BLD-Final | 4/10/2017 | 4/11/2017 | 4/11/2017 | P | PASS |
Dave Hannah
|
|
|
Justin Phone #: ###-####
|
DOC - Permit Finaled | 4/11/2017 | 4/11/2017 | 4/11/2017 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 1/11/2017 | 1/12/2017 | 1/12/2017 | A | PASS |
Tony Young
|
|
|
Jay Phone #: ###-####
|
BLD-Framing/Rough-in | 1/11/2017 | 1/11/2017 | 1/11/2017 | P | PASS |
Tony Young
|
|
|
Jay Phone #: ###-####
|
BLD-Framing/Rough-in | 12/28/2016 | 12/29/2016 | 12/29/2016 | P | PART |
Phil Shearer
|
|
|
james Phone #: ###-####. Pending MEC rough in, Point load beam in the basement. OK to insulate
|
Plan Modification Accepted | | | 12/27/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 12/27/2016 | | 12/27/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
Routing - PLAN CHECK | 12/19/2016 | | 12/21/2016 | | PASS |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 12/21/2016 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/21/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/21/2016 | | DONE |
|
|
|
|
Routing - MECHANICAL | 12/16/2016 | | 12/19/2016 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 12/15/2016 | | DONE |
|
|
|
One copy of Entire house HVAC Manuals J, S & D. Taken to Tisha
|
CHANGE STATUS TO (REV) | | | 12/15/2016 | | |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 12/13/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/13/2016 | | 12/13/2016 | | PASS |
Tisha Gallop
|
|
|
no zoining inspection required
|
Plan assigned to (LEG) Tisha | 12/13/2016 | | 12/13/2016 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/13/2016 | | DONE |
|
|
|
NEED GC form
|
Telephone call | | | 12/13/2016 | | DONE |
|
|
|
called GC- left message that we need a GC form, permit is ready, and fees due
|
Routing Walk-In (BLD) | 12/12/2016 | 12/12/2016 | 12/12/2016 | P | FAIL |
David Ferguson
|
|
|
Head height issues and still no Manual J - see Tisha's comments from previous meeting.
|
Routing Walk-In (Zoning) | 12/8/2016 | 12/8/2016 | 12/8/2016 | P | DONE |
Katelyn Menuge
|
|
|
DRH16-00526
|
Routing Walk-In (BLD) | 12/8/2016 | 12/8/2016 | 12/8/2016 | P | FAIL |
Tisha Gallop
|
|
|
NEED MAN J for gas to electric conversion. needs more details on plans of what he is doing. detail new beam and post better, dimensions of bathroom. Per Adele ok to remodel existing bathroom that does not meet ceiling ht. as long as it was existing and they are not touching the ceiling framing.
customer was informed unable to do over the counter permit per Man J requirement.
|
1st review completed | | | 12/8/2016 | | FAIL |
|
|
|
|
Application received | | 12/8/2016 | | | |
|
|
|
|