BLD-Final | 8/28/2017 | 8/28/2017 | 8/28/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
DOC - Permit Finaled | 8/28/2017 | 8/28/2017 | 8/28/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 7/20/2017 | 7/20/2017 | 7/20/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Framing/Rough-in | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman stair #2 sheer walls east and west ok
|
BLD-Framing/Rough-in | 7/16/2017 | 7/17/2017 | 7/17/2017 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman c/n posted/ ok to insulate
|
Plan Modification Accepted | | | 6/30/2017 | | DONE |
|
|
|
new manual j reports
|
Routing - MECHANICAL | 6/30/2017 | | 6/30/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j reports
|
BLD-Wall Bracing | 6/27/2017 | 6/28/2017 | 6/28/2017 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Wall Bracing | 6/27/2017 | 6/27/2017 | 6/27/2017 | P | DEFR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman out of time
|
BLD-Other | 5/23/2017 | 5/23/2017 | 5/23/2017 | P | PASS |
Jim Storey
|
|
|
Fire wall // Jason Phone #: ###-#### first floor ok
|
BLD-Foundation | 4/10/2017 | 4/11/2017 | 4/11/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 4/10/2017 | 4/10/2017 | 4/10/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Telephone call | | | 3/13/2017 | | DONE |
|
|
|
emailed Valerie with ACHD to see what fees if any need to be assessed for the duplex that is going in. There was a SFD that was demo'd
|
Issue PAID IN FULL permit | | | 3/13/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/13/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/10/2017 | | |
|
|
|
|
Plan assigned to (DAF) | 2/21/2017 | 2/21/2017 | 3/10/2017 | | DONE |
David Ferguson
|
|
|
due 3/10
|
Routing - Erosion and Sediment | 3/8/2017 | | 3/10/2017 | | PASS |
Andy J. Long
|
|
|
No changes to BMP selections on previously approved ESC plan, new ESC plan reflects some changes to duplex design and backyard patios.
|
1st review completed | | | 3/10/2017 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/10/2017 | | DONE |
|
|
|
***all requirments met
eed RP
|
Routing - PLAN CHECK | 2/13/2017 | | 3/10/2017 | | PASS |
David Ferguson
|
|
|
|
Routing PW Grading-Hillside | 3/8/2017 | | 3/8/2017 | | PASS |
Jason C. Taylor
|
|
|
No hillside requirements project is out of the hillside area. Subgrade only.
|
Routing - PLANNING | 3/6/2017 | | 3/6/2017 | | PASS |
Nicolette Womack
|
|
|
Only 5 unrelated occupants are allowed.
|
Routing - PLANNING | 2/13/2017 | | 2/23/2017 | | FAIL |
Sarah Schafer
|
|
|
The driveway layout was not per the approved plans in CAA17-00311 on plans dated January 9, 2017 per the approval letter. The driveway must be modified to meet ordinance requirements.
|
Plan assigned to (LEG) Tisha | 2/13/2017 | | 2/21/2017 | | DEFR |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | 2/13/2017 | | 2/16/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Route to Impact Fee Review | 2/13/2017 | 2/16/2017 | 2/15/2017 | | PASS |
Cindy M. Gould
|
|
|
Initial residential review of all new news permit requested for now.
|
Route to Impact Fee Review | 2/13/2017 | 2/16/2017 | 2/15/2017 | | PASS |
Cindy M. Gould
|
|
|
Initial residential review of all new news permit requested for now.
|
Route to Impact Fee Review | 2/13/2017 | 2/16/2017 | 2/15/2017 | | PASS |
Cindy M. Gould
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - MECHANICAL | 2/13/2017 | | 2/15/2017 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 2/13/2017 | | 2/15/2017 | | PASS |
Andy J. Long
|
|
|
BMPs. Inlet protection, construction entrance (on Boise Ave), 2 sand filled drainage windows protected with wattles, silt fence along perimeter of site, concrete washout, sand/gravel burlap bar or fiber wattle placed in the gutter flow line. Swales are around the sides and back of the property, sand/ gravel bags or fiber wattles are to be placed in the swale flow line.
|
Routing - FIRE | 2/13/2017 | 2/13/2017 | 2/14/2017 | | PASS |
Scott Arellano
|
|
|
Plans were reviewed for FD Access and hydrant availability.
|
Routing - Addressing | 2/13/2017 | | 2/13/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/13/2017 | | 2/13/2017 | | PASS |
Morgan Webb
|
|
|
CREDIT GIVEN FOR SFD DEMO.
|
Plans ACCEPTED BY PLAN TECH | | | 2/13/2017 | | DONE |
|
|
|
|
Intake Approval | | | 2/13/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/13/2017 | | DONE |
|
|
|
|
Application received | | | 2/8/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 8 2017 1:15PM
|