Information based on query as of Sunday, June 23, 2024.
Permit Information
Permit NumberBLD16-04524
StatusFinaled
Name CANNING CONSTRUCTION INC
Site Address 9465 W EMERALD ST 260
Project NameAcosta
Customer Number 
ePlanReviewYes
Description
**(ACOSTA – PART OF 1ST STORY & PART OF 2ND STORY SUITE #260)** //Plan modification #2 to remove from scope of work all new card readers, remove from scope of work the interior nonbearing wall at first floor from plan modification #1, remove select door/door frames and infill and additional electrical work on the second floor. 3-17-2017 JG// - //Plan modification #1 to re-configure entry by adding an interior nonbearing wall and additional electrical work on the second floor. 2-28-2017 JG. // Permit is to remodel an existing 12,313 sq. ft. 2nd floor tenant space on the north/northeast end section of the building and minor work at the existing 2,252 sq. ft. 1st floor storage warehouse. Approval is contingent upon adhering to the approved plans on file. Work to include: removal of select interior nonbearing wall, removal of door/door frames, removal of select millwork, construction of interior non-bearing walls to create a nonrated stairway enclosure at the first floor, new wall in-fill, new door /door frames, millwork, electrical work and interior finishes in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/23/20173/24/20173/24/2017APASS
DetailsMike Jordan
Greg Phone #: ###-####. Ok for perm occ.
First Notice 4/3/20173/24/2017 DONE
Print Statement  3/24/2017 DONE
Permanent Occupancy  3/24/2017 DONE
FIRE-Final Inspection3/22/20173/22/20173/22/2017PPASS
DetailsTroy Cobbley
Life safety passed. Per conversation with Greg the project super the tenant will be changing the suite number from 260 to 200 in the future. I let him know that they will need to contact addressing for guidance.
BLD-Framing/Rough-in3/20/20173/20/20173/20/2017PPASS
DetailsMike Jordan
Greg Phone #: ###-####. Steel stud infill for existing doors ok.
Plan assigned to (JG) 3/16/20173/17/2017 PASS
DetailsJavier Guzman
Plan mod, Acosta ePlan
Routing - PLAN CHECK3/17/2017 3/17/2017 PASS
DetailsJavier Guzman
Permit Ready to Issue  3/17/2017 DONE
DO NOT REISSUE PLAN MOD
CHANGE STATUS TO (ISS)  3/17/2017 DONE
DetailsChristina Prado
Plan Mod fees paid in full, status changed back to ISS
Plan Modification Accepted  3/16/2017  
FIRE-Conference3/8/20173/9/20173/9/2017ADONE
DetailsTroy Cobbley
We went over life safety requirements.
BLD-Conference3/1/20173/2/20173/2/2017ADONE
DetailsMike Jordan
GREG Phone #: ###-####. resubmit plans to reflect changes.
CHANGE STATUS TO (ISS)  3/1/2017 DONE
Plan assigned to (JG)2/13/20172/13/20172/28/2017 PASS
DetailsJavier Guzman
Plan Mod, Acosta
Permit Ready to Issue  2/28/2017 DONE
DO NOT REISSUE PLAN MOD
Routing - PLAN CHECK2/21/2017 2/28/2017 PASS
DetailsJavier Guzman
Routing - MECHANICAL2/21/2017 2/21/2017 PASS
DetailsTroy James
No mechanical work with plan modification. No fees charged.
Plan Reviewer's activity  2/21/2017 DONE
DetailsAdele J Schaffeld-Griffin
I have deleted the sheets uploaded for the plan mod. Please re upload them using the same name as to allow for the sheets to version.
BLD-Framing/Rough-in2/16/20172/17/20172/17/2017APART
DetailsJim Storey
Greg-PARTIAL Phone #: ###-####-Greg says inspection doesn't have anything to do with the plan mod infil ok per issued plan wall under plan mod pending.
Route to Impact Fee Review2/13/20172/16/20172/15/2017 PASS
DetailsCindy M. Gould
Review requested for Commercial Permit
Plan Modification Accepted  2/13/2017 DONE
Issue PAID IN FULL permit  2/10/2017 DONE
Print Occupancy Form  2/10/2017 DONE
Routing - FIRE1/4/20171/4/20171/4/2017 PASS
DetailsKatie Marron
comments attached to case.
Plan assigned to (JG)12/21/201612/21/20161/4/2017 PASS
DetailsJavier Guzman
1st review completed, 1/03 L2 Acosta TI ePlan
Routing - PLAN CHECK1/4/2017 1/4/2017 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  1/4/2017 DONE
Permit Ready to Issue  1/4/2017 DONE
***all requirments met 2-9-17 /CEV

Need GC Form and Revised Cert of Value
Routing - PLAN CHECK12/21/2016 1/3/2017 FAIL
DetailsJavier Guzman
Pending possible need for CDH forms Applicant was going to ask tenent if storing food
1st review completed  1/3/2017 FAIL
DetailsJavier Guzman
Routing - MECHANICAL12/21/2016 12/27/2016 PASS
DetailsTroy James
Routing - PUBLIC WORKS12/21/2016 12/22/2016 PASS
DetailsRachael Beierle
Routing - Addressing12/21/2016 12/22/2016 PASS
DetailsLaura Hunter
Suite number 260
Intake Approval  12/21/2016 FAIL
DetailsDavid Ferguson
Plans are bundled and need to be separated. Use proper naming convention.
Intake Approval  12/21/2016 PASS
DetailsJavier Guzman
Application received  12/16/2016 DONE
Application submitted via PDS Online on Dec 16 2016 1:30PM