Second Notice | | 9/29/2017 | 9/25/2017 | | DONE |
|
|
|
This permit finaled on the web by Kenna Draper
|
First Notice | | 8/13/2017 | 9/19/2017 | | DONE |
|
|
|
Mailed 9-20-17
|
Permanent Occupancy | | | 8/3/2017 | | DONE |
|
|
|
|
BLD-Final | 8/1/2017 | 8/2/2017 | 8/2/2017 | A | PASS |
Mike Jordan
|
|
|
Call half hour before // Chad or ###-#### Phone #: ###-####. All issues resolved. Ok for perm occ. No card to sign.
|
Print Occupancy Form | | | 8/2/2017 | | DONE |
|
|
|
|
BLD-Final | 7/31/2017 | 8/1/2017 | 8/1/2017 | A | FAIL |
Mike Jordan
|
|
|
Call half hour before to meet /// Kyle Phone #: ###-####. Remove thumb turns from both exits and provide key locking hardware. Correction notice posted.
|
FIRE-Final Inspection | 7/26/2017 | 7/27/2017 | 7/27/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Foundation | 6/21/2017 | 6/22/2017 | 6/22/2017 | A | PASS |
Mike Jordan
|
|
|
Art Phone #: ###-####. Reviewed engineer's approval for pressure treated wood and special inspection report for the post installed anchors. ok to skirt and install the code compliant ramp.
|
BLD-Other | 4/11/2017 | 4/11/2017 | 4/11/2017 | P | FAIL |
Mike Jordan
|
|
|
block & tie down: Phone #: ###-####. Provide the special inspection report for the concrete anchor sysem that has been isnstalled. Modualar building not installed per the approved plans. Building not set on steel piers as shown, but on wood. Iether place the modualr as shown or engineer of record to resubmit altermate method for approval. Correction notice was issued.
|
Print Occupancy Form | | | 3/14/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/14/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/8/2017 | | 3/8/2017 | | PASS |
Andy J. Long
|
|
|
removed ESC requirement after further review.
|
OVERRIDE | | | 2/23/2017 | | |
|
|
|
|
Plan assigned to (CDM) | 12/21/2016 | 12/21/2016 | 2/23/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp. Boise Chinese Christian Church
|
Routing - PLAN CHECK | 2/23/2017 | | 2/23/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/23/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/23/2017 | | DONE |
|
|
|
***all requirements met 3-13-17 /CEV***
***still needs RP***
NEED RP, GC & Rev cert of val
|
Routing - PLAN CHECK | 2/4/2017 | | 2/4/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 12/30/2016 | 1/2/2017 | 1/3/2017 | | PASS |
Stephanie Jensen
|
|
|
|
Routing - PLAN CHECK | 12/21/2016 | | 12/30/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 12/21/2016 | | 12/30/2016 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 12/30/2016 | | FAIL |
|
|
|
|
Routing - Design Review | 12/21/2016 | | 12/23/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - Erosion and Sediment | 12/21/2016 | | 12/22/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved
|
Routing - PLANNING Land Div | 12/21/2016 | | 12/22/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - FIRE | 12/21/2016 | 12/21/2016 | 12/21/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Drainage | 12/21/2016 | | 12/21/2016 | | PASS |
Brian Murphy
|
|
|
LESS THAN 500SQ FT
|
Intake Approval | | | 12/21/2016 | | PASS |
|
|
|
|
Routing - Addressing | 12/21/2016 | | 12/21/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/21/2016 | | 12/21/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 12/16/2016 | | FAIL |
David Ferguson
|
|
|
1) Upload all plan sheets using the proper naming convention. For example, Electrical Plan, Elevations, Floor Plan, etc.
2) Make sure that EVERY plan sheet is stamped, signed and dated by an architect licensed in the State of Idaho.
3) Make sure that all plan sheets that are submitted are listed on the "DRAWINGS" located on page #1.
4) Make sure that all plan sheets are on a minimum sized paper of 18"x24".
5) On the checklist, you've indicated that you've provided a Fire Department Access Roadway plan however I could not find it. Please clarify or add this detail.
Note: all plan sheets except the "Foundation" plan have been deleted. The foundation plan was the only sheet that had both the proper naming convention and was stamped.
|
Intake Approval | | | 12/12/2016 | | FAIL |
David Ferguson
|
|
|
1) The file titled "Stamped Plans" has 6 individual sheets that have been bundled into one file. I've deleted this file so please upload each sheet individually.
2) Plan sheets 1 & 2 from your office have not been stamped, signed and dated at required.
3) Plan Sheet Index located sheet #1 does not include the plan sheets that are located in the Stamped Plans file. Please add these sheets to your Sheet Index.
4) On the checklist, you've indicated that you've provided a Fire Department Access Roadway plan however I could not find it. Please clarify or add this detail.
|
Application received | | | 12/9/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 9 2016 9:00AM
|