Second Notice | | 7/22/2017 | 7/21/2017 | | DONE |
|
|
|
This permit finaled on the web by Andrew Stewart
|
First Notice | | 6/30/2017 | 7/12/2017 | | DONE |
|
|
|
Mailed 7-13-17
|
Permanent Occupancy | | | 6/20/2017 | | DONE |
|
|
|
|
BLD-Final | 6/19/2017 | 6/19/2017 | 6/19/2017 | P | PASS |
Mike Jordan
|
|
|
Please call ahead Phone #: ###-#### Inspection requested via web by Andrew Stewart
|
BLD-Final | 6/14/2017 | 6/15/2017 | 6/15/2017 | P | NR |
Dave Hannah
|
|
|
Plumbing final is scheduled for AM, so we should be ready for a final after noon. Thanks, Andrew Phone #: ###-#### Inspection requested via web by Andrew Stewart
|
FIRE-Final Inspection | 5/4/2017 | 5/5/2017 | 5/5/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Ceiling Grid Inspection | 5/2/2017 | 5/2/2017 | 5/2/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andrew Stewart
|
BLD-Framing/Rough-in | 3/15/2017 | 3/15/2017 | 3/15/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Framing/Rough-in | 3/10/2017 | 3/13/2017 | 3/13/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Interior steel stud furred walls and soffits ok.
|
Issue PAID IN FULL permit | | | 3/1/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 3/1/2017 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 2/28/2017 | | DONE |
|
|
|
Andrew emailed the GC and rev cert of val so i emailed him the fees due
|
Plan assigned to (CJW) | 1/6/2017 | 1/6/2017 | 2/21/2017 | | PASS |
Carl Westfall
|
|
|
(1st done) (Jan 26 - 15 days) (Feb 2 - 20 days) (45 sheets) SARMC 3N Cath Lab Remodel
|
Routing - PLAN CHECK | 2/13/2017 | | 2/21/2017 | | PASS |
Carl Westfall
|
|
|
Approved after approved by the Consultant Structural Engineer.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/21/2017 | | DONE |
|
|
|
***MET 2/28/17 CAN***Need GC Form and Revised Cert of Value
|
Routing Off Site - STRUCTURAL | 2/14/2017 | | 2/20/2017 | | PASS |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
Plan resubmittals received | | | 2/13/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 2/7/2017 | 2/10/2017 | 2/8/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/7/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 2/7/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/6/2017 | | 2/7/2017 | | FAIL |
Carl Westfall
|
|
|
Pending structural
|
Routing PW Environmental | 1/9/2017 | | 1/19/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing Off Site - STRUCTURAL | 1/6/2017 | | 1/18/2017 | | FAIL |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
Routing - MECHANICAL | 1/6/2017 | | 1/11/2017 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 1/6/2017 | 1/6/2017 | 1/9/2017 | | PASS |
Katie Marron
|
|
|
No comments attached.
|
Routing - PUBLIC WORKS | 1/6/2017 | | 1/9/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 1/6/2017 | | 1/9/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 1/6/2017 | | 1/6/2017 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 1/6/2017 | | PASS |
David Ferguson
|
|
|
|
Application received | | | 12/22/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 22 2016 10:49AM
|