarm permit FIR17-00230 needs to be inspected and finaled before life fire safety inspection can be completed.

call him if have any questions // Brandon Phone #: ###-####
BLD-Final6/25/20186/25/20186/25/2018PNR
DetailsJim Sly
Brandon Phone #: ###-####
Called Brandon and gave him a list........Need final letter of approval from MTI special inspections, Finals from Ele 17-01549 Fir 17- 00230 (alarm). Fire Life Safety, PWK 17-00071, 00008 and 00019 and Zoning. Then call for structural final.
BLD-Aging Inspection5/1/20185/1/20185/1/2018 PEND
DetailsDave Hannah
BLD-Final12/15/201712/15/201712/18/2017PPART
DetailsDave Hannah
Partial for occupancy Phone #: ###-#### Inspection requested via web by Brandon Reynolds hand rail front steps ok to use
BLD-Conference10/25/201710/26/201710/26/2017ADONE
DetailsDave Hannah
Would like to discuss handrails on ped ramp at Idaho St. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
BLD-Final10/24/201710/25/201710/25/2017APART
DetailsDave Hannah
This is for approval to allow pedestrian access to the Capitol St. doors on Wednesday the 25th. Phone #: ###-#### Inspection requested via web by Brandon Reynolds ok to use front doors
BLD-Final10/23/201710/24/201710/24/2017PNR
DetailsDave Hannah
This is for approval to allow pedestrian access to the Capitol St. doors on Wednesday the 25th. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
BLD-Ceiling Grid Inspection10/16/201710/17/201710/18/2017PPASS
DetailsDave Hannah
Ceiling grid inspection, Electrical inspection in a.m. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
BLD-Framing/Rough-in9/19/20179/19/20179/19/2017PPASS
DetailsDave Hannah
Wall and header framing in vestibule capitol st. entrance. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
BLD-Foundation5/31/20176/1/20176/1/2017APEND
DetailsDave Hannah
Brandon-rebar Phone #: ###-#### ok after spec insp sign off
Print Occupancy Form  4/4/2017 DONE
Issue PAID IN FULL permit  4/4/2017 DONE
OVERRIDE  3/31/2017  
Plan assigned to (CDM)12/19/201612/19/20163/31/2017 PASS
DetailsCarl D Madsen
1st comp. City Hall Plaza
Routing - PLAN CHECK3/31/2017 3/31/2017 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  3/31/2017 DONE
Permit Ready to Issue  3/31/2017 DONE
***ALL MET*** Need RP, GC Form and Revised Cert of Value
Routing - PUBLIC WORKS2/13/2017 3/31/2017 PASS
DetailsRachael Beierle
Routing Off Site - STRUCTURAL2/13/2017 3/11/2017 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK2/13/2017 3/11/2017 FAIL
DetailsCarl D Madsen
Failed pending handrail discussions.
Routing PW Street Lights12/19/2016 2/13/2017 PASS
DetailsTom Marshall
Route to Impact Fee Review1/28/20171/31/20171/30/2017 PASS
DetailsTonya Wallace
Review requested for Commercial Permit
Routing Off Site - STRUCTURAL12/19/2016 1/28/2017 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK12/19/2016 1/28/2017 FAIL
DetailsCarl D Madsen
1st review completed  1/28/2017 FAIL
Routing PW Environmental12/19/2016 1/19/2017 PASS
DetailsRick Christenson
Routing PW Drainage12/19/2016 1/12/2017 PASS
DetailsBrian Murphy
Routing - Design Review12/19/2016 12/23/2016 PASS
DetailsJosh Wilson
Routing PW Geothermal12/19/2016 12/22/2016 PASS
DetailsJon R. Gunnerson
no geothermal use
Routing - Erosion and Sediment12/19/2016 12/20/2016 PASS
DetailsAndy J. Long
ESC plan approved, RP to be designated.
Routing - Addressing12/19/2016 12/20/2016 PASS
DetailsLaura Hunter
Routing - FIRE12/19/201612/19/201612/19/2016 PASS
DetailsKatie Marron
Work to entry vestibule will require Separate Fire Permits. No comments attached.
Plan Reviewer's activity  12/19/2016 DONE
DetailsAdele J Schaffeld-Griffin
City working on ACHD agreement, do not issue till completed
Routing - PUBLIC WORKS12/19/2016 12/19/2016 PASS
DetailsRachael Beierle
Routing - PLUMBING12/19/2016 12/19/2016 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Intake Approval  12/19/2016 PASS
DetailsDavid Ferguson
Intake Approval  12/13/2016 FAIL
DetailsDavid Ferguson
Need proper naming convention, code analysis and fire flow letter.
Application received  12/6/2016 DONE
Application submitted via PDS Online on Dec 6 2016 5:50PM