Second Notice | | 6/22/2017 | 6/16/2017 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | | 5/12/2017 | 6/12/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 5/2/2017 | | DONE |
|
|
|
|
BLD-Final | 4/28/2017 | 5/1/2017 | 5/1/2017 | P | PASS |
Jim Storey
|
|
|
Larry Phone #: ###-####
|
FIRE-Final Inspection | 4/27/2017 | 4/27/2017 | 4/27/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are mounted with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Framing/Rough-in | 3/23/2017 | 3/24/2017 | 3/24/2017 | A | PASS |
Jim Storey
|
|
|
Larry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/14/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/14/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/14/2017 | | DONE |
|
|
|
|
Plan assigned to (DAF) | 2/7/2017 | 2/7/2017 | 2/9/2017 | | DONE |
David Ferguson
|
|
|
due 2/13 - L1 Symphony EYC Suite #325 ePlan
|
Routing - PLAN CHECK | 2/7/2017 | | 2/9/2017 | | PASS |
David Ferguson
|
|
|
|
1st review completed | | | 2/9/2017 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/9/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/9/2017 | | DONE |
Christina Prado
|
|
|
**ALL MET** Need GC Form & Revised Cert of Value for issuance
|
Intake Approval | | | 2/7/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 2/7/2017 | | 2/7/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/7/2017 | | 2/7/2017 | | PASS |
Morgan Webb
|
|
|
NO NEW FEES DUE TO CREDITS.
|
Application received | | | 2/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 6 2017 8:24AM
|