BLD-Final | 5/10/2018 | 5/11/2018 | 5/11/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter
|
DOC - Permit Finaled | 5/11/2018 | 5/11/2018 | 5/11/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, needs to verify address.. (out of sync,, should be 2706?),, needs tempered glass, etc.
|
BLD-Blower Door Test Results | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, 6.0
|
BLD-Final | 5/4/2018 | 5/7/2018 | 5/7/2018 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porterl,, walk through only
|
BLD-Energy code compliance | 2/14/2018 | 2/15/2018 | 2/15/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter
|
BLD-Energy code compliance | 2/12/2018 | 2/14/2018 | 2/14/2018 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter
|
BLD-Framing/Rough-in | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter
|
BLD-Wall Bracing | 1/17/2018 | 1/18/2018 | 1/18/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, exterior nailing ok
|
BLD-Footing | 10/30/2017 | 10/31/2017 | 10/31/2017 | A | DEFR |
Mike Jordan
|
|
|
Ryan Phone #: ###-####. Concrete footings already placed when arrived on site. no city approved plans or lot lines strung. Footings appear to be 8x16. Concrete proceeds at own risk and accpts all responsibility for foundation system.
|
BLD-Footing | 10/30/2017 | 10/30/2017 | 10/30/2017 | P | CANC |
Tony Young
|
|
|
Ryan Phone #: ###-####,, forms,, work in progress
|
Issue PAID IN FULL permit | | | 10/10/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/10/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/20/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 9/1/2017 | 9/1/2017 | 9/20/2017 | | DONE |
Brian McGowan
|
|
|
9/07 Plan Mod for Brian ePlan
|
Routing - PLAN CHECK | 9/20/2017 | | 9/20/2017 | | PASS |
Brian McGowan
|
|
|
Please add (1) hour of plan review time for the modification.
|
Permit Ready to Issue | | | 9/20/2017 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing - MECHANICAL | 9/8/2017 | | 9/11/2017 | | PASS |
Chad Schwendiman
|
|
|
|
CHANGE STATUS TO (REV) | | | 9/1/2017 | | DONE |
Christina Prado
|
|
|
|
Plan Modification Accepted | | | 9/1/2017 | | DONE |
Christina Prado
|
|
|
Changing foundation to slab and hvac to ductless
|
Extend Review Timeline | | | 8/8/2017 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Telephone call | | | 7/17/2017 | | DONE |
|
|
|
Left a message for Travis informing him that this permit is going to expire in 9 days and if he would like he may send in a request for a 180 day extension. Left the permit number, my email and my number
|
Expiration Notice | 7/5/2017 | 7/26/2017 | 7/5/2017 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (BJM) | 2/21/2017 | 2/21/2017 | 3/27/2017 | | DONE |
Brian McGowan
|
|
|
Due 2-27 ePlan - Fail- need engineering for angled support column
|
Routing - PLANNING | 2/14/2017 | | 3/27/2017 | | PASS |
Ted Vanegas
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/27/2017 | | DONE |
|
|
|
All Met
|
Routing - PLAN CHECK | 3/26/2017 | | 3/26/2017 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 2/14/2017 | | 2/28/2017 | | FAIL |
Brian McGowan
|
|
|
Engineering for angled column is required, verify floor cover (conc?)
|
1st review completed | | | 2/27/2017 | | FAIL |
Brian McGowan
|
|
|
Engineering for angled column is required, verify floor cover (conc?)
|
Plan assigned to (LEG) Tisha | 2/14/2017 | | 2/21/2017 | | DEFR |
Tisha Gallop
|
|
|
|
Plan Modification Accepted | | | 2/17/2017 | | DONE |
|
|
|
Revised manual J
|
Routing - MECHANICAL | 2/17/2017 | | 2/17/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Routing Walk-In (Zoning) | 2/16/2017 | 2/16/2017 | 2/16/2017 | A | PASS |
Ted Vanegas
|
|
|
|
Routing Walk-In (BLD) | 2/16/2017 | 2/16/2017 | 2/16/2017 | A | PASS |
Brian McGowan
|
|
|
no contact
|
Route to Impact Fee Review | 2/14/2017 | 2/17/2017 | 2/15/2017 | | PASS |
Cindy M. Gould
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - MECHANICAL | 2/14/2017 | | 2/15/2017 | | FAIL |
Troy James
|
|
|
Emailed corrections to building energy
|
Routing - Addressing | 2/14/2017 | | 2/15/2017 | | PASS |
Laura Hunter
|
|
|
New SFD address is 2702 N 26th St
|
Routing - PUBLIC WORKS | 2/14/2017 | | 2/15/2017 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/14/2017 | | DONE |
|
|
|
|
Intake Approval | | | 2/14/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/14/2017 | | DONE |
|
|
|
|
Intake Approval | | | 1/31/2017 | | FAIL |
Christina Prado
|
|
|
Need revised shear bracing plans, currently states TBD on plan set
|
Application received | | | 1/26/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 26 2017 1:57PM
|