BLD-Final | 8/7/2017 | 8/7/2017 | 8/8/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 8/8/2017 | 8/8/2017 | 8/8/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Wall cover | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Brandon Shaw
|
|
|
This is for the exterior can light fire-rated boxes. Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Wall cover | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | PASS |
Brandon Shaw
|
|
|
Interior shear wall inspection Phone #: ###-#### Inspection requested via web by Braxton Hansen Spacing good- 7" & 7", watch edge nailing spacing, min 3/8" from edge. Ok to cover.
|
BLD-Energy code compliance | 4/20/2017 | 4/20/2017 | 4/20/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Framing/Rough-in | 4/16/2017 | 4/17/2017 | 4/17/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Wall Bracing | 3/22/2017 | 3/23/2017 | 3/23/2017 | A | PASS |
Jim Storey
|
|
|
Shear inspection, approved set is on site with the framers Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Footing | 2/21/2017 | 2/21/2017 | 2/21/2017 | P | PASS |
Jim Sly
|
|
|
Sergio Phone #: ###-####
|
BLD-Footing | 2/16/2017 | 2/17/2017 | 2/17/2017 | A | PART |
Jim Storey
|
|
|
Sergio-pour time 10:00 Phone #: ###-#### ft ok no copaction report to be with plans at wall insp.
|
BLD-Footing | 2/15/2017 | 2/15/2017 | 2/15/2017 | P | NR |
Jim Storey
|
|
|
Phone #: ###-#### fill need compaction report for ne corner
|
Issue PAID IN FULL permit | | | 1/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/20/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 1/11/2017 | | |
|
|
|
|
Plan assigned to (DAF) | 12/22/2016 | 12/22/2016 | 1/11/2017 | | PASS |
David Ferguson
|
|
|
due 1/03 - plan review failed - need WUI detail
|
Routing - PLAN CHECK | 1/11/2017 | | 1/11/2017 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/11/2017 | | DONE |
|
|
|
all requirments met
|
1st review completed | | | 1/6/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 12/21/2016 | | 1/6/2017 | | FAIL |
David Ferguson
|
|
|
|
Routing - MECHANICAL | 12/21/2016 | | 12/27/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/21/2016 | | 12/22/2016 | | PASS |
Sue Cummings
|
|
|
|
Plan assigned to (LEG) Tisha | 12/21/2016 | | 12/22/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Application received | | | 12/21/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 21 2016 10:38AM
|
Plans ACCEPTED BY PLAN TECH | | | 12/21/2016 | | DONE |
|
|
|
|
Intake Approval | | | 12/21/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/21/2016 | | DONE |
|
|
|
|
Routing - Addressing | 12/21/2016 | | 12/21/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/21/2016 | | 12/21/2016 | | PASS |
Morgan Webb
|
|
|
|