Print Statement | | | 7/25/2017 | | DONE |
|
|
|
|
First Notice | | 6/11/2017 | 7/12/2017 | | DONE |
|
|
|
Mailed 7-13-17
|
BLD-Final | 6/1/2017 | 6/1/2017 | 6/1/2017 | P | PASS |
Jim Storey
|
|
|
Greg Phone #: ###-####
|
Permanent Occupancy | | | 6/1/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/24/2017 | 5/25/2017 | 5/24/2017 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete (alarm permit FIR17-00187 is not attached in project related cases) fire extinguishers are in place with current inspection tags. Final lilfe fire safety inspection passed/complete
|
BLD-Ceiling Grid Inspection | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | PASS |
Jim Storey
|
|
|
Greg Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 3/9/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/9/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 3/1/2017 | 3/1/2017 | 3/8/2017 | | PASS |
Javier Guzman
|
|
|
Plan Mod, Albertsons ACAMS Phase I, Pend Mech
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/8/2017 | | DONE |
|
|
|
Plan mod ONLY - DO NOT RE-ISSUE
|
Routing - MECHANICAL | 3/3/2017 | | 3/6/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 3/3/2017 | | 3/3/2017 | | PASS |
Javier Guzman
|
|
|
|
Plan Modification Accepted | | | 3/1/2017 | | DONE |
Christina Prado
|
|
|
Minor updates to equipment room 012, electrical, new mechanical system
|
BLD-Framing/Rough-in | 2/22/2017 | 2/22/2017 | 2/22/2017 | P | PASS |
Jim Sly
|
|
|
Greg Phone #: ###-####
|
Print Occupancy Form | | | 2/21/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/21/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 1/27/2017 | 1/27/2017 | 2/14/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 2/02 L1 Albertsons ACAMS Phase I ePlan Pend Fire
|
Routing - PLAN CHECK | 2/8/2017 | | 2/14/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/14/2017 | | DONE |
|
|
|
Needs; GC Form & Revised Cert of Value
|
Route to Impact Fee Review | 2/6/2017 | 2/9/2017 | 2/8/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 2/8/2017 | 2/8/2017 | 2/8/2017 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing - FIRE | 1/31/2017 | 1/31/2017 | 2/6/2017 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
1st review completed | | | 2/6/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 1/27/2017 | | 2/1/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 1/27/2017 | | 1/30/2017 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 1/27/2017 | | 1/30/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 1/27/2017 | | 1/27/2017 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 1/27/2017 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 1/25/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 25 2017 4:00PM
|