BLD-Ceiling Grid Inspection | 3/6/2017 | 3/7/2017 | 3/7/2017 | A | DONE |
Mike Jordan
|
|
|
Justin Phone #: ###-####
|
DOC - Permit Finaled | 3/7/2017 | 3/7/2017 | 3/7/2017 | P | PASS |
Mike Jordan
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/9/2017 | | DONE |
|
|
|
|
Intake Approval | | | 2/9/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/9/2017 | | DONE |
|
|
|
|
Plan assigned to (BLH)Brittany | 2/9/2017 | | 2/9/2017 | | DONE |
Brittany Hill
|
|
|
|
Routing - PLAN CHECK | 2/9/2017 | | 2/9/2017 | | PASS |
Brittany Hill
|
|
|
|
Permit Ready to Issue | | | 2/9/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/9/2017 | | DONE |
|
|
|
|
Application received | | | 2/8/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 8 2017 8:10AM
|
Intake Approval | | | 2/8/2017 | | FAIL |
|
|
|
Didn't have drawings up loaded. Needs to be 18x24 and rotated
|
First Notice | 3/7/2017 | 3/7/2017 | | | |
Mike Jordan
|
|
|
|