BLD-Final | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | PASS |
Brandon Shaw
|
|
|
|
DOC - Permit Finaled | 6/1/2017 | 6/1/2017 | 6/1/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 5/30/2017 | 5/31/2017 | 5/31/2017 | A | CANC |
Brandon Shaw
|
|
|
Adam Phone #: ###-####
|
BLD-Final | 5/30/2017 | 5/30/2017 | 5/30/2017 | P | NR |
Jim Sly
|
|
|
Adam Phone #: ###-#### Need Electr Final.
|
BLD-Energy code compliance | 4/6/2017 | 4/6/2017 | 4/6/2017 | A | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 4/5/2017 | 4/6/2017 | 4/6/2017 | A | PASS |
Jim Storey
|
|
|
Adam Phone #: ###-####
|
BLD-Framing/Rough-in | 3/28/2017 | 3/29/2017 | 3/29/2017 | A | PART |
Jim Storey
|
|
|
Adam Phone #: ###-#### exterior ok to cover/ pending girder nailling in garage ok to insulate
|
BLD-Framing/Rough-in | 3/27/2017 | 3/28/2017 | 3/28/2017 | A | PART |
Jim Storey
|
|
|
Adam Phone #: ###-#### cn ok to insulate
|
BLD-Wall Bracing | 3/13/2017 | 3/13/2017 | 3/13/2017 | P | PASS |
Jim Storey
|
|
|
Shear // Adam Phone #: ###-####
|
BLD-Footing | 2/9/2017 | 2/9/2017 | 2/9/2017 | P | PASS |
Jim Storey
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
Issue PAID IN FULL permit | | | 2/6/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/23/2017 | | DONE |
|
|
|
|
Telephone call | | | 1/23/2017 | | DONE |
|
|
|
called josh- told him permit is ready and fees due
|
OVERRIDE | | | 1/20/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 12/22/2016 | 12/22/2016 | 1/20/2017 | | DONE |
Brian McGowan
|
|
|
Due 1-4 - fail - WUI compliance must be on the plans. Several beams over the garage did not pass struCalc.
|
Routing - PLAN CHECK | 1/20/2017 | | 1/20/2017 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 1/20/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 1/20/2017 | | DONE |
|
|
|
All Met
|
Inspection Record Card- Bld | | | 1/20/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/18/2017 | | DONE |
|
|
|
Two copies of Member Report and two copies of full set of plans. Taken to Brian Mc
|
1st review completed | | | 1/4/2017 | | FAIL |
Brian McGowan
|
|
|
WUI compliance must be on the plans. Several beams over the garage did not pass struCalc.
|
Routing - PLAN CHECK | 12/28/2016 | | 1/4/2017 | | FAIL |
Brian McGowan
|
|
|
WUI compliance must be on the plans. Several beams over the garage did not pass struCalc.
|
Routing - MECHANICAL | 12/22/2016 | | 12/28/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/21/2016 | | 12/22/2016 | | PASS |
Susan Riggs
|
|
|
MAINTAIN 30' OF DEFENSIBLE SPACE ALONG REAR LOT LINE.
|
Plan assigned to (LEG) Tisha | 12/21/2016 | | 12/22/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - Addressing | 12/21/2016 | | 12/21/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/21/2016 | | 12/21/2016 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/21/2016 | | DONE |
|
|
|
|
Intake Approval | | | 12/21/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/21/2016 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 12/21/2016 | | 12/21/2016 | | DONE |
Brittany Hill
|
|
|
|
Application received | | 12/21/2016 | | | |
|
|
|
|