Permit Information
Permit NumberBLD17-00059
StatusFinaled
Name HILL CONSTRUCTION & PROPERTY SERVIC
Site Address 6125 W POPLAR ST
Project Name 
Customer Number 
ePlanReviewYes
Description
Permit for demolition of existing dwelling and detached garage and construct a new 1488 sq. ft., two story (first story 844 sq. ft., second story 644 sq. ft.) single family dwelling with 3 bedrooms, 3 bathrooms, approximately 38 sq. ft. of covered patio/porch and a 418 sq. ft. detached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning. //leg
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/26/20181/29/20181/29/2018APASS
DetailsJim Sly
Dean Phone #: ###-####
DOC - Permit Finaled1/29/20181/29/20181/29/2018PPASS
DetailsJim Sly
BLD-Framing/Rough-in12/8/201712/8/201712/11/2017PPASS
DetailsJim Sly
Dean Phone #: ###-####
BLD-Wall Bracing12/1/201712/4/201712/4/2017APASS
DetailsJim Sly
Dean Phone #: ###-####
BLD-Energy code compliance11/8/201711/8/201711/8/2017PPASS
DetailsJim Sly
Dean Phone #: ###-####
BLD-Framing/Rough-in11/6/201711/6/201711/6/2017PPASS
DetailsJim Sly
Dean Phone #: ###-####
BLD-Foundation10/25/201710/26/201710/26/2017APASS
DetailsJim Sly
Dean Phone #: ###-####
Garage
BLD-Foundation10/24/201710/25/201710/25/2017ANR
DetailsJim Sly
Dean Phone #: ###-####
BLD-Footing10/18/201710/19/201710/19/2017APASS
DetailsJim Sly
Dean Phone #: ###-####
BLD-Wall Bracing8/21/20178/21/20178/21/2017PPASS
DetailsJim Storey
Shear // Dean Phone #: ###-####
BLD-Wall cover8/17/20178/18/20178/18/2017AFAIL
DetailsBrandon Shaw
No plans on site
BLD-Foundation4/19/20174/20/20174/20/2017APASS
DetailsJim Sly
Dean Phone #: ###-####
BLD-Footing4/18/20174/19/20174/19/2017APASS
DetailsJim Sly
Gene Phone #: ###-####
BLD-Footing4/17/20174/18/20174/18/2017ANR
DetailsJim Sly
Gene Phone #: ###-####
Issue PAID IN FULL permit  3/27/2017 DONE
Inspection Record Card- Bld  3/27/2017 DONE
OVERRIDE  2/21/2017  
Plan assigned to (LEG) Tisha1/18/2017 2/21/2017 DONE
DetailsTisha Gallop
1st review 1/31; plan check (planning if new site plan uploaded)
Routing - PLANNING2/10/2017 2/21/2017 PASS
DetailsSarah Schafer
revised site plan - Approved per DRH16-00492.
PLANS/APPL TAKEN TO FRONT DESK  2/21/2017 DONE
Permit Ready to Issue  2/21/2017 DONE
DetailsChristina Prado
All requirements met
Plan resubmittals received  2/10/2017 DONE
Routing - PUBLIC WORKS2/10/2017 2/10/2017 PASS
DetailsRachael Beierle
Routing - Addressing2/10/2017 2/10/2017 PASS
DetailsLaura Hunter
Routing - PLAN CHECK2/10/2017 2/10/2017 PASS
DetailsTisha Gallop
Routing - Addressing1/31/2017 1/31/2017 PASS
DetailsLaura Hunter
Address of new dwelling is 6125 W Poplar St
1st review completed  1/31/2017 FAIL
Routing - PLAN CHECK1/18/2017 1/31/2017 FAIL
DetailsTisha Gallop
Routing - MECHANICAL1/18/2017 1/23/2017 PASS
DetailsTroy James
Route to Impact Fee Review1/18/20171/21/20171/19/2017 PASS
DetailsCindy M. Gould
Initial residential review of all new news permit requested for now.
Routing - PLANNING1/18/2017 1/19/2017 PASS
DetailsJosh Wilson
Routing - Addressing1/18/2017 1/18/2017 FAIL
DetailsLaura Hunter
Need to do a lot split and get new parcels from Ada County
Routing - PUBLIC WORKS1/18/2017 1/18/2017 FAIL
DetailsMorgan Webb
NO DEMO AND ADDRESSING ISSUES
Plans ACCEPTED BY PLAN TECH  1/18/2017 DONE
Intake Approval  1/18/2017 PASS
Recd Pcfee & Taken To Pln CK  1/18/2017 DONE
Application received  1/17/2017 DONE
Application submitted via PDS Online on Jan 17 2017 10:02AM
Intake Approval  1/17/2017 FAIL
DetailsChristina Prado
Thom,

Please revise the site plan to reflect current state, or resubmit when the demo & record of survey are in place.

Christina ###-####