BLD-Final | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | PASS |
Tony Young
|
|
|
garage code 4663 Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
DOC - Permit Finaled | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | PASS |
Tony Young
|
|
|
c of o issued
|
Plan Modification Accepted | | | 11/17/2017 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 11/17/2017 | | 11/17/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Final | 10/30/2017 | 10/30/2017 | 10/31/2017 | P | NR |
Tony Young
|
|
|
Garage code is 4663 Inspection requested via web by Marty Pieroni,, needs mech 1st
|
BLD-Aging Inspection | 10/27/2017 | 10/27/2017 | 10/30/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 6/15/2017 | 6/15/2017 | 6/15/2017 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Framing/Rough-in | 6/9/2017 | 6/12/2017 | 6/12/2017 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni,, ok to insulate
|
BLD-Framing/Rough-in | 6/8/2017 | 6/9/2017 | 6/9/2017 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni,, corrections needed,, written on blue tag
|
BLD-Wall Bracing | 5/16/2017 | 5/17/2017 | 5/17/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Foundation | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PART |
Tony Young
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 3/31/2017 | 4/3/2017 | 4/3/2017 | A | PASS |
Jim Sly
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 3/30/2017 | 3/31/2017 | 3/31/2017 | A | CANC |
Mike Jordan
|
|
|
Matt Phone #: ###-####. Cancelled by contractor via phone call.
|
Issue PAID IN FULL permit | | | 3/28/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/28/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/22/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 2/10/2017 | 2/10/2017 | 3/22/2017 | | DONE |
Brian McGowan
|
|
|
Due 2-22 ePlan - Fail - Beams and headers must be specified on the plans. Wall Bracing does not work,
|
Routing - PLAN CHECK | 3/22/2017 | | 3/22/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/22/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 3/9/2017 | | 3/9/2017 | | PASS |
Sue Cummings
|
|
|
Reduce driveway by 1 ft. to comply wiwth 11-07-03-(4)(e)
|
1st review completed | | | 2/22/2017 | | FAIL |
Brian McGowan
|
|
|
Beams and headers must be specified on the plans. Wall Bracing does not work,
|
Routing - PLAN CHECK | 2/9/2017 | | 2/22/2017 | | FAIL |
Brian McGowan
|
|
|
Beams and headers must be specified on the plans. Wall Bracing does not work,
|
Route to Impact Fee Review | 2/9/2017 | 2/12/2017 | 2/10/2017 | | PASS |
Cindy M. Gould
|
|
|
Initial residential review of all new news permit requested for now.
|
Plan assigned to (LEG) Tisha | 2/9/2017 | | 2/10/2017 | | DEFR |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/9/2017 | | DONE |
|
|
|
|
Intake Approval | | | 2/9/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/9/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 2/9/2017 | | 2/9/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 2/9/2017 | | 2/9/2017 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 2/9/2017 | | 2/9/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/9/2017 | | 2/9/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 2/3/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 3 2017 5:15PM
|
BLD-Footing | 3/28/2017 | 3/30/2017 | | A | |
|
|
|
Matt Phone #: ###-####
|