BLD-Final | 8/7/2017 | 8/7/2017 | 8/7/2017 | P | PASS |
Brandon Shaw
|
|
|
see final notes on 6/12 conference// after 2:30 if you need to go out there. // Donald Phone #: ###-####
|
DOC - Permit Finaled | 8/7/2017 | 8/7/2017 | 8/7/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Conference | 6/12/2017 | 6/12/2017 | 6/12/2017 | P | DONE |
Brandon Shaw
|
|
|
Don Phone #: ###-#### Final good, no issues, pending electrical rough in and final
|
Permit Ready to Issue | | | 6/12/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/12/2017 | | DONE |
|
|
|
Plan Mod
|
BLD-Footing | 4/28/2017 | 5/1/2017 | 5/1/2017 | A | PASS |
Brandon Shaw
|
|
|
would like call ahead; Dustin Phone #: ###-####
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2017 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 4/19/2017 | 4/19/2017 | 4/19/2017 | P | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 4/19/2017 | | DONE |
David Ferguson
|
|
|
|
Routing Walk-In (Zoning) | 4/13/2017 | 4/13/2017 | 4/13/2017 | P | PASS |
Ted Vanegas
|
|
|
|
Routing Walk-In (BLD) | 4/13/2017 | 4/13/2017 | 4/13/2017 | P | FAIL |
David Ferguson
|
|
|
Need a copy of the approved plans. Wrong plans scanned into case file.
|
Plan Modification Accepted | | | 4/13/2017 | | DONE |
|
|
|
modification being made to the exterior layout
|
Routing Walk-In (BLD) | 12/28/2016 | 12/28/2016 | 12/28/2016 | A | FAIL |
David Ferguson
|
|
|
Need to make plan sheets match with each other and customer wants to bump out the entry an additional 1.5 ft. He will revise plans and come back in.
|
Routing Walk-In (Zoning) | 12/28/2016 | 12/28/2016 | 12/28/2016 | P | PASS |
Jeff Lowe
|
|
|
size of building has changed - site has been revised /CEV
|
Routing Walk-In (BLD) | 12/28/2016 | 12/28/2016 | 12/28/2016 | P | PASS |
David Ferguson
|
|
|
|
Plan assigned to (DAF) | 12/28/2016 | 12/28/2016 | 12/28/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 12/28/2016 | | 12/28/2016 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 12/28/2016 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 12/28/2016 | | DONE |
David Ferguson
|
|
|
|
Permit Ready to Issue | | | 12/28/2016 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 12/28/2016 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 12/27/2016 | 12/27/2016 | 12/27/2016 | P | PASS |
Leon Letson
|
|
|
|
Routing Walk-In (BLD) | 12/27/2016 | 12/27/2016 | 12/27/2016 | P | FAIL |
Brian McGowan
|
|
|
Needed more comprehensive plans with dimensions, wall section, stair section to show head height and stair way compliance.
|
1st review completed | | | 12/27/2016 | | DONE |
Brian McGowan
|
|
|
|
Application received | | 12/27/2016 | | | |
|
|
|
|