BLD-Final | 12/20/2017 | 12/20/2017 | 12/20/2017 | P | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Cassandra Hessing,, need final engineer letter of ok
|
BLD-Foundation | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | PEND |
Tony Young
|
|
|
Cassandra Phone #: ###-####,, pending special inspection
|
Issue PAID IN FULL permit | | | 7/18/2017 | | DONE |
|
|
|
|
Telephone call | | | 7/17/2017 | | DONE |
|
|
|
Spoke with Cassandra informing her that this permit is going to expire in 9 days. Informed her that they can send in a request for a 180 day extension or pay and pick up the permit. She stated that they would come in pay and pick up the permit
|
Expiration Notice | 7/5/2017 | 7/26/2017 | 7/5/2017 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 6/23/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 4/3/2017 | 4/3/2017 | 6/23/2017 | | DONE |
Brian McGowan
|
|
|
1st Review Complete -Helitical Piers - Failed
|
Telephone call | | | 6/23/2017 | | DONE |
|
|
|
called Cassandra o let know permit is ready and how much is owed
|
Routing - PLAN CHECK | | | 6/23/2017 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 6/23/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/23/2017 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 6/13/2017 | | 6/16/2017 | | PASS |
Jason C. Taylor
|
|
|
Special inspections required by ICC-ES report. JCT
|
Plan resubmittals received | | | 6/13/2017 | | DONE |
|
|
|
received one copy of geotech report; taken to Brian M.
|
Routing Walk-In (PW Hillside) | 4/27/2017 | 4/27/2017 | 4/27/2017 | P | FAIL |
Jason C. Taylor
|
|
|
Geotech report does not meet ICC-ES evaluation section 4.1.1. Pleae revise report nad resubmit. Jason Taylor ###-####
|
Routing Walk-In (BLD) | 1/26/2017 | 1/26/2017 | 4/27/2017 | P | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 4/21/2017 | | 4/27/2017 | | FAIL |
Brian McGowan
|
|
|
See Hillside requirements
|
Plan resubmittals received | | | 4/21/2017 | | DONE |
|
|
|
received form #310 and Geotech report
|
Routing - PLAN CHECK | 1/26/2017 | | 1/31/2017 | | FAIL |
Brian McGowan
|
|
|
Need Geotech and completed Special Inspection Form completed.
|
1st review completed | | | 1/31/2017 | | FAIL |
Brian McGowan
|
|
|
Need Geotech and completed Special Inspection Form completed.
|
Routing PW Grading-Hillside | 1/26/2017 | | 1/30/2017 | | FAIL |
Jason C. Taylor
|
|
|
Need geotechnical engineering report for site. JCT
|
Routing - Erosion and Sediment | 1/26/2017 | | 1/27/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved.
|
Application received | | 1/26/2017 | | | |
|
|
|
|