Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD17-00022
StatusFinaled
Name WRIGHT BROTHERS THE BLDG CO EAGLE
Site Address 3625 W ELDER ST
Project NameComfort Inn and Suites - ID077
Customer Number 
ePlanReviewYes
Description
(COMFORT SUITES) (Plan Modification for changes to the 4th floor HVAC) For the construction of a new 108 room 4 story wood framed hotel with work to include general site work and utilities. The first story is 15,970 sq. ft. consists of 12 sleeping rooms, a pool, general off, laundry room, lobby and a breakfast area and the 900 sq. ft. porte cochere, the remaining 3 stories are 15,114 sq. ft. each with 32 sleeping units on the 2nd and 3rd stories and 33 units on the 4th story. This building is fully fire sprinklered with an NFPA 13 system for area increase
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Meeting  11/29/2018 DONE
waiting for Rob to sign and return the final value sheet back in
Print Statement  10/24/2018 DONE
Third Notice 9/12/201810/12/2018 DONE
mailed 10-15-18
Second Notice 8/19/20189/7/2018 DONE
mailed 9-10-18
First Notice 8/3/20188/9/2018 DONE
mailed 8-10-18
Permanent Occupancy  7/24/2018 DONE
BLD-Final7/23/20187/23/20187/23/2018PPASS
DetailsJim Storey
Tyler Phone #: ###-####
BLD-Final6/27/20186/28/20186/28/2018APART
DetailsMike Jordan
Tyler Phone #: ###-####. Ok for temp occ. All stairway sing issues have been resolved. Work in progress on correcting ADA issues in indivdual units.
Temporary Occupancy6/28/20189/26/20186/28/2018 DONE
DetailsBrittany Hill
FIRE-Final Inspection6/26/20186/27/20186/27/2018APASS
DetailsTroy Cobbley
Life safety passed

Tyler Phone #: ###-####
BLD-Final6/26/20186/27/20186/27/2018ANR
DetailsDave Hannah
Tyler Phone #: ###-#### needs other trades to final or go to tco also walked site they have several ada items that will need to be fixed also signage in stair towers
FIRE-Final Inspection6/26/20186/26/20186/26/2018PFAIL
DetailsTroy Cobbley
See the city approved fire life safety notes for items that need corrected which include signage, repair one exit sign, final on fire alarm permit, painting on curbing...ect.


Tyler Phone #: ###-####
BLD-Other6/21/20186/22/20186/22/2018PPART
DetailsJim Storey
2nd & 1st floor door swings - Tyler Phone #: ###-#### ok all but 4th east stair and1st hall way
Zoning Approval6/19/20186/19/20186/19/2018 DONE
DetailsAndrea Tuning
BLD-Other6/15/20186/18/20186/18/2018APASS
DetailsJim Storey
fire colking // Tyler Phone #: ###-#### ceillings ok to cover.
BLD-Other6/14/20186/15/20186/15/2018PNR
DetailsMike Jordan
fire caulking, remainder of first floor - tyler Phone #: ###-####. Needs to firecaulk sheet rock at fireproofed beams as per plans.
BLD-Conference6/15/20186/15/20186/15/2018PDONE
DetailsTroy Cobbley
This was a conference with the fire inspector to verify that the fire alarm system was actively monitoring the sprinkler system and that the sprinkler system was live. Furniture can be moved into the project as long as both the fire alarm system and fire sprinkler systems remain active.

Tyler-- conference for fire life safety Phone #: ###-####
PubWorks Occupancy Approval6/15/20186/15/20186/15/2018 DONE
DetailsTiffany Lowery
BLD-Conference6/6/20186/6/20186/6/2018PPASS
DetailsJim Storey
Tyler Phone #: ###-#### doors 3rd and 4th ok
CHANGE STATUS TO (ISS)  6/6/2018 DONE
Print Occupancy Form  6/6/2018 DONE
OVERRIDE  6/5/2018  
BLD-Conference6/4/20186/5/20186/5/2018PPASS
DetailsJim Storey
fire caulking- tyler Phone #: ###-#### 2.3 and 4th ceilling and fire stopping ok
Plan assigned to (CDM)5/21/20185/21/20186/5/2018 PASS
DetailsCarl D Madsen
Plan Mod - ducting on 3rd & 4th level re-routed, additional smoke/fire dampers added
PLANS/APPL TAKEN TO FRONT DESK  6/5/2018 DONE
Permit Ready to Issue  6/5/2018 DONE
PLAN MOD
Routing - PLAN CHECK5/31/2018 6/5/2018 PASS
DetailsCarl D Madsen
Routing - MECHANICAL5/31/2018 6/5/2018 PASS
DetailsTroy James
BLD-Other5/24/20185/25/20185/25/2018AFAIL
DetailsJim Storey
Tyler-fire caulking for floors 4, 3 & 2 in the corridors Phone #: ###-####
BLD-Other5/23/20185/23/20185/23/2018PCANC
DetailsJim Storey
fire caulking insp on floors 4, 3, & 2 in the corridor // Tyler Higgins Phone #: ###-####
Plan Modification Accepted  5/21/2018 DONE
DetailsChristina Prado
Plan Mod - ducting on 3rd & 4th level re-routed, additional smoke/fire dampers added
BLD-Other5/17/20185/18/20185/18/2018PPASS
DetailsJim Storey
Partial fire caulking, 1st/laundry - Tyler Phone #: ###-#### ok to cover ceilling
BLD-Other5/9/20185/10/20185/10/2018PPASS
DetailsJim Storey
fire colking..first floor // Tyler Phone #: ###-#### pool ok
BLD-Other5/8/20185/8/20185/8/2018PPASS
DetailsJim Storey
Pat--Partial fire caulking 1st floor Phone #: ###-#### lobby/breafast area and pool vesabul ceillings ok fire stopping complet
BLD-Other4/6/20184/6/20184/6/2018PPASS
DetailsJim Storey
fire colking Tyler Phone #: ###-####
BLD-Other4/5/20184/6/20184/6/2018ADEFR
DetailsJim Storey
fire colking Tyler Phone #: ###-####
BLD-Other4/4/20184/4/20184/4/2018PNR
DetailsJim Storey
Tyler Phone #: ###-####
BLD-Wall cover4/2/20184/2/20184/2/2018PPASS
DetailsJim Storey
for first floor guest rooms Tyler Phone #: ###-#### aso lobby walls and ceilling ok to cover.
BLD-Energy code compliance3/21/20183/22/20183/22/2018PPASS
DetailsJim Storey
first floor
BLD-Energy code compliance3/20/20183/21/20183/21/2018PNR
DetailsBrandon Shaw
Tyler for first floor Phone #: ###-####
BLD-Other3/14/20183/15/20183/15/2018APART
DetailsJim Storey
fire caulk 1st fl guest rm - Tyler Phone #: ###-#### ok for frame/ ok to proceed with gyp and reinsp fire caulk
BLD-Other3/8/20183/8/20183/8/2018PPASS
DetailsJim Storey
2nd floor guest restroom // Tyler Phone #: ###-####
BLD-Other2/28/20183/1/20183/1/2018APASS
DetailsJim Storey
fire caluking-tyloer Phone #: ###-#### 2nd floor chases ok to insulate and rc
BLD-Other2/22/20182/22/20182/22/2018PPASS
DetailsJim Storey
Fire caulking - Tyler Phone #: ###-#### 3rd floor rooms/ east stair insulated ok to cover.
BLD-Energy code compliance2/21/20182/21/20182/22/2018PPART
DetailsDave Hannah
3rd floor-Taylor Phone #: ###-#### insulation ok ok to cover
BLD-Other2/12/20182/12/20182/12/2018PPASS
DetailsJim Storey
fire caulking 3rd floor gues rooms // Tyler Phone #: ###-####
BLD-Wall cover2/9/20182/9/20182/9/2018PPASS
DetailsJim Storey
part // Tyler Phone #: ###-#### 3rd floor ok to prerock all bath rooms
BLD-Other2/8/20182/8/20182/8/2018PPASS
DetailsJim Storey
Tyler-Partial fire caulking-4th floor guest restrooms Phone #: ###-#### ok and ceilling first floor ok to cover
FIRE-Sprinkler Rough-in1/31/20181/31/20181/31/2018PCANC
DetailsTroy Cobbley
Wrong inspector sourced

colk // Tyler Phone #: ###-####
BLD-Other1/23/20181/24/20181/24/2018APART
DetailsJim Storey
10-20 grid line- fire caulking- Tyler Phone #: ###-#### can light gyp boxes ok need fire stopping/ oversized membrane penatrations need patch of gyp / fireblk plate hole/ fireproofing incapsilation of tube and beams.
BLD-Other1/19/20181/19/20181/19/2018PPART
DetailsBrandon Shaw
West half, 4th floor corridor- fire caulk
BLD-Other1/16/20181/17/20181/17/2018AFAIL
DetailsJim Storey
Fire colking ... 4th // Tyler Phone #: ###-####
BLD-Framing/Rough-in1/10/20181/10/20181/10/2018PPART
DetailsJim Storey
Tyler,-partial 2, 3, 4 floors Phone #: ###-#### rc ok // truss hanger // rat run// can light// ok to pre rock
BLD-Wall Bracing1/10/20181/10/20181/10/2018PPASS
DetailsJim Storey
Tyler Phone #: ###-####-partial wall bracing and frame on 2,3,and 4th foor pending rfi from egn. perfarated sheer ok or not
BLD-Energy code compliance1/4/20181/5/20181/5/2018APASS
DetailsJim Storey
Tyler Phone #: ###-#### 2nd floor corridor ok
BLD-Energy code compliance1/4/20181/4/20181/4/2018PDEFR
DetailsJim Storey
Tyler Phone #: ###-#### out of time
BLD-Energy code compliance1/2/20181/3/20181/3/2018APASS
DetailsJim Storey
partial thermal insp for 3rd floor corridor // Tyler Phone #: ###-#### rockwool ok 4 th fl. rc and pre rock ok tubs and chase walls
BLD-Wall Bracing12/28/201712/29/201712/29/2017APASS
DetailsDave Hannah
north exerior - tyler Phone #: ###-####
BLD-Wall Bracing12/26/201712/27/201712/27/2017APASS
DetailsJim Storey
Partial shear, West end exterior - Tyler Phone #: ###-#### west end ok to cover
BLD-Energy code compliance12/21/201712/21/201712/21/2017PPASS
DetailsJim Storey
Tyler Phone #: ###-#### r 30 ok at roof corridor
BLD-Framing/Rough-in12/21/201712/21/201712/21/2017PPART
DetailsJim Storey
Tyler Phone #: ###-####corridor 2 thur 4 ok to gyp ceilling/ r 30 ok at roof
BLD-Wall cover12/14/201712/15/201712/15/2017PPASS
DetailsJim Storey
Tyler-partial bracing on east and south side Phone #: ###-####east and south side sheer ok to cover/ roof nailling ok/ pre rock ok to aply at tubs and hvac areas.
BLD-Ceiling Grid Inspection12/14/201712/15/201712/15/2017PPASS
DetailsJim Storey
Tyler-grid lines 12 thru 20 Phone #: ###-#### east and south side sheer ok to cover/ roof nailling ok/ pre rock ok to aply at tubs and hvac areas.
BLD-Other11/21/201711/22/201711/22/2017APASS
DetailsJim Storey
roof nailng-(grid lines 1-12 on roof) Bob Phone #: ###-#### west end
BLD-Other8/29/20178/30/20178/30/2017APASS
DetailsJim Storey
steal column- Bob Phone #: ###-####
Telephone call  6/7/2017 DONE
called Terry to let know we received all fees but the ACHD fees-can't issue permits until paid-left message on her phone
Issue PAID IN FULL permit  6/7/2017 DONE
DetailsChristina Prado
Print Occupancy Form  6/7/2017 DONE
DetailsChristina Prado
Meeting  5/31/2017 DONE
Bob Goodwin came in and gve me #302 & # 306, RP-still need ACHD-i gave him the number for Morgan (ACHD) to find out what is left to do to get the plans approved thru them. I gave Bob the fees due for us and wrote on there does not include ACHD
OVERRIDE  5/30/2017  
Permit Ready to Issue  5/30/2017 DONE
DetailsChristina Prado
***received a payment in mail STILL need ACHD 6/7/17 CAN******received RP, GC & rev cert-still need ACHD 5-31-17 CAN***Need ACHD, RP, GC form & Revised certificate of value for issuance
Plan assigned to (CDM)1/19/20171/19/20175/29/2017 PASS
DetailsCarl D Madsen
1st comp. COMFORT SUITES Due 2/19
Routing - PLAN CHECK5/22/2017 5/29/2017 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL5/22/2017 5/29/2017 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  5/29/2017 DONE
Routing - Design Review5/22/2017 5/23/2017 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK3/29/2017 4/12/2017 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL3/29/2017 4/12/2017 FAIL
DetailsCarl D Madsen
Routing PW Sewer Design3/29/2017 4/10/2017 PASS
DetailsKyle S. Rosenmeyer
Routing - FIRE3/29/20173/29/20173/31/2017 PASS
DetailsKatie Marron
Revised report attached to case.
Routing - Design Review3/31/2017 3/31/2017 FAIL
DetailsAndrea Tuning
Construct a pedestrian walkway that extends directly from the main entrance to Elder Street.

The parking stalls located along the north porperty line will be required to be 20-feet in length or provide a 22-foot landsacpe buffer along Elder Street to accomodate for the bumper overhang.
Routing - MECHANICAL3/29/2017 3/31/2017 PASS
DetailsTroy James
Routing - PUBLIC WORKS3/29/2017 3/29/2017 PASS
DetailsRachael Beierle
Route to Impact Fee Review2/27/20173/2/20173/6/2017 PASS
DetailsTonya Wallace
Review requested for Commercial Permit
Routing - FIRE2/23/20171/19/20172/24/2017 FAIL
DetailsScott Arellano
Report attached to case and emailed to architect.
1st review completed  2/24/2017 DONE
DetailsCarl D Madsen
Routing - Design Review2/23/2017 2/23/2017 FAIL
DetailsAndrea Tuning
Routing Off Site - STRUCTURAL1/19/2017 2/23/2017 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK1/19/2017 2/23/2017 FAIL
DetailsCarl D Madsen
Routing PW Drainage2/8/2017 2/22/2017 PASS
DetailsBrian Murphy
Routing PW Environmental2/8/2017 2/21/2017 PASS
DetailsRick Christenson
Routing - PLANNING Land Div1/19/2017 2/17/2017 PASS
DetailsTodd Tucker
Routing - MECHANICAL1/19/2017 2/16/2017 FAIL
DetailsTroy James
Routing PW Solid Waste2/8/2017 2/13/2017 PASS
DetailsEvan Carpenter
Solid waste is OK as planned.
Routing - PLUMBING1/19/2017 2/10/2017 PASS
DetailsBill VanDegrift
Per plan and ISPC.
Routing - Erosion and Sediment1/19/2017 2/9/2017 PASS
DetailsAndy J. Long
BMPs: Stabilized construction entrances (4) one on Elder street and three on the east side of the site, permit signs, DI protection, lined water based waste trench, trash disposal, fiber roll on the south east corner of the site, silt fence as needed (site slopes east to west so potentially on the west side of site). RP TBD.
Routing - PLANNING1/19/2017 2/8/2017 PASS
DetailsSusan Riggs
Routing PW Sewer Design2/8/2017 2/8/2017 FAIL
DetailsKyle S. Rosenmeyer
Existing sewer service does not exist. Connect new service to existing 10" sewer main with insert-a-tee connection and Type "D" configuration. Maintain minimum slope of 2% in the public R/W. Contact Boise Public Works 48 hours prior to making connection to obtain tap permit and schedule inspection.
Routing PW Street Lights2/8/2017 2/8/2017 PASS
DetailsTom Marshall
Routing - Addressing1/19/2017 2/8/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS1/19/2017 2/8/2017 PASS
DetailsRachael Beierle
REVIEWED BY RMB. PERMIT INCLUDES HOTEL, POOL, AND DINING. NO ASSESSMENT PER MS. MUST SUPPLY OWN SERVICE LINE.

Routing - Design Review1/19/2017 2/8/2017 FAIL
DetailsAndrea Tuning
Intake Approval  1/19/2017 PASS
Intake Approval  1/13/2017 FAIL
DetailsDavid Ferguson
First page of #310 form is incomplete.
Intake Approval  1/12/2017 FAIL
DetailsDavid Ferguson
Please provide a completed #502 Checklist so that I can start the pre-screen process.
Application received  1/5/2017 DONE
Application submitted via PDS Online on Jan 5 2017 4:53PM