BLD-Final | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
DOC - Permit Finaled | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | DONE |
Mike Jordan
|
|
|
6.4ACH @50pa
|
BLD-Aging Inspection | 7/31/2018 | 7/31/2018 | 7/31/2018 | | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Brown Inspection cancelled from web by: Sam Brown
|
BLD-Framing/Rough-in | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Brown Inspection cancelled from web by: Sam Brown
|
BLD-Energy code compliance | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Framing/Rough-in | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Framing/Rough-in | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Brown Inspection cancelled from web by: Sam Brown
|
BLD-Framing/Rough-in | 3/8/2018 | 3/8/2018 | 3/8/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Other | 2/22/2018 | 2/22/2018 | 2/22/2018 | P | PASS |
Mike Jordan
|
|
|
Fire rated assembly at roof eave. Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Wall Bracing | 1/16/2018 | 1/16/2018 | 1/16/2018 | P | PASS |
Mike Jordan
|
|
|
Stan Phone #: ###-####
|
BLD-Wall Bracing | 1/10/2018 | 1/10/2018 | 1/10/2018 | P | FAIL |
Mike Jordan
|
|
|
Sam Phone #: ###-####. Complete install of holdowns and nail off missed areas.
|
BLD-Foundation | 11/3/2017 | 11/3/2017 | 11/3/2017 | P | PASS |
Mike Jordan
|
|
|
Rebar // Sam Phone #: ###-####
|
BLD-Foundation | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | PASS |
Mike Jordan
|
|
|
Sam-foundation-insulation Phone #: ###-####
|
BLD-Foundation | 9/18/2017 | 9/18/2017 | 9/18/2017 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Footing | 9/15/2017 | 9/15/2017 | 9/15/2017 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/6/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/6/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 8/29/2017 | | |
|
|
|
|
Plan resubmittals received | | | 8/29/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/29/2017 | | 8/29/2017 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/29/2017 | | DONE |
|
|
|
Need
GC Form-MET
|
Plan assigned to (LEG) Tisha | 2/28/2017 | | 8/29/2017 | | DONE |
Tisha Gallop
|
|
|
3rd review 8/28; 2nd review 8/24; 1st review 3/17 L2 townhouse
|
Plan resubmittals received | | | 8/28/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/28/2017 | | 8/28/2017 | | FAIL |
Tisha Gallop
|
|
|
side/side main floor middle shear wall missing on foundation plan
|
Routing - PLAN CHECK | 8/23/2017 | | 8/24/2017 | | FAIL |
Tisha Gallop
|
|
|
update plans to match eng. shear, A5.02 details missing (see changemarks)
|
Plan resubmittals received | | | 8/23/2017 | | DONE |
|
|
|
|
Extend Review Timeline | | | 6/5/2017 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Expiration Notice | 5/18/2017 | 6/9/2017 | 5/18/2017 | | DONE |
Brittany Hill
|
|
|
|
1st review completed | | | 3/17/2017 | | FAIL |
|
|
|
pending approval by plan check
|
Routing - PLAN CHECK | 2/28/2017 | | 3/17/2017 | | FAIL |
Tisha Gallop
|
|
|
shear
|
Route to Impact Fee Review | 2/28/2017 | 3/3/2017 | 3/6/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - MECHANICAL | 2/28/2017 | | 3/3/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 2/28/2017 | | 3/1/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/28/2017 | | 2/28/2017 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/28/2017 | | DONE |
|
|
|
|
Intake Approval | | | 2/28/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/28/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 2/28/2017 | | 2/28/2017 | | PASS |
Cody Riddle
|
|
|
|
Application received | | | 12/13/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 13 2016 3:47PM
|