Print Statement | | | 8/2/2017 | | DONE |
|
|
|
|
Second Notice | | 6/22/2017 | 7/12/2017 | | DONE |
|
|
|
Mailed 7-13-17
|
First Notice | | 6/4/2017 | 6/12/2017 | | DONE |
|
|
|
Mailed 6-13-17
|
Permanent Occupancy | | | 5/25/2017 | | DONE |
|
|
|
|
BLD-Final | 5/11/2017 | 5/11/2017 | 5/11/2017 | P | PASS |
Dave Hannah
|
|
|
final c/o for penthouse // patrick Phone #: ###-####
|
FIRE-Final Inspection | 3/31/2017 | 4/3/2017 | 4/3/2017 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection passed/complete.
|
BLD-Framing/Rough-in | 3/7/2017 | 3/9/2017 | 3/10/2017 | P | PASS |
Dave Hannah
|
|
|
Patrick Phone #: ###-####
|
Place hold on job | 3/3/2017 | | 3/7/2017 | | DONE |
Candy A. Nichols
|
|
|
Building permit fees need to be paid. See notes under meeting
fees were paid
|
Fees Due Hold | 3/4/2017 | | 3/7/2017 | | DONE |
Candy A. Nichols
|
|
|
fees were paid
|
Issue PAID IN FULL permit | | | 3/3/2017 | | DONE |
|
|
|
|
Meeting | | | 3/3/2017 | | DONE |
|
|
|
Spoke with Sarah Cunningham. She stated that she will be in first thing Monday morning 2/6/17 to pay the building permit fees. Mix up with Building and Sewer fees, their customer is paying sewer. Candy, Rita and Morgan (SWR) know what's going on
|
Plan assigned to (JG) | 1/27/2017 | 1/27/2017 | 3/1/2017 | | PASS |
Javier Guzman
|
|
|
1st review completed, 2/09 L2 ZEES ROOFTOP CAFE – CW MOORE PLAZA – 9th FLOOR, paper plans
|
Routing - PLAN CHECK | 3/1/2017 | | 3/1/2017 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 3/1/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/1/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/1/2017 | | DONE |
|
|
|
ALL MET 3-1-17 BLH Need rev cert of val
|
Print Occupancy Form | | | 3/1/2017 | | DONE |
|
|
|
|
Telephone call | | | 3/1/2017 | | DONE |
|
|
|
called Sarah to let know permit is ready and that we need the GC and rev cert of val-left message on her cell
|
Print Occupancy Form | | | 3/1/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/21/2017 | | DONE |
|
|
|
Two copies of sheets A1.0, A1.1 and A1.3 taken to javier
|
Route to Impact Fee Review | 2/13/2017 | 2/16/2017 | 2/15/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/13/2017 | | DONE |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 1/27/2017 | | 2/13/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 2/7/2017 | | 2/13/2017 | | PASS |
Bill VanDegrift
|
|
|
signed off by B. Vandergrifth
|
Routing - FIRE | 2/10/2017 | | 2/10/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to plans
|
Routing - MECHANICAL | 2/3/2017 | | 2/7/2017 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | | | 2/3/2017 | | PASS |
|
|
|
|
Routing PW Environmental | 2/1/2017 | | 2/3/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - Addressing | 1/27/2017 | | 1/31/2017 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/27/2017 | | DONE |
|
|
|
|
Intake Approval | | | 1/27/2017 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 1/23/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 23 2017 6:03PM
|