BLD-Final | 5/4/2017 | 5/4/2017 | 5/4/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
DOC - Permit Finaled | 5/4/2017 | 5/4/2017 | 5/4/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 3/21/2017 | 3/22/2017 | 3/22/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Framing/Rough-in | 3/21/2017 | 3/22/2017 | 3/22/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Framing/Rough-in | 3/19/2017 | 3/20/2017 | 3/20/2017 | A | FAIL |
Mike Jordan
|
|
|
HVAC had to call in for an am re-inspection. Please make one of your last am stops. Builder will be happy to meet on site to go over corrections. Phone #: ###-#### Inspection requested via web by Andy Thompson. Provide truss engineering. Provide tempered glazing on window at 2nd. floor to balcony. Provide (2) 2x6 headers on doorways to laundry room and bedroom(archway). Fireblock at B vent at ceiling 2nd. floor. ok to insulate. Correction notice issued.
|
BLD-Wall Bracing | 3/2/2017 | 3/3/2017 | 3/3/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
(F) Reprint permit | | | 2/22/2017 | | DONE |
|
|
|
|
BLD-Foundation | 2/13/2017 | 2/14/2017 | 2/14/2017 | A | PART |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 2/10/2017 | 2/13/2017 | 2/13/2017 | A | PART |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 2/10/2017 | 2/10/2017 | 2/10/2017 | P | CANC |
Dave Hannah
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/10/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/10/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 1/30/2017 | | |
|
|
|
|
Telephone call | | | 1/30/2017 | | DONE |
|
|
|
talked to Andy on the phone-he wants the credit for the impact fees on this permit-as per Tonia downstairs-no credit can be issued for this lot and as per Valerie & Austin @ ACHD-no credit for impact fees can be done on this permit/lot either-Andy said he would contact them him self because they told him he could get it- I told him to jusst bring us confirmation that they changed there mind and how much is owed
|
Permit Ready to Issue | | | 1/30/2017 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing - PLAN CHECK | 1/23/2017 | | 1/27/2017 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2017 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 1/10/2017 | | 1/27/2017 | | DONE |
Tisha Gallop
|
|
|
1st review 1/19; plan check (see changemarks)
|
Plan resubmittals received | | | 1/23/2017 | | DONE |
|
|
|
|
1st review completed | | | 1/19/2017 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 1/10/2017 | | 1/19/2017 | | FAIL |
Tisha Gallop
|
|
|
see changemarks
|
Route to Impact Fee Review | 1/10/2017 | 1/13/2017 | 1/11/2017 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 1/10/2017 | | 1/11/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 1/10/2017 | | 1/11/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/10/2017 | | 1/10/2017 | | PASS |
Rachael Beierle
|
|
|
CALL WEST BOISE SEWER DISTRICT FOR PERMIT
|
Routing - PLANNING | 1/10/2017 | | 1/10/2017 | | PASS |
Sue Cummings
|
|
|
See redlines. NO duplex
|
Plans ACCEPTED BY PLAN TECH | | | 1/10/2017 | | DONE |
|
|
|
|
Intake Approval | | | 1/10/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/10/2017 | | DONE |
|
|
|
|
Intake Approval | | | 1/4/2017 | | FAIL |
Christina Prado
|
|
|
Need perscriptive notes on plans rather than seperate 8.5X11 sheet
|
Application received | | | 12/30/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 30 2016 11:26AM
|