BLD-Final | 2/13/2017 | 2/14/2017 | 2/14/2017 | A | PASS |
Jim Storey
|
|
|
greg Phone #: ###-####
|
Letter of compliance/Occupancy | | | 2/14/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/13/2017 | 2/13/2017 | 2/13/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete
|
FIRE-Final Inspection | 1/23/2017 | 1/23/2017 | 1/23/2017 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for life safety until the door/hardware has been installed
|
FIRE-Final Inspection | 1/18/2017 | 1/19/2017 | 1/19/2017 | A | CANC |
Troy Cobbley
|
|
|
To be canceled per general contractor. To be rescheduled. Greg Phone #: ###-####
|
BLD-Framing/Rough-in | 12/15/2016 | 12/16/2016 | 12/16/2016 | A | PASS |
Jim Storey
|
|
|
Greg Phone #: ###-####
|
Inspection Record Card- Bld | | | 12/15/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/15/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/9/2016 | 12/9/2016 | 12/14/2016 | | PASS |
Javier Guzman
|
|
|
12/15 L1 Albertsons GO - Phase 9 TI
|
Routing - PLAN CHECK | 12/9/2016 | | 12/14/2016 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 12/14/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/14/2016 | | DONE |
Christina Prado
|
|
|
All met 12/15/16
need GC & rev cert of val
|
Intake Approval | | | 12/9/2016 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 12/8/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 8 2016 9:24AM
|
Intake Approval | | | 12/8/2016 | | FAIL |
David Ferguson
|
|
|
provide dimensions on your floorplan detail A1 located on page A1.00
|