Permanent Occupancy | | | 9/25/2017 | | DONE |
|
|
|
|
BLD-Final | 9/19/2017 | 9/20/2017 | 9/20/2017 | P | PASS |
Brandon Shaw
|
|
|
Call one hour in advance please Phone #: ###-#### Inspection requested via web by bryan murdoch
|
DOC - Permit Finaled | 9/20/2017 | 9/20/2017 | 9/20/2017 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 9/19/2017 | 9/19/2017 | 9/19/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 6/29/2017 | 6/30/2017 | 6/30/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by bryan murdoch
|
BLD-Framing/Rough-in | 6/29/2017 | 6/30/2017 | 6/30/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by bryan murdoch
|
BLD-Framing/Rough-in | 6/26/2017 | 6/27/2017 | 6/27/2017 | P | PASS |
Brandon Shaw
|
|
|
Per engineering D01 grider- 2 rows 3.75" o.c.
OK to insulate
|
BLD-Wall Bracing | 6/26/2017 | 6/27/2017 | 6/27/2017 | P | PASS |
Brandon Shaw
|
|
|
See cn and red paint
|
Plan Modification Accepted | | | 4/19/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 4/19/2017 | | 4/19/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Foundation | 3/28/2017 | 3/29/2017 | 3/29/2017 | P | PASS |
Jim Sly
|
|
|
If there are any questions please call Eric at ###-#### Phone #: ###-#### Inspection requested via web by bryan murdoch
|
BLD-Footing | 3/20/2017 | 3/21/2017 | 3/21/2017 | P | PASS |
Dave Hannah
|
|
|
Call Eric ###-#### Phone #: ###-#### Inspection requested via web by bryan murdoch
|
PubWorks Subgrade Approval | 3/15/2017 | 3/15/2017 | 3/15/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 3/3/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/2/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 2/17/2017 | 2/17/2017 | 3/2/2017 | | DONE |
Brian McGowan
|
|
|
2/17 L2 hillside
|
Routing - PLAN CHECK | 3/2/2017 | | 3/2/2017 | | PASS |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 3/2/2017 | | DONE |
|
|
|
|
Telephone call | | | 3/2/2017 | | DONE |
|
|
|
Left message for Doug informing him that this permit is ready and the fee amount due for issuance.
|
Routing PW Grading-Hillside | 2/27/2017 | | 3/2/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PUBLIC WORKS | 3/2/2017 | | 3/2/2017 | | PASS |
Morgan Webb
|
|
|
|
Case Summary (BLD) | | | 3/2/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/2/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/2/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/27/2017 | | |
Christina Prado
|
|
|
Received three sets of sheet C1; Plans stamped and taken to Brian M for processing
|
1st review completed | | | 2/24/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 2/23/2017 | | 2/23/2017 | | PASS |
Troy James
|
|
|
|
Plan assigned to (LEG) Tisha | 1/31/2017 | | 2/17/2017 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
2/17 L2 hillside
|
Routing - FIRE | 2/15/2017 | | 2/16/2017 | | PASS |
Scott Arellano
|
|
|
Approved as shown.
|
Routing - Erosion and Sediment | 2/10/2017 | | 2/15/2017 | | PASS |
Andy J. Long
|
|
|
BMPs: Concrete washout (cleaning waste disposal pit), Street sweeping, construction entrance, inlet protection (1), staging area, straw wattles along SE side of site at lowest elevation. May request addition wattles upon site inspection to be placed along sidewalk if gradient is steep enough to cause runoff to sidewalk/road.
|
Routing - MECHANICAL | 2/13/2017 | | 2/13/2017 | | FAIL |
Troy James
|
|
|
Emailed corrections to building energy
|
Routing - MECHANICAL | 2/8/2017 | | 2/10/2017 | | FAIL |
Troy James
|
|
|
emailed correction to building energy
|
Routing - PLANNING | 2/7/2017 | | 2/8/2017 | | PASS |
Jeff Lowe
|
|
|
CONDITONAL APPROVAL - CFH approved by zoning, applicant shall comply with PW for grading.
|
Routing - Addressing | 2/7/2017 | | 2/7/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/7/2017 | | 2/7/2017 | | FAIL |
Rachael Beierle
|
|
|
FAIL HILLSIDE. SEE JCT.
|
Routing PW Grading-Hillside | 1/31/2017 | | 2/7/2017 | | FAIL |
Jason C. Taylor
|
|
|
Grading plan was not edited as per CFH conditions of approval. Please revise plans:
1. Foundation drain lines must be placed on grading plan. Foundation drains cannot be connected to subdivision drainage system. Show outlet protection detail.
2. Provide cross section of rock retaining walls and drainage line.
Jason
|
Routing PW Sewer Rating | 2/7/2017 | | 2/7/2017 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 1/31/2017 | 2/3/2017 | 2/3/2017 | | PASS |
Cindy M. Gould
|
|
|
Initial residential review of all new news permit requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 1/31/2017 | | DONE |
|
|
|
|
Intake Approval | | | 1/31/2017 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 1/31/2017 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/31/2017 | | DONE |
|
|
|
|
First Notice | | 10/5/2017 | | | |
|
|
|
|
Application received | | 1/31/2017 | | | |
|
|
|
|