BLD-Final | 12/6/2017 | 12/7/2017 | 12/6/2017 | A | PASS |
Brandon Shaw
|
|
|
Rolo Phone #: ###-####
|
DOC - Permit Finaled | 12/6/2017 | 12/6/2017 | 12/6/2017 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 11/30/2017 | 11/30/2017 | 11/30/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
BLD-Other | 8/15/2017 | 8/16/2017 | 8/16/2017 | A | PASS |
Brandon Shaw
|
|
|
Rolo Phone #: ###-####
|
BLD-Energy code compliance | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | PASS |
Brandon Shaw
|
|
|
Rolo Phone #: ###-####
|
BLD-Framing/Rough-in | 7/28/2017 | 7/31/2017 | 7/31/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 7/24/2017 | 7/24/2017 | 7/24/2017 | P | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
BLD-Wall Bracing | 7/19/2017 | 7/19/2017 | 7/19/2017 | P | NR |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
BLD-Wall Bracing | 7/13/2017 | 7/13/2017 | 7/13/2017 | P | CANC |
Brandon Shaw
|
|
|
Rollo Phone #: ###-#### CANC PER ROLLO
|
BLD-Foundation | 5/31/2017 | 5/31/2017 | 5/31/2017 | P | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 5/26/2017 | 5/26/2017 | 5/26/2017 | P | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
OVERRIDE | | | 5/22/2017 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/22/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/22/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/22/2017 | | DONE |
|
|
|
DO NOT REISSUE PERMIT. PLAN MOD
|
Plan assigned to (CDM) | 5/12/2017 | 5/12/2017 | 5/19/2017 | | PASS |
Carl D Madsen
|
|
|
SFD Plan Mod
|
Routing - PLAN CHECK | 5/19/2017 | | 5/19/2017 | | PASS |
Carl D Madsen
|
|
|
|
Plan assigned to (AJS) | 5/10/2017 | 5/10/2017 | 5/12/2017 | | DEFR |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 5/10/2017 | | |
|
|
|
|
PubWorks Subgrade Approval | 4/20/2017 | 4/20/2017 | 4/20/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 4/13/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 3/17/2017 | | |
|
|
|
|
Routing - PLAN CHECK | 3/14/2017 | | 3/17/2017 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/17/2017 | | DONE |
|
|
|
met
|
Plan assigned to (LEG) Tisha | 2/13/2017 | | 3/17/2017 | | DONE |
Tisha Gallop
|
|
|
2nd review 3/13; 1st review 3/3; elevations, two beams
|
Plan resubmittals received | | | 3/14/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/8/2017 | | 3/13/2017 | | FAIL |
Tisha Gallop
|
|
|
revised engineering needed for girder truss added to plan on resubmittal.
|
Routing PW Grading-Hillside | 3/9/2017 | | 3/13/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Plan resubmittals received | | | 3/8/2017 | | DONE |
|
|
|
|
1st review completed | | | 3/3/2017 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 2/13/2017 | | 3/3/2017 | | FAIL |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | 2/13/2017 | | 2/21/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - MECHANICAL | 2/13/2017 | | 2/17/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/13/2017 | 2/16/2017 | 2/15/2017 | | PASS |
Cindy M. Gould
|
|
|
Initial residential review of all new news permit requested for now.
|
Routing - Erosion and Sediment | 2/13/2017 | | 2/15/2017 | | PASS |
Melissa Jannusch
|
|
|
BMPs: stilt fence along Hoot Owl. Stabilized construction entrance, concrete washout, staging area, inlet protection, waste control.
|
Routing - PLANNING | 2/13/2017 | | 2/14/2017 | | PASS |
Jeff Lowe
|
|
|
|
Routing - FIRE | 2/13/2017 | 2/13/2017 | 2/13/2017 | | PASS |
Scott Arellano
|
|
|
Plans were reviewed for FD Access, Hydrant availability and defensible space.
FD Subdivision Comments are under SUB15-00005
|
Plans ACCEPTED BY PLAN TECH | | | 2/13/2017 | | DONE |
|
|
|
|
Intake Approval | | | 2/13/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/13/2017 | | DONE |
|
|
|
|
Routing - Addressing | 2/13/2017 | | 2/13/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/13/2017 | | 2/13/2017 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 2/9/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 9 2017 3:04PM
|