Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD16-04549
StatusFinaled
Name KB FINANCIAL LLC
Site Address 2236 W HILL TERRACE LN
Project NameNORTH HILL SUBDIVISION
Customer NumberBLD16-04550
ePlanReviewYes
Description
(2 PERMITS TOTAL FILED UNDER BLD16-04549 IN EPLANREVIEW) DRH14-00164/PUD14-00006; WUI Zone A; Permit for the construction of a new 1904 sq. ft., two story (first story 786 sq. ft., second story 1118 sq. ft.) Townhouse with 3 bedrooms, 2.5 bathrooms, approximately 121 sq. ft. of covered patio/porch and a 492 sq. ft. attached garage per the approved plans, engineering, ACCA report and any notations. R-1C zoning and setbacks per planning. //leg ***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/23/20184/23/20184/23/2018PPASS
DetailsTony Young
RON Phone #: ###-####
DOC - Permit Finaled4/23/20184/23/20184/23/2018PPASS
DetailsTony Young
c of o issued
PubWorks Occupancy Approval4/20/20184/20/20184/20/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Foundation3/5/20183/6/20183/6/2018ACANC
DetailsTony Young
rebar // Austin Phone #: ###-####
BLD-Energy code compliance1/8/20181/9/20181/9/2018APASS
DetailsTony Young
Ron Phone #: ###-####
BLD-Wall Bracing1/2/20181/3/20181/3/2018APASS
DetailsTony Young
Ron Phone #: ###-####
BLD-Framing/Rough-in12/29/20171/2/20181/2/2018APASS
DetailsTony Young
Ron Phone #: ###-####
BLD-Conference12/14/201712/14/201712/14/2017PPEND
DetailsTony Young
Ron Phone #: ###-####,, firewall ?s,, needs to get architect on site
BLD-Framing/Rough-in12/12/201712/14/201712/14/2017ANR
DetailsTony Young
Ron Phone #: ###-####
BLD-Framing/Rough-in12/8/201712/12/201712/12/2017ADEFR
DetailsJim Storey
Ron Phone #: ###-#### to tony for thur. am
BLD-Wall Bracing11/27/201711/28/201711/28/2017AFAIL
DetailsBrandon Shaw
Ron Phone #: ###-####..See correction notice and red paint.

OK to wrap exterior only
BLD-Other11/8/201711/9/201711/9/2017PPART
DetailsTony Young
fire wall // Aaron Phone #: ###-####,, upper patio firewalls ok,, also trusses are work in progress on the ground
BLD-Other11/1/201711/1/201711/2/2017PPART
DetailsBrandon Shaw
Fire wall, work in progress
BLD-Other10/19/201710/20/201710/20/2017APART
DetailsTony Young
Aaron-fire wall Phone #: ###-####,, screw pattern on main level ok
BLD-Foundation8/18/20178/18/20178/18/2017PPART
DetailsTony Young
Rebar // Austin Phone #: ###-####,, work in progress
BLD-Concrete8/10/20178/11/20178/11/2017APASS
DetailsBrandon Shaw
rebar- Austin Phone #: ###-####
PubWorks Occupancy Approval5/10/20175/10/20175/10/2017 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
BLD-Footing2/10/20172/14/20172/14/2017ANR
DetailsTony Young
Austin Phone #: ###-####,, need soils 1st
Issue PAID IN FULL permit  2/9/2017 DONE
DetailsChristina Prado
Inspection Record Card- Bld  2/9/2017 DONE
DetailsChristina Prado
OVERRIDE  1/9/2017  
Permit Ready to Issue  1/9/2017 DONE
DetailsChristina Prado
Parcel Owner is GC - All requirements met
1st review completed  1/6/2017 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/6/2017 DONE
Plan assigned to (LEG) Tisha12/22/2016 1/6/2017 DONE
DetailsTisha Gallop
1/10 L2 hillside townhouse
Routing - PLAN CHECK12/22/2016 1/6/2017 PASS
DetailsTisha Gallop
Routing - Design Review12/22/2016 12/29/2016 PASS
DetailsJosh Wilson
Routing - Erosion and Sediment12/22/2016 12/27/2016 PASS
DetailsAndy J. Long
ESC plan with site map and narrative approved.
Routing - MECHANICAL12/22/2016 12/27/2016 PASS
DetailsTroy James
Routing PW Grading-Hillside12/22/2016 12/23/2016 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Routing - FIRE12/22/201612/22/201612/22/2016 PASS
DetailsKatie Marron
Plans were evaluated for FD Access, hydrant availability and defensible space.
Routing - Addressing12/22/2016 12/22/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS12/22/2016 12/22/2016 PASS
DetailsMorgan Webb
Plans ACCEPTED BY PLAN TECH  12/22/2016 DONE
DetailsChristina Prado
Intake Approval  12/22/2016 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  12/22/2016 DONE
DetailsChristina Prado
Application received  12/20/2016 DONE
Application submitted via PDS Online on Dec 20 2016 7:44PM