BLD-Final | 10/24/2018 | 10/24/2018 | 10/24/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
DOC - Permit Finaled | 10/24/2018 | 10/24/2018 | 10/24/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 10/24/2018 | 10/24/2018 | 10/24/2018 | P | DONE |
Mike Jordan
|
|
|
5.6ACH @50pa
|
BLD-Energy code compliance | 8/1/2018 | 8/1/2018 | 8/1/2018 | P | PASS |
Mike Jordan
|
|
|
Questions or issues, please call Krista at ###-####. Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Framing/Rough-in | 7/25/2018 | 7/26/2018 | 7/26/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Wall Bracing | 4/23/2018 | 4/23/2018 | 4/23/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Aging Inspection | 4/18/2018 | 4/18/2018 | 4/18/2018 | | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 | P | PASS |
Mike Jordan
|
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD-Foundation | 11/3/2017 | 11/3/2017 | 11/3/2017 | P | PASS |
Mike Jordan
|
|
|
Sam Phone #: ###-####
|
BLD-Foundation | 10/23/2017 | 10/24/2017 | 10/24/2017 | A | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 10/23/2017 | 10/23/2017 | 10/23/2017 | P | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/12/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/12/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/8/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 3/1/2017 | 3/1/2017 | 9/8/2017 | | DONE |
Brian McGowan
|
|
|
1st Review Complete -Due 3-17 Level 2 - Fail- Engineering required for townhome submittal
|
Routing - PLAN CHECK | 8/23/2017 | | 9/8/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 9/8/2017 | | DONE |
|
|
|
need RP-kdo not issue without BLD17-04509
|
Plan resubmittals received | | | 8/23/2017 | | DONE |
|
|
|
|
Extend Review Timeline | | | 6/5/2017 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Expiration Notice | 5/18/2017 | 6/9/2017 | 5/18/2017 | | DONE |
Brittany Hill
|
|
|
|
1st review completed | | | 3/22/2017 | | FAIL |
Brian McGowan
|
|
|
Engineering required for townhome submittal
|
Routing - PLAN CHECK | 2/28/2017 | | 3/22/2017 | | FAIL |
Brian McGowan
|
|
|
Engineering required for townhome submittal
|
Route to Impact Fee Review | 2/28/2017 | 3/3/2017 | 3/6/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - MECHANICAL | 2/28/2017 | | 3/6/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 2/28/2017 | | 3/1/2017 | | PASS |
Laura Hunter
|
|
|
|
Plan assigned to (LEG) Tisha | 2/28/2017 | | 3/1/2017 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - PUBLIC WORKS | 2/28/2017 | | 2/28/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 2/28/2017 | | 2/28/2017 | | PASS |
Cody Riddle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/28/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 2/28/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/28/2017 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 12/14/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 14 2016 3:00PM
|