BLD-Final | 8/21/2018 | 8/21/2018 | 8/21/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
DOC - Permit Finaled | 8/21/2018 | 8/21/2018 | 8/21/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown. Needs to install code compliant handrail. Everything elese ok.
|
BLD-Blower Door Test Results | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | DONE |
Mike Jordan
|
|
|
6.8ACH @50pa
|
BLD-Energy code compliance | 5/11/2018 | 5/11/2018 | 5/11/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Framing/Rough-in | 5/11/2018 | 5/11/2018 | 5/11/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Framing/Rough-in | 5/10/2018 | 5/10/2018 | 5/10/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Energy code compliance | 5/10/2018 | 5/10/2018 | 5/10/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Framing/Rough-in | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown. fireblock concealed space at ceiling next to shower/tub upstairs. Complete lateral bracing. Fire block fir downs downstairs. Ok to insulate.
|
BLD-Other | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PASS |
Mike Jordan
|
|
|
Fire rated assembly at roof eave. Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Wall Bracing | 3/22/2018 | 3/22/2018 | 3/22/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 3/21/2018 | 3/21/2018 | 3/21/2018 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown. Missing straps, nailing and holdowns.
|
BLD-Foundation | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
Mike Jordan
|
|
|
rebar // dan Phone #: ###-####
|
BLD-Foundation | 10/18/2017 | 10/18/2017 | 10/18/2017 | P | PASS |
Mike Jordan
|
|
|
foundation insulation // Sam Phone #: ###-####
|
BLD-Foundation | 10/16/2017 | 10/16/2017 | 10/16/2017 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Footing | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/1/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/1/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 8/31/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 3/2/2017 | 3/2/2017 | 8/31/2017 | | DONE |
Brian McGowan
|
|
|
1st Review Complete -Due 3-17 Level 2 - Fail- Engineering was done as a duplex
|
Routing - PLAN CHECK | 8/22/2017 | | 8/31/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 8/31/2017 | | DONE |
|
|
|
all met, Issue with Bld16-04456
|
Plan resubmittals received | | | 8/22/2017 | | DONE |
|
|
|
|
Extend Review Timeline | | | 6/5/2017 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Expiration Notice | 5/18/2017 | 6/9/2017 | 5/18/2017 | | DONE |
Brittany Hill
|
|
|
|
1st review completed | | | 3/17/2017 | | FAIL |
Brian McGowan
|
|
|
Lateral and shear was done as a duplex
|
Routing - PLAN CHECK | 2/28/2017 | | 3/17/2017 | | FAIL |
Brian McGowan
|
|
|
Lateral and shear was done as a duplex
|
Route to Impact Fee Review | 2/28/2017 | 3/3/2017 | 3/6/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Plan assigned to (LEG) Tisha | 2/28/2017 | | 3/2/2017 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - Addressing | 2/28/2017 | | 3/1/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/28/2017 | | 2/28/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 2/28/2017 | | 2/28/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 2/28/2017 | | 2/28/2017 | | PASS |
Cody Riddle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/28/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 2/28/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/28/2017 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 12/13/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 13 2016 10:15AM
|