Second Notice | | 6/23/2017 | 7/12/2017 | | DONE |
|
|
|
Mailed 7-13-17
|
First Notice | | 5/8/2017 | 6/13/2017 | | DONE |
|
|
|
sent in mail 6-14-17
|
BLD-Final | 4/28/2017 | 4/28/2017 | 4/28/2017 | P | PASS |
Mike Jordan
|
|
|
Tim Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 4/28/2017 | 4/28/2017 | 4/28/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 4/28/2017 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | PART |
Mike Jordan
|
|
|
west half // Tim Phone #: ###-####. West offices ok, pending fire sprinkler rough in inspection.
|
BLD-Ceiling Grid Inspection | 4/7/2017 | 4/7/2017 | 4/7/2017 | P | DONE |
Mike Jordan
|
|
|
Please call ahead for access - Tim Phone #: ###-####. This portion of ceiling grid is existing.
|
BLD-Framing/Rough-in | 3/27/2017 | 3/28/2017 | 3/28/2017 | A | PASS |
Mike Jordan
|
|
|
Restroom framing and consult on draftstop - Tim Phone #: ###-####. Interior steel stud framed walls and hardlid for restroom.
|
BLD-Framing/Rough-in | 3/21/2017 | 3/22/2017 | 3/22/2017 | A | PASS |
Mike Jordan
|
|
|
Offices - Tim Phone #: ###-####. Interior steel stud framed walls for conferance/offices and training rooms only. No grid.
|
Issue PAID IN FULL permit | | | 3/9/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 3/9/2017 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (DAF) | 2/17/2017 | 2/17/2017 | 2/28/2017 | | DONE |
David Ferguson
|
|
|
(1st done) due 2/22 - L2 Saint Alphonsus TI ePlan
|
Routing - PLAN CHECK | 2/28/2017 | | 2/28/2017 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/28/2017 | | DONE |
|
|
|
MET
|
Route to Impact Fee Review | 2/22/2017 | 2/25/2017 | 2/24/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit no change in use
|
1st review completed | | | 2/22/2017 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 2/9/2017 | | 2/22/2017 | | FAIL |
David Ferguson
|
|
|
|
Plan assigned to (JG) | 2/9/2017 | 2/9/2017 | 2/17/2017 | | DEFR |
Javier Guzman
|
|
|
2/22 L2 Saint Alphonsus TI ePlan
|
Routing - FIRE | 2/9/2017 | 2/9/2017 | 2/10/2017 | | PASS |
Katie Marron
|
|
|
no comments required.
|
Routing - PLUMBING | 2/9/2017 | | 2/10/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 2/9/2017 | | 2/10/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 2/9/2017 | | 2/9/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/9/2017 | | 2/9/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 2/9/2017 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 2/8/2017 | | FAIL |
David Ferguson
|
|
|
Need proper naming convention on MEP sheets.
|
Application received | | | 2/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 7 2017 2:09PM
|