BLD-Aging Inspection | 12/14/2017 | 12/14/2017 | 12/15/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 12/13/2017 | 12/13/2017 | 12/14/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 7/31/2017 | 8/1/2017 | 8/1/2017 | A | PASS |
Tony Young
|
|
|
kenji Phone #: ###-#### - call 15 mins prior
|
BLD-Framing/Rough-in | 7/19/2017 | 7/20/2017 | 7/20/2017 | P | PART |
Tony Young
|
|
|
Please call 20 mins ahead -Kenji Phone #: ###-####,, floor joists ok
|
OVERRIDE | | | 3/27/2017 | | |
|
|
|
|
Routing Walk-In (BLD) | 3/27/2017 | 3/27/2017 | 3/27/2017 | P | PASS |
Tisha Gallop
|
|
|
As per Andy - general ESC ok, no waiver needed;
|
Inspection Record Card- Bld | | | 3/27/2017 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 3/27/2017 | | 3/27/2017 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/27/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/27/2017 | | DONE |
|
|
|
|
Meeting | | | 3/14/2017 | | DONE |
|
|
|
customer in office, gave all failed plans and documents back to applicant (homeowner) per his request.
|
Routing PW Grading-Hillside | 2/24/2017 | | 2/27/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing PW Flood Plain | 2/24/2017 | | 2/27/2017 | | PASS |
Jason C. Taylor
|
|
|
Not considered substantial improvement. No elevation certificate needed. JCT
|
Plan assigned to (LEG) Tisha | 2/24/2017 | | 2/27/2017 | | DONE |
Tisha Gallop
|
|
|
1st review 2/27; eng. foundation (I have plans)
|
Telephone call | | | 2/27/2017 | | DONE |
|
|
|
called Walter Poly. Told him no floodplain requirements, geotech subgrade inspection is requried, need engineered foundation calcs and details.
|
Routing Walk-In (BLD) | 2/24/2017 | 2/24/2017 | 2/24/2017 | P | FAIL |
Tisha Gallop
|
|
|
need engineering for foundation; routed to floodplain and hillside review
|
Route to Impact Fee Review | 1/17/2017 | 1/20/2017 | 1/18/2017 | | PASS |
Cindy M. Gould
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing Walk-In (Zoning) | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | FAIL |
Brian McGowan
|
|
|
Project needs foundation engineered, flood plain certificate, section completed and a more detailed scope of work.
|
1st review completed | | | 1/17/2017 | | FAIL |
Brian McGowan
|
|
|
Project needs foundation engineered, flood plain certificate, section completed and a more detailed scope of work.
|
Routing - PLAN CHECK | 1/17/2017 | | 1/17/2017 | | FAIL |
Brian McGowan
|
|
|
Project needs foundation engineered, flood plain certificate, section completed and a more detailed scope of work.
|
Application received | | 1/17/2017 | | | |
|
|
|
|