Print Statement | | | 2/20/2018 | | DONE |
|
|
|
|
Second Notice | | 1/21/2018 | 2/12/2018 | | DONE |
|
|
|
Mailed 2-13-18
|
First Notice | 12/22/2017 | 12/22/2017 | 1/11/2018 | | DONE |
Mike Jordan
|
|
|
Mailed 1-12-18
|
BLD-Final | 12/20/2017 | 12/22/2017 | 12/22/2017 | A | PASS |
Mike Jordan
|
|
|
Elad Phone #: ###-####
|
DOC - Permit Finaled | 12/22/2017 | 12/22/2017 | 12/22/2017 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Conference | 5/24/2017 | 5/24/2017 | 5/24/2017 | P | PASS |
Mike Jordan
|
|
|
After 3 // Vald Phone #: ###-####. Remainder of 1hr. construction in attic ok.
|
FIRE-Conference | 5/22/2017 | 5/23/2017 | 5/23/2017 | P | DONE |
Troy Cobbley
|
|
|
I discussed exit door hardware with Vlad Phone #: ###-####
|
BLD-Framing/Rough-in | 5/2/2017 | 5/3/2017 | 5/3/2017 | P | PASS |
Mike Jordan
|
|
|
Zlad Phone #: ###-####. Interior wood framed walls and ceiling ok to cover.
|
BLD-Conference | 4/13/2017 | 4/14/2017 | 4/14/2017 | P | DONE |
Mike Jordan
|
|
|
Paul Phone #: ###-####. went over 1hr. fire partition details.
|
Inspection Record Card- Bld | | | 2/28/2017 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 2/28/2017 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 1/6/2017 | 1/6/2017 | 2/22/2017 | | PASS |
Carl Westfall
|
|
|
(1st done) (Jan 26 - 15 days) (Feb 2 - 20 days) (8 sheets) 909 N. Cole Rd Shell and Core
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/22/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/22/2017 | | DONE |
Christina Prado
|
|
|
All Met 2/24/17 C_P ///// need ACHD, GC & rev cert of val
|
Routing - PLAN CHECK | 2/17/2017 | | 2/21/2017 | | PASS |
Carl Westfall
|
|
|
|
Routing - MECHANICAL | 2/21/2017 | | 2/21/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Plan resubmittals received | | | 2/17/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/3/2017 | | 2/6/2017 | | PASS |
Carl Westfall
|
|
|
|
Routing - MECHANICAL | 2/6/2017 | | 2/6/2017 | | FAIL |
Troy James
|
|
|
Per previous change mark on 1/9/2017. Still need mechanical plans stamped and signed by an Idaho licensed engineer for commercial projects.
Emailed corrections to project contact.
|
Plan resubmittals requested | | | 2/6/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 2/1/2017 | 2/4/2017 | 2/3/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals received | | | 2/3/2017 | | DONE |
|
|
|
|
1st review completed | | | 2/1/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 2/1/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/6/2017 | | 2/1/2017 | | FAIL |
Carl Westfall
|
|
|
|
Routing - FIRE | 1/6/2017 | 1/6/2017 | 1/13/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - PUBLIC WORKS | 1/6/2017 | | 1/9/2017 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT.
|
Routing - MECHANICAL | 1/6/2017 | | 1/9/2017 | | FAIL |
Chad Schwendiman
|
|
|
Need mechanical plans stamped and signed by an Idaho licensed engineer
|
Routing - Addressing | 1/6/2017 | | 1/6/2017 | | PASS |
Laura Hunter
|
|
|
Added address: 901 N Cole Rd for office
|
Routing - Design Review | 1/6/2017 | | 1/6/2017 | | PASS |
Sarah Schafer
|
|
|
Approved through building permit.
|
Intake Approval | | | 1/6/2017 | | PASS |
Carl D Madsen
|
|
|
|
Application received | | | 12/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 15 2016 2:26PM
|