First Notice | | 3/12/2017 | 4/13/2017 | | DONE |
Christina Prado
|
|
|
mailed 4/14
|
BLD-Final | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
Permanent Occupancy | | | 3/2/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/28/2017 | 3/1/2017 | 3/1/2017 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modofcations, fire alarm inspection complete, final commercial hood fire suppression system inspection complete, fire extinguishers are mounted with current inspection tags. Final life fire safety inspection passed/complete
|
BLD-Final | 2/28/2017 | 2/28/2017 | 3/1/2017 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 2/3/2017 | 2/3/2017 | 2/3/2017 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####,, walls ok to cover
|
BLD-Wall Bracing | 2/2/2017 | 2/3/2017 | 2/3/2017 | A | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
Plans ACCEPTED BY PLAN TECH | | | 1/30/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/30/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/30/2017 | | DONE |
|
|
|
|
Plan assigned to (DAF) | 1/17/2017 | 1/17/2017 | 1/20/2017 | | DONE |
David Ferguson
|
|
|
due 1/23
|
Routing - PLAN CHECK | 1/17/2017 | | 1/20/2017 | | PASS |
David Ferguson
|
|
|
|
1st review completed | | | 1/20/2017 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/20/2017 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Routing - FIRE | 1/17/2017 | 1/17/2017 | 1/19/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Environmental | 1/17/2017 | | 1/19/2017 | | PASS |
Rick Christenson
|
|
|
Grease Trap exsiting.
|
Routing - MECHANICAL | 1/17/2017 | | 1/18/2017 | | PASS |
Troy James
|
|
|
New gas/wood fired pizza oven with high temp double wall flue to exterior.
|
Intake Approval | | | 1/17/2017 | | PASS |
David Ferguson
|
|
|
|
Routing - Addressing | 1/17/2017 | | 1/17/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/17/2017 | | 1/17/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 1/10/2017 | | FAIL |
David Ferguson
|
|
|
Since this is a restaurant with an occupant greater than 49, this project will be considered a Major TI with a review time of up to 20 business days instead of 10. Also, additional documentation such as a fire flow letter from Suiz, etc. fire lane access, etc. must be submitted. Please go through our #520 Major TI checklist and provide those additional documents.
|
Application received | | | 1/2/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 2 2017 3:26PM
|