Print Statement | | | 2/26/2019 | | DONE |
|
|
|
|
Second Notice | | 1/17/2019 | 2/7/2019 | | DONE |
|
|
|
mailed 2-11-19
|
First Notice | | 1/6/2019 | 1/7/2019 | | DONE |
|
|
|
MAILED 1-11-19
|
Print Occupancy Form | | | 12/27/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/27/2018 | | DONE |
|
|
|
|
BLD-Final | 11/16/2017 | 11/17/2017 | 11/17/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by JANET TATILIAN life safety passed. At the time of this inspection thee were not chemicals or anything for that matter stored under the canopy. The storage cabinets addressed in the review comments had not been provided. // no card on site
|
FIRE-Final Inspection | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. At the time of this inspection thee were not chemicals or anything for that matter stored under the canopy. The storage cabinets addressed in the review comments had not been provided.
Phone #: ###-#### Inspection requested via web by JANET TATILIAN
|
FIRE-Final Inspection | 11/16/2017 | 11/17/2017 | 11/17/2017 | A | FAIL |
Troy Cobbley
|
|
|
Fire extinguishers still are not tagged.
Phone #: ###-#### Inspection requested via web by JANET TATILIAN
|
BLD-Final | 11/8/2017 | 11/9/2017 | 11/9/2017 | P | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by JANET TATILIAN fire failled
|
FIRE-Final Inspection | 11/8/2017 | 11/9/2017 | 11/9/2017 | A | FAIL |
Troy Cobbley
|
|
|
No small documents and the new fire extinguishers need current inspection tags from a certified company. There was not contact at job site and no answer on the phone.
Phone #: ###-#### Inspection requested via web by JANET TATILIAN
|
FIRE-Final Inspection | 10/26/2017 | 10/27/2017 | 10/27/2017 | A | FAIL |
Troy Cobbley
|
|
|
No inspection performed due to no small documents on site. I noted the need for a fire extinguisher and specific requirements for the storage of hazardous chemicals.
|
BLD-Final | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | NR |
Jim Storey
|
|
|
Call Rob 2089418575 for access Phone #: ###-#### Inspection requested via web by JANET TATILIAN need fire insp.
|
BLD-Foundation | 8/10/2017 | 8/11/2017 | 8/11/2017 | A | PASS |
Jim Storey
|
|
|
Rebar... Call half hour before to meet // Curtis Phone #: ###-#### slab and pit rebar ok
|
BLD-Footing | 6/5/2017 | 6/7/2017 | 6/7/2017 | A | PASS |
Jim Storey
|
|
|
Roberr-pour time 1:00 Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/5/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/5/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/10/2017 | | |
|
|
|
|
Plan assigned to (CDM) | 2/1/2017 | 2/1/2017 | 3/10/2017 | | PASS |
Carl D Madsen
|
|
|
1st Comp. Idaho Power due 2-24
|
Routing Off Site - STRUCTURAL | 3/6/2017 | | 3/10/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/10/2017 | | DONE |
|
|
|
need GC, rev cert of val, RP
|
Routing - PLAN CHECK | 3/6/2017 | | 3/6/2017 | | PASS |
Carl D Madsen
|
|
|
Pending engineering approval
|
Route to Impact Fee Review | 2/24/2017 | 2/27/2017 | 2/24/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/24/2017 | | FAIL |
|
|
|
|
Routing PW Drainage | 2/1/2017 | | 2/24/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Environmental | 2/1/2017 | | 2/13/2017 | | PASS |
Rick Christenson
|
|
|
Per Terry Alber review.
|
Routing Off Site - STRUCTURAL | 2/1/2017 | | 2/13/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/1/2017 | | 2/13/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | 2/1/2017 | 2/1/2017 | 2/7/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Design Review | 2/1/2017 | | 2/6/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH16-00519
|
Routing - Erosion and Sediment | 2/1/2017 | | 2/3/2017 | | PASS |
Andy J. Long
|
|
|
RP TBD. BMPs include: stabilized construction entrance, water based waste trench, staging/ parking area, inlet protection, and fiber rolls along the west side of the project.
|
Routing - PLANNING | 2/1/2017 | | 2/2/2017 | | PASS |
Cody Riddle
|
|
|
Design Review only.
|
Routing - PLANNING Land Div | 2/1/2017 | | 2/2/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 2/1/2017 | | 2/2/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/1/2017 | | 2/1/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 2/1/2017 | | PASS |
|
|
|
|
Application received | | | 1/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 30 2017 4:26PM
|