Permit Information
Permit NumberBLD16-04396
StatusFinaled
Name CANYON CREST HOMES
Site Address 6481 W HAMMERMILL DR
Project Name11-1 Millwell
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 2002 sq. ft., one story single family dwelling with 3 bedrooms, 2 bathrooms, approximately 268 sq. ft. of covered patio/porch and a 783 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning. **BJM**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/21/20176/22/20176/22/2017APASS
DetailsTony Young
Larry Phone #: ###-####,, 5.3 blower door
DOC - Permit Finaled6/22/20176/22/20176/22/2017PPASS
DetailsTony Young
c of o issued
BLD-Final6/21/20176/21/20176/22/2017PPART
DetailsTony Young
Larry Phone #: ###-####,, needs a support post on floor joist, then ok
BLD-Energy code compliance3/15/20173/16/20173/16/2017APASS
DetailsTony Young
Larry Phone #: ###-####
BLD-Framing/Rough-in3/14/20173/14/20173/14/2017PPART
DetailsMike Jordan
Larry Phone #: ###-####. provide header over door from garage to house. Ok to insulate.
BLD-Wall Bracing3/6/20173/7/20173/7/2017PPASS
DetailsTony Young
Larry Phone #: ###-####,, exterior ok
BLD-Wall Bracing3/6/20173/6/20173/6/2017PNR
DetailsTony Young
Larry Phone #: ###-####,, need to re-do some areas
BLD-Foundation1/25/20171/25/20171/25/2017PPART
DetailsTony Young
Chris Phone #: ###-####,, cold weather provisions explained
BLD-Foundation1/24/20171/25/20171/25/2017ANR
DetailsTony Young
Chris Phone #: ###-####
BLD-Footing1/24/20171/24/20171/24/2017PPASS
DetailsTony Young
Chris Phone #: ###-####
BLD-Footing1/20/20171/23/20171/23/2017ACANC
DetailsTony Young
Chris Phone #: ###-####
BLD-Footing1/20/20171/20/20171/20/2017PNR
DetailsJim Storey
BLD-Footing1/19/20171/20/20171/20/2017ANR
DetailsMike Jordan
Chris Phone #: ###-####. Footings not yet excavated.
BLD-Footing1/18/20171/19/20171/19/2017PCANC
DetailsTony Young
Chris Phone #: ###-####
Issue PAID IN FULL permit  1/12/2017 DONE
Inspection Record Card- Bld  1/12/2017 DONE
OVERRIDE  1/3/2017  
Plan assigned to (BJM)12/9/201612/9/20161/3/2017 DONE
DetailsBrian McGowan
Due 12-20 ePlan - No build on sub. - bld. review complete
PLANS/APPL TAKEN TO FRONT DESK  1/3/2017 DONE
DetailsBrian McGowan
Permit Ready to Issue  1/3/2017 DONE
all requirements met
Routing - PLANNING12/30/2016 12/30/2016 PASS
DetailsSue Cummings
No build satisfied
Routing - MECHANICAL12/7/2016 12/19/2016 PASS
DetailsTroy James
Routing - PLAN CHECK12/7/2016 12/16/2016 PASS
DetailsBrian McGowan
1st review completed  12/16/2016 DONE
DetailsBrian McGowan
Plan assigned to (LEG) Tisha12/7/2016 12/9/2016 DEFR
DetailsTisha Gallop
Application received  12/7/2016 DONE
Application submitted via PDS Online on Dec 7 2016 8:51AM
Plans ACCEPTED BY PLAN TECH  12/7/2016 DONE
Intake Approval  12/7/2016 PASS
Recd Pcfee & Taken To Pln CK  12/7/2016 DONE
Routing - Addressing12/7/2016 12/7/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS12/7/2016 12/7/2016 PASS
DetailsRachael Beierle
Routing - PLANNING12/7/2016   FAIL
Still has "no build" on sub