Third Notice | | 12/17/2017 | 12/19/2017 | | DONE |
|
|
|
This permit finaled on the web by T.J. Wilcomb
|
Third Notice | | 11/19/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
Second Notice | | 10/22/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
First Notice | | 10/12/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
PubWorks Occupancy Approval | 10/3/2017 | 10/3/2017 | 10/3/2017 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 10/2/2017 | | DONE |
|
|
|
|
BLD-Final | 9/28/2017 | 9/29/2017 | 9/29/2017 | A | PASS |
Jim Storey
|
|
|
Jake Phone #: ###-#### final ok pending pw sign off
|
FIRE-Final Inspection | 9/28/2017 | 9/28/2017 | 9/28/2017 | P | PASS |
Jim Page
|
|
|
No fire sprinkler, no fire alarms, fire extinguisher will be mounted in discussed location, all have current inspection tags. Final life fire safety inspection passed/complete.
|
Zoning Approval | 8/31/2017 | 8/31/2017 | 8/31/2017 | | PASS |
Sarah Schafer
|
|
|
|
BLD-Framing/Rough-in | 7/17/2017 | 7/18/2017 | 7/18/2017 | A | PASS |
Jim Storey
|
|
|
Jake Black Phone #: ###-####
|
BLD-Framing/Rough-in | 6/23/2017 | 6/23/2017 | 6/23/2017 | P | PASS |
Jim Storey
|
|
|
Jacob Phone #: ###-#### cooller walls and cielling ok
|
BLD-Framing/Rough-in | 5/10/2017 | 5/10/2017 | 5/10/2017 | P | PART |
Jim Storey
|
|
|
Jacob Phone #: ###-#### restarm frame and bar area ok to cover/ pending 3hr top of rating details.
|
CHANGE STATUS TO (ISS) | | | 5/10/2017 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 5/8/2017 | | |
|
|
|
|
Plan assigned to (JG) | 5/3/2017 | 5/3/2017 | 5/8/2017 | | PASS |
Javier Guzman
|
|
|
Plan Modification Lost Grove Brewery Cooler
|
Routing - PLAN CHECK | 5/3/2017 | | 5/8/2017 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 5/8/2017 | | DONE |
Christina Prado
|
|
|
All requirements met for Plan Modification
Fees must be paid in full, DO NOT RE-ISSUE
|
Routing - FIRE | 5/3/2017 | 5/3/2017 | 5/4/2017 | | PASS |
Katie Marron
|
|
|
Modification to create a cold storage space within existing building footprint. No changes to previous review comments.
|
Issue PAID IN FULL permit | | | 3/28/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/28/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/27/2017 | | |
|
|
|
|
Plan assigned to (JG) | 1/24/2017 | 1/24/2017 | 3/27/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 2/16 L3 Lost Grove Brewery Level III E Plan
|
Routing - PLAN CHECK | 3/22/2017 | | 3/27/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2017 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/27/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 3/27/2017 | | DONE |
|
|
|
All Met
|
Routing PW Sewer Rating | 3/22/2017 | | 3/24/2017 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLAN CHECK | 3/8/2017 | | 3/13/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 3/8/2017 | | 3/13/2017 | | PASS |
Javier Guzman
|
|
|
Passed in ePlan by AHJ Engineers Chris Holladay
|
Routing - PLANNING | 3/8/2017 | | 3/9/2017 | | PASS |
Susan Riggs
|
|
|
|
Route to Impact Fee Review | 2/23/2017 | 2/26/2017 | 2/24/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit
|
Routing PW Drainage | 1/24/2017 | | 2/21/2017 | | PASS |
Brian Murphy
|
|
|
|
1st review completed | | | 2/21/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 1/24/2017 | | 2/21/2017 | | PASS |
Rick Christenson
|
|
|
Pretreatment Requirements uploaded to ePlan (agency comments) contact Terry Alber ###-####.
|
Routing - FIRE | 1/24/2017 | 1/24/2017 | 2/17/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Sewer Rating | 1/24/2017 | | 2/17/2017 | | FAIL |
Beverly Mountain
|
|
|
Lost Grove must sign agreement of understanding with PW for future fee payments. bam
|
Routing - PLANNING | 1/24/2017 | | 2/17/2017 | | FAIL |
Susan Riggs
|
|
|
Failed in ePlan by Susan Riggs
|
Routing - PLAN CHECK | 1/24/2017 | | 2/17/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 1/24/2017 | | 2/14/2017 | | FAIL |
Javier Guzman
|
|
|
failed in ePlan by AHJ Engineers Chris Holladay
|
Routing PW Flood Plain | 2/8/2017 | | 2/8/2017 | | PASS |
Jason C. Taylor
|
|
|
Project Market Value has determined that this project does not meet the threshold for Substantial Improvement. No floodplain review is required. JCT
|
Routing - Design Review | 1/24/2017 | | 1/31/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH16-00197.
|
Routing PW Sewer Design | 1/24/2017 | | 1/30/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Flood Plain | 1/26/2017 | | 1/30/2017 | | FAIL |
Jason C. Taylor
|
|
|
See letter uploaded to ePlan (agency comments) for review. Jason Taylor ###-####
|
Routing - PLUMBING | 1/24/2017 | | 1/27/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 1/24/2017 | | 1/25/2017 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 1/24/2017 | | PASS |
Javier Guzman
|
|
|
|
Plan Reviewer's activity | | | 1/24/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Marianne, Please make sure this change of use permit is reviewed by ACHD for any comment and additional fees. When the permit is ready to be picked up you will need to provide proof that fees have been paid to ACHD or the fees due can be paid at the time the permit is picked up.
Thank you
|
Routing PW Street Lights | 1/24/2017 | | 1/24/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - Addressing | 1/24/2017 | | 1/24/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/24/2017 | | 1/24/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 1/24/2017 | | 1/24/2017 | | PASS |
Melissa Jannusch
|
|
|
ESC plan with site map and narrative approved. Valid PD designated RP TBD. Site preparation inspection required.
|
Intake Approval | | | 1/19/2017 | | FAIL |
Javier Guzman
|
|
|
Incomplete prescreen submittal, Applicants with incomplete submittals must upload additional documents or upload revised documents, below is what is required:
- Checklist proper floor plan page numbers are not showing the correct plan sheet numbers (for example the finish schedule is shown on checklist sheet 2.21 but it is actually found on sheet 3.22) please revise checklist and list correct & proper sheet numbers.
- Uploaded Soils and geotech report for support of the structure is required to be stamped and signed by an Idaho licensed engineer
-Architectural plan sheets shall be separated and uploaded as individual sheets not as a packet per ePlan submittal standards found at our website at http://pds.cityofboise.org/media/105041/electronicstandards.pdf
- Architectural plan sheets are required to be signed and stamped by an Idaho licensed architect
- Remove note on Architectural, Mechanical and Plumbing sheets stating “not for construction”
- Please provide structural plan sheet/s with the engineer’s details signed and stamped by an Idaho licensed engineer
- Electrical plan sheets are required to be uploaded in “Landscape” format in the horizontal position per ePlan submittal standards found at our website at http://pds.cityofboise.org/media/105041/electronicstandards.pdf
- Electrical plan sheets shall be separated and uploaded as individual sheets not as a packet per ePlan submittal standards found at our website at http://pds.cityofboise.org/media/105041/electronicstandards.pdf
- Civil plan sheets shall be separated and uploaded as individual sheets not as a packet per ePlan submittal standards found at our website at http://pds.cityofboise.org/media/105041/electronicstandards.pdf
-ESC plan sheets shall be separated and uploaded as individual sheets not as a packet per ePlan submittal standards found at our website at http://pds.cityofboise.org/media/105041/electronicstandards.pdf
- Mechanical plan sheets shall be separated and uploaded as individual sheets not as a packet per ePlan submittal standards found at our website at http://pds.cityofboise.org/media/105041/electronicstandards.pdf
- Plumbing plan sheets shall be separated and uploaded as individual sheets not as a packet per ePlan submittal standards found at our website at http://pds.cityofboise.org/media/105041/electronicstandards.pdf
- I could not find location of fir/smoke damper as noted in checklist, please clarify location of such damper
|
Application received | | | 1/18/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 18 2017 10:27AM
|
Routing PW Sewer Rating | 3/8/2017 | | | | FAIL |
Beverly Mountain
|
|
|
Contacting Jake to get signed agreement. bam
|