BLD-Final | 11/15/2017 | 11/15/2017 | 11/15/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
DOC - Permit Finaled | 11/15/2017 | 11/15/2017 | 11/15/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 9/28/2017 | 9/28/2017 | 9/28/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Framing/Rough-in | 9/27/2017 | 9/28/2017 | 9/28/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Wall cover | 9/26/2017 | 9/26/2017 | 9/26/2017 | A | PART |
Jim Storey
|
|
|
north soffit ok to cover
|
BLD-Framing/Rough-in | 9/19/2017 | 9/19/2017 | 9/20/2017 | P | CANC |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Wall Bracing | 8/21/2017 | 8/21/2017 | 8/21/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Foundation | 6/22/2017 | 6/22/2017 | 6/23/2017 | P | PART |
Jim Storey
|
|
|
Joe Phone #: ###-####
|
BLD-Footing | 6/20/2017 | 6/20/2017 | 6/20/2017 | P | PASS |
Brandon Shaw
|
|
|
James Phone #: ###-####
|
Expiration Notice | 6/5/2017 | 6/26/2017 | 6/5/2017 | | DONE |
Brittany Hill
|
|
|
|
Issue PAID IN FULL permit | | | 6/5/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 5/22/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 5/22/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/19/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/19/2017 | | 5/19/2017 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/19/2017 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 1/9/2017 | | 5/19/2017 | | DONE |
Tisha Gallop
|
|
|
3rd review 4/3 (need eng. for eng. shear lines); 2nd review 3/20; 1st review 1/18; plan check (see changemarks)
|
Plan resubmittals received | | | 4/18/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/14/2017 | | 4/18/2017 | | FAIL |
Tisha Gallop
|
|
|
did not address previous comments (engineering or presc. compliance for three wall bracing lines)
|
Routing - MECHANICAL | 3/31/2017 | | 4/3/2017 | | PASS |
Chad Schwendiman
|
|
|
revised man J
|
Plan resubmittals received | | | 3/31/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/31/2017 | | 3/31/2017 | | FAIL |
Tisha Gallop
|
|
|
need calcs for engineered wall lines
|
Routing - Design Review | 3/31/2017 | | 3/31/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Design Review | 3/19/2017 | | 3/20/2017 | | FAIL |
Andrea Tuning
|
|
|
Front setback is required to be 15-feet from the front property line.
|
Routing - PLAN CHECK | 3/19/2017 | | 3/20/2017 | | FAIL |
Tisha Gallop
|
|
|
in addition to comments, need new Man J per Chad S.
|
OVERRIDE | | | 3/15/2017 | | |
|
|
|
|
CHANGE STATUS TO (REV) | | | 3/15/2017 | | DONE |
|
|
|
was made RDY by mistake
|
Permit Ready to Issue | | | 3/15/2017 | | DONE |
|
|
|
please make sure the PRK fees have been verified before fees are paid-demo on existing home so may have less fees-emailed Tonya
|
Plan resubmittals received | | | 3/14/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/9/2017 | | 1/18/2017 | | FAIL |
Tisha Gallop
|
|
|
see changemarks
|
1st review completed | | | 1/18/2017 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 1/9/2017 | | 1/10/2017 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 1/9/2017 | | 1/9/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Addressing | 1/9/2017 | | 1/9/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/9/2017 | | 1/9/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2017 | | DONE |
|
|
|
|
Intake Approval | | | 1/9/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/9/2017 | | DONE |
|
|
|
|
Application received | | | 12/28/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 28 2016 1:02PM
|