Permit Information
Permit NumberBLD17-00066
StatusIssued
Name ST LUKES REGIONAL MEDICAL CENTER LT
Site Address 190 E BANNOCK ST
Project NameElevator Install - St. Luke's
Customer Number 
ePlanReviewYes
Description
(NEW ELEVATORS – EXISTING ELEVATOR TOWER – ST. LUKE’S HOSPITAL TOWER) The fire sprinkler system is used for high-rise and for occupancy. To install 2 new elevators in an existing elevator hoistway shaft. The shaft will be restored to 2-hr fire-resistance-rated construction where deficient. The new elevators will serve 11 stories. Demolition work includes removing infill floors at each floor level within the existing elevator hoistway shaft. An opening will be created in the penthouse floor to facilitate elevator cab installation and hoistway venting. Openings will be created in the penthouse roof to accommodate the hoistway vent and the ducts from the new roof top HVAC units. Work is to include a 2-hr hoistway vent shaft at the top of the elevator hoistway, a gravity ventilator hood on the roof, two roof top HVAC units to condition the elevator equipment room, hoistway beams, concrete roof infills, elevator blocking beams, elevator equipment, structural separator beams, 2-hr walls to restore the 2-hr fire-resistance-rating of the elevator shaft, an elevator pit concrete slab, two new elevators, elevator hoistway shaft doors having a fire-protection-rating of at least 90 minutes at each story, structural sills at each elevator door, and new elevator lobby finishes including repairs to the suspended acoustical ceilings. Special Inspection is required for anchors post-installed in hardened concrete (expansion and epoxy) and for welding. The existing elevator lobby enclosures are required to be maintained on each story. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. Egress paths for each story are required to be maintained at all times. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall cover7/14/20207/14/20207/14/2020PPASS
DetailsDave Hannah
Kelly < he was out state and just got back Phone #: ###-####
BLD-Aging Inspection3/9/20203/9/20203/9/2020AFAIL
DetailsJim Page
Reference notes entered on 21OCT2019, fire alarm permit FIR18-00106 has not been finaled as of this entry, permit is required to finaled before life fire safety can be completed.
BLD-Aging Inspection3/5/20203/5/20203/9/2020 PEND
DetailsDave Hannah
BLD-Aging Inspection3/4/20203/4/20203/9/2020 PEND
DetailsDave Hannah
FIRE-Final Inspection10/22/201910/22/201910/22/2019PPART
DetailsJim Page
Partial final inspection for fire life safety is complete, TCO for elevator use is approved per conversation with Ron Johnson with Boise Fire, contingent upon fire alarm inspection for job attached FIR permit is finaled. This permit can be finaled when mentioned fire alarm permit is finaled.

KELLY Phone #: ###-####
FIRE-Final Inspection10/21/201910/21/201910/21/2019PCANC
DetailsTroy Cobbley
Canceled due to work load. Kelly Phone #: ###-####
FIRE-Conference10/11/201910/11/201910/11/2019ADONE
DetailsJim Page
Fire conference complete.
FIRE-Final Inspection10/10/201910/11/201910/11/2019ACANC
DetailsJim Page
Request was for a conference, this request is cancelled.

Stan Phone #: ###-####
FIRE-Final Inspection10/7/201910/8/201910/8/2019ACANC
DetailsJim Page
Need project related fire alarm inspection inspected and passed before life fire safety inspection can be completed, point of contact provided has been notified. This request is cancelled and will be rescheduled to coincide with project related fire alarm inspection at a later date.

Kelly Phone #: ###-####
Issue PAID IN FULL permit  3/27/2017 DONE
(F) Reprint permit  3/27/2017 DONE
Plan assigned to (CJW)1/20/20171/20/20173/13/2017 PASS
DetailsCarl Westfall
(1st done) (Feb 9 - 15 days) (67 sheets) St. Lukes elevator
Routing - PLAN CHECK3/8/2017 3/13/2017 PASS
DetailsCarl Westfall
Approved after approved by the consultant structural engineer
PLANS/APPL TAKEN TO FRONT DESK  3/13/2017 DONE
Permit Ready to Issue  3/13/2017 DONE
Need GC Form and Revised Cert of Value
Routing Off Site - STRUCTURAL3/8/2017 3/9/2017 PASS
DetailsCarl Westfall
Jorday Terry - KPFF
Plan resubmittals received  3/8/2017 DONE
Route to Impact Fee Review2/13/20172/16/20172/15/2017 PASS
DetailsCindy M. Gould
Review requested for Commercial Permit
1st review completed  2/13/2017 DONE
Plan resubmittals requested  2/13/2017 DONE
Routing - PLAN CHECK1/20/2017 2/13/2017 FAIL
DetailsCarl Westfall
Routing Off Site - STRUCTURAL1/20/2017 2/2/2017 FAIL
DetailsCarl Westfall
Jorday Terry KPFF
Routing - MECHANICAL1/20/2017 1/24/2017 PASS
DetailsTroy James
Routing - FIRE1/20/20171/20/20171/23/2017 PASS
DetailsKatie Marron
Comments attached to case.
Routing - ELECTRICAL1/20/2017 1/23/2017 CANC
DetailsJavier Guzman
Per city ordinance no electrical review required
Intake Approval  1/20/2017 PASS
Application received  1/17/2017 DONE
Application submitted via PDS Online on Jan 17 2017 1:49PM
Intake Approval  1/17/2017 FAIL
Please upload the structural sheet in the correct orientation as well as the correct sheet size of a minimum of 18 x 24. The current structural sheets are 11 x 17,