Second Notice | | 8/21/2017 | 8/17/2017 | | DONE |
|
|
|
This permit finaled on the web by Shawn Metier
|
First Notice | | 8/6/2017 | 8/11/2017 | | DONE |
|
|
|
mailed
|
BLD-Final | 7/26/2017 | 7/27/2017 | 7/27/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson. Ok for perm occ.
|
Permanent Occupancy | | | 7/27/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/25/2017 | 7/26/2017 | 7/26/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 7/25/2017 | 7/26/2017 | 7/26/2017 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson
|
BLD-Final | 7/24/2017 | 7/25/2017 | 7/25/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Richard Wilson Inspection cancelled from web by: Richard Wilson
|
FIRE-Final Inspection | 7/24/2017 | 7/25/2017 | 7/25/2017 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Richard Wilson Inspection cancelled from web by: Richard Wilson
|
BLD-Final | 7/24/2017 | 7/24/2017 | 7/24/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Richard Wilson Inspection cancelled from web by: Richard Wilson
|
FIRE-Final Inspection | 7/24/2017 | 7/24/2017 | 7/24/2017 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Richard Wilson Inspection cancelled from web by: Richard Wilson
|
BLD-Final | 7/3/2017 | 7/3/2017 | 7/3/2017 | P | PART |
Mike Jordan
|
|
|
Partial, 2nd floor Phone #: ###-#### Inspection requested via web by Richard Wilson. Ok to occupy 2nd floor.
|
FIRE-Final Inspection | 7/3/2017 | 7/3/2017 | 7/3/2017 | P | CANC |
Jim Page
|
|
|
Duplicate inspection request.
|
FIRE-Final Inspection | 7/3/2017 | 7/3/2017 | 7/3/2017 | A | PART |
Jim Page
|
|
|
Partial final for life fire safety complete, fire sprinkler inspection is complete (fire sprinkler head in mens restroom on level 2 needs replaced, seat and base of glass bulb are painted, sprinkler head in front of level 2 elevator needs replaced with an intermediate temperature fire sprinkler head, head is with 12 inches of heat register, landscaping needs to be trimmed back to provide access to the wall mounted PIV and FDC, items to be verified at final life fire safety inspection for level 1 area of work associated with this BLD permit) fire alarm complete for level 2 excluding elevator lobby smoke detector, operation will be verified at fire alarm completion for project, fire extinguishers are in place with current inspection tags, building does have a knox box mounted by main entry.
|
BLD-Ceiling Grid Inspection | 6/23/2017 | 6/23/2017 | 6/23/2017 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson. Pending mech. rough in inspection.
|
BLD-Framing/Rough-in | 5/23/2017 | 5/23/2017 | 5/23/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson. Interior steel stud walls at 2nd. floor ok. No grid. Pending elec. and plumbing rough in inspections.
|
BLD-Framing/Rough-in | 5/22/2017 | 5/22/2017 | 5/22/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Richard Wilson
|
Issue PAID IN FULL permit | | | 5/2/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/2/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/2/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 2/13/2017 | 2/13/2017 | 3/8/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 2/23 L2 Smoke Guard TI ePlan
|
Routing - PLAN CHECK | 3/8/2017 | | 3/8/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/8/2017 | | DONE |
|
|
|
***All met //4/27/17 leg*** Needs; GC Form & Revised Cert of Value
|
Route to Impact Fee Review | 2/23/2017 | 2/26/2017 | 2/24/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit no change in use
|
1st review completed | | | 2/23/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 2/13/2017 | | 2/23/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 2/13/2017 | | 2/21/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - Design Review | 2/13/2017 | | 2/15/2017 | | PASS |
Katelyn Menuge
|
|
|
New exterior window okay.
|
Routing - MECHANICAL | 2/13/2017 | | 2/14/2017 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 2/13/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 2/13/2017 | | 2/13/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/13/2017 | | 2/13/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 2/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 7 2017 12:20PM
|