Second Notice | | 6/22/2017 | 6/15/2017 | | DONE |
|
|
|
This permit finaled on the web by Shawn Metier
|
First Notice | | 5/11/2017 | 6/12/2017 | | DONE |
|
|
|
Mailed 6-13-17
|
BLD-Final | 5/1/2017 | 5/1/2017 | 5/1/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson. Ok for perm occ.
|
FIRE-Final Inspection | 5/1/2017 | 5/1/2017 | 5/1/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Permanent Occupancy | | | 5/1/2017 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson
|
BLD-Framing/Rough-in | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson. Interior steel stud framed wall for conferance/breakroom ok.
|
BLD-Final | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson. Issues with the key faub system have been resolved. Ok to occupy south east portion of building.
|
BLD-Final | 3/31/2017 | 3/31/2017 | 3/31/2017 | A | PART |
Mike Jordan
|
|
|
Partial/temp Phone #: ###-#### Inspection requested via web by Richard Wilson. A temp. occ. has been given with the understanding that the card reader system that was installed will remain disabled until the architect submits a plan mod showing the card readers to plan review for approval. This is for the south east corner of the building only. (flex room, Finance room).
|
FIRE-Final Inspection | 3/30/2017 | 3/30/2017 | 3/30/2017 | A | PART |
Troy Cobbley
|
|
|
Life safety passed in the second floor south east corner office remodel. Waiting for the conference room/office area to be completed before a final is given.
|
BLD-Ceiling Grid Inspection | 3/17/2017 | 3/17/2017 | 3/17/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Ceiling Grid Inspection | 3/16/2017 | 3/17/2017 | 3/17/2017 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson. Electrical rough in failed. moved to pm.
|
BLD-Ceiling Grid Inspection | 3/2/2017 | 3/3/2017 | 3/3/2017 | A | PASS |
Mike Jordan
|
|
|
Fat grid ceilings in restrooms Phone #: ###-#### Inspection requested via web by Richard Wilson. HArdlid in restrooms ok.
|
BLD-Framing/Rough-in | 2/27/2017 | 2/28/2017 | 2/28/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson. Suite 200- Interior steel stud framed walls for restroom, lactation room and flex area.
|
Print Occupancy Form | | | 2/8/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/8/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/6/2017 | | DONE |
Christina Prado
|
|
|
Need GC & revised certificate of value for issuance
|
Plan assigned to (JG) | 1/3/2017 | 1/3/2017 | 2/3/2017 | | PASS |
Javier Guzman
|
|
|
1st review completed, 1/16 L2 Kendall Auto Group NAFCO
|
Routing - PLAN CHECK | 2/3/2017 | | 2/3/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/3/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/17/2017 | 1/20/2017 | 1/18/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 1/3/2017 | | 1/17/2017 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 1/17/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 1/3/2017 | | 1/3/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/3/2017 | | 1/3/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 1/3/2017 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 12/28/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 28 2016 11:34AM
|