Third Notice | | 6/16/2018 | 6/16/2018 | | DONE |
|
|
|
This permit finaled on the web by Ami Tracy
|
Third Notice | | 5/15/2018 | 6/11/2018 | | DONE |
|
|
|
Mailed 6-12
|
Second Notice | | 4/20/2018 | 5/10/2018 | | DONE |
|
|
|
mailed 5-11-18
|
First Notice | | 3/19/2018 | 4/10/2018 | | DONE |
|
|
|
mailed 4-11-18
|
Permanent Occupancy | | | 3/9/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/8/2018 | 3/9/2018 | 3/8/2018 | A | PASS |
Jim Page
|
|
|
Life fire safety inspection complete.
|
BLD-Final | 3/7/2018 | 3/8/2018 | 3/8/2018 | P | PASS |
Dave Hannah
|
|
|
Jason Phone #: ###-####
|
BLD-Aging Inspection | 2/20/2018 | 2/20/2018 | 2/20/2018 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 1/3/2018 | 4/3/2018 | 1/3/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason B. ok'd extension good for 90 days
|
BLD-Aging Inspection | 12/19/2017 | 12/19/2017 | 12/19/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 10/17/2017 | 10/18/2017 | 10/18/2017 | P | PART |
Dave Hannah
|
|
|
Inspection request is for the TCO. Phone #: ###-#### Inspection requested via web by Carl Benjamin ok for temp occ ok for perm occ after bld final
|
FIRE-Final Inspection | 10/17/2017 | 10/18/2017 | 10/18/2017 | P | PART |
Jim Page
|
|
|
Fire sprinkler inspection for TCO complete, fire alarm inspection for TCO complete, commercial hood fire suppression system inspection for TCO complete, fire extinguishers are in place with a current inspection tags. TCO for life fire safety authorized for 90 days per conversation with Angela Brosious ###-####.
|
Temporary Occupancy | 10/18/2017 | 1/16/2018 | 10/18/2017 | | DONE |
Christina Prado
|
|
|
|
BLD-Other | 10/13/2017 | 10/16/2017 | 10/17/2017 | P | DONE |
Dave Hannah
|
|
|
Inspection request for the Temporary TCO for Monday and Tuesday Evening Friends and Family events. Phone #: ###-#### Inspection requested via web by Carl Benjamin ok for events
|
BLD-Ceiling Grid Inspection | 9/25/2017 | 9/25/2017 | 9/25/2017 | P | PASS |
Dave Hannah
|
|
|
Inspection request for ceiling grid inspection in the prep area of the Wylder restaurant as well as a soffit in the pump room of the Fowler. Phone #: ###-#### Inspection requested via web by Guillaume Chatelus
|
FIRE-Final Inspection | 9/20/2017 | 9/20/2017 | 9/20/2017 | P | PART |
Jim Page
|
|
|
Partial final inspection complete for tenant space associated with this permit. As per signed TCO agreement, fire pump testing/commissioning is complete, tamper switch and flow switch testing is complete for levels 1 and 2 wet pipe fire sprinkler systems, tamper switch/pressure switch and high low air sensor testing complete for levels 1 and 2 dry pipe fire sprinkler systems, commercial hood fire suppression system inspection is complete (FIR permit for hood suppression system will remain in issued status until core and shell permits for building are complete and passed), fire sprinkler inspection complete for tenant space (FIR permit for fire sprinklers will remain in issued status until core and shell inspections are complete), fire alarm inspection complete for tenant space (FIR permit for fire alarms will remain in issued status until core and shell inspections are complete), fire extinguishers are in place with current inspection tags. Per note number 8 of the signed temporary occupancy plan no employees will be in the space except for the 2 owners and their executive chef until TCO is authorized.
|
BLD-Conference | 9/18/2017 | 9/19/2017 | 9/19/2017 | A | DONE |
Dave Hannah
|
|
|
Inspection request for going through and walking through required interior signage for the Wylder TI restaurant. Phone #: ###-#### Inspection requested via web by Guillaume Chatelus
|
BLD-Ceiling Grid Inspection | 8/11/2017 | 8/14/2017 | 8/14/2017 | A | PASS |
Dave Hannah
|
|
|
Inspection request for the Wood Ceiling Clouds Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
FIRE-Conference | 8/2/2017 | 8/3/2017 | 8/3/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete, General Contractor will be sending a formal request to the fire code official for employee/owner TCO for pizza tenant.
|
BLD-Framing/Rough-in | 6/15/2017 | 6/16/2017 | 6/16/2017 | A | PASS |
Dave Hannah
|
|
|
Inspection request for Metal Studs framing - Fire rated sheathing. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
(F) Reprint permit | | | 4/13/2017 | | DONE |
|
|
|
|
Telephone call | | | 4/13/2017 | | DONE |
|
|
|
emailed Duel the building permit to see if he would print and sign it for me and send it back
|
Issue PAID IN FULL permit | | | 4/11/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/11/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/11/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/11/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/10/2017 | | DONE |
Christina Prado
|
|
|
***Still need ACHD but received the GC and rev cert of val 4-11-17 CAN***Need ACHD, GC Form & Revised Certificate of Value for issuance
|
Plan assigned to (CDM) | 1/25/2017 | 1/25/2017 | 4/8/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp. Rex Pizza Due 2/15
|
Routing - PLAN CHECK | 3/17/2017 | | 4/8/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 3/17/2017 | | 3/20/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/24/2017 | 2/27/2017 | 3/6/2017 | | PASS |
Tonya Wallace
|
|
|
Review requested for Commercial Permit
|
Routing Off Site - C.D.H | 1/27/2017 | | 2/24/2017 | | PASS |
Carl D Madsen
|
|
|
Passed on early start
|
1st review completed | | | 2/24/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/25/2017 | | 2/24/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLANNING Land Div | 1/25/2017 | | 2/22/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Environmental | 1/26/2017 | | 2/6/2017 | | PASS |
Rick Christenson
|
|
|
Need to confirm New Grease lines are connected to Existing line and grease abatement is functioning properly.
|
Routing - Design Review | 1/27/2017 | | 1/31/2017 | | PASS |
Sarah Schafer
|
|
|
|
Routing - MECHANICAL | 1/25/2017 | | 1/30/2017 | | FAIL |
Troy James
|
|
|
|
Routing - FIRE | 1/25/2017 | 1/25/2017 | 1/27/2017 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing - PLUMBING | 1/25/2017 | | 1/27/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING | 1/25/2017 | | 1/26/2017 | | PASS |
Cody Riddle
|
|
|
Site, building and landscape approved by DR.
|
Routing - Addressing | 1/25/2017 | | 1/26/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/25/2017 | | 1/26/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan Reviewer's activity | | | 1/25/2017 | | PASS |
|
|
|
Plan intake approved
|
Intake Approval | | | 1/25/2017 | | PASS |
|
|
|
|
Application received | | | 1/23/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 23 2017 11:08AM
|