Print Statement | | | 12/19/2017 | | DONE |
|
|
|
|
First Notice | | 11/19/2017 | 12/12/2017 | | DONE |
|
|
|
sent in mail 12-13-17
|
PubWorks Occupancy Approval | 11/13/2017 | 11/13/2017 | 11/13/2017 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | PASS |
Tony Young
|
|
|
Troy Phone #: ###-####
|
FIRE-Final Inspection | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection for core and shell passed/complete.
|
Letter of compliance/Occupancy | | | 11/9/2017 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 11/9/2017 | | DONE |
|
|
|
|
Zoning Approval | 11/2/2017 | 11/2/2017 | 11/2/2017 | | PASS |
Sarah Schafer
|
|
|
|
BLD-Energy code compliance | 9/12/2017 | 9/12/2017 | 9/12/2017 | P | PASS |
Brandon Shaw
|
|
|
Shell only
|
BLD-Framing/Rough-in | 8/21/2017 | 8/22/2017 | 8/22/2017 | A | PART |
Tony Young
|
|
|
Troy Phone #: ###-####,, exterior walls ok to insulate after fixing/adding/tightening sill bolts,, no trades in exterior walls under this permit,, tenent improvment permit has trades
|
BLD-Footing | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | PASS |
Tony Young
|
|
|
Rebar for trash enclosure & pillars in front - Troy Phone #: ###-####
|
BLD-Wall Bracing | 5/2/2017 | 5/3/2017 | 5/3/2017 | A | PART |
Dave Hannah
|
|
|
Jay Phone #: ###-#### ok to cover roof
|
BLD-Wall Bracing | 5/2/2017 | 5/2/2017 | 5/2/2017 | P | NR |
Mike Jordan
|
|
|
Jay Phone #: ###-####. No access to roof. Will recall in the am.
|
BLD-Foundation | 4/5/2017 | 4/6/2017 | 4/6/2017 | A | DEFR |
Mike Jordan
|
|
|
Jay Phone #: ###-####. Work in progress on interior column pad footings. Pending special inspecction.
|
BLD-Footing | 3/28/2017 | 3/29/2017 | 3/29/2017 | P | DEFR |
Mike Jordan
|
|
|
pour at 3 // Jay Phone #: ###-####. Ok to place pending special inspection.
|
BLD-Footing | 3/24/2017 | 3/27/2017 | 3/27/2017 | P | PASS |
Mike Jordan
|
|
|
would like call ahead; Jay Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 2/13/2017 | | |
|
|
|
|
Plan assigned to (CDM) | 1/6/2017 | 1/6/2017 | 2/13/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp. Shell (Black Bear Diner) Due 2/6
|
Routing - PLAN CHECK | 2/9/2017 | | 2/13/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 2/9/2017 | | 2/13/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/13/2017 | | DONE |
Christina Prado
|
|
|
Need RP
|
Route to Impact Fee Review | 1/30/2017 | 2/2/2017 | 1/31/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/30/2017 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 1/6/2017 | | 1/30/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 1/6/2017 | | 1/30/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Environmental | 1/6/2017 | | 1/19/2017 | | PASS |
Rick Christenson
|
|
|
1500 Gallon Exterior Grease Interceptor Shown
|
Routing - PLANNING Land Div | 1/6/2017 | | 1/17/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Sewer Design | 1/6/2017 | | 1/12/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - MECHANICAL | 1/6/2017 | | 1/12/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/6/2017 | | 1/11/2017 | | PASS |
David Moser
|
|
|
|
Routing PW Solid Waste | 1/6/2017 | | 1/11/2017 | | PASS |
Evan Carpenter
|
|
|
The solid waste enclosure is OK as planned.
|
Routing PW Drainage | 1/6/2017 | | 1/11/2017 | | PASS |
Jason C. Taylor
|
|
|
Paver inspection required when project completed. JCT
|
Routing - Design Review | 1/6/2017 | | 1/11/2017 | | PASS |
Sarah Schafer
|
|
|
|
Routing - FIRE | 1/6/2017 | 1/6/2017 | 1/6/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - PLUMBING | 1/6/2017 | | 1/6/2017 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing PW Street Lights | 1/6/2017 | | 1/6/2017 | | PASS |
Tom Marshall
|
|
|
|
Intake Approval | | | 1/6/2017 | | PASS |
|
|
|
|
Routing - Addressing | 1/6/2017 | | 1/6/2017 | | PASS |
Laura Hunter
|
|
|
Corrected address to 7530 W State St
|
Routing - PUBLIC WORKS | 1/6/2017 | | 1/6/2017 | | PASS |
Rachael Beierle
|
|
|
NO FEES YET. SHELL. NO FIXTURES YET.
|
Routing - Erosion and Sediment | 1/6/2017 | | 1/6/2017 | | PASS |
Andy J. Long
|
|
|
ESC narrative and site map approved. Valid PD designated, need to provide RP prior to permit issue.
|
Application received | | | 1/4/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 4 2017 9:53AM
|